Professional Documents
Culture Documents
DC Water 1st ST Tunnel Forum MTG 2014 04 24
DC Water 1st ST Tunnel Forum MTG 2014 04 24
GeorgeS.Hawkins,GeneralManager
Briefingon:
Construction Update and Focus on Noise, Vibration, and Air Monitoring / Controls
Briefingfor:
dcwater_template_art
Tunnel Forum
Representative
Dr. Marilyn Lashley Renee Peres Victoria Leonard Shelly Parker Joe Levesque Angela Ray Serita Sanders Chris Von Ferro Scott Roberts Mark Mueller Sherry Howard
Alternate
Tomas Encaracion TBD Pia Brown TBD TBD Theodore Bush John Salatti Harvey Hartfield Betsy McDaniel Teri Janine Quinn
Presentation Agenda
Construction Update Six-Week Look-Ahead and Street Activity Tunnel Forum Consensus Topics Noise and Vibration Control, and Air Quality Trees Protection of Structures Parking Next Steps
ConstructionUpdate
ScottHoffman,SkanskaJayDee(SKJD)
Construction Update
Main mining shaft activities/demo Schedule for freeze trench and Construction Staging Areas (CSAs) Rodent control Utility work Site office Instrumentation and monitoring Hotline testing and roll-out Special Needs Survey Noise, vibration, and air monitoring
MAY2014)
(OPENMAY2014)
(OPENMAY2014)
SixWeekLookAheadandStreetActivity
ScottHoffman,SkanskaJayDee(SKJD)
Channing St, late April mid May: Conduct surveys, perform rodent control applications, prepare site for slurry wall construction Adams St, mid May: Locate utilities V St: mid May: Locate and relocate utilities Bryant St, April mid May: Removed street light at Bryant and Second Streets, demo sidewalk along W St, paving and striping, install signs and curbs McMillan, early May: Utility coordination, install perimeter fence, site prep, paving and striping W St, late May: Lot demo and site prep; install temporary lighting, perimeter fencing, curb, and retaining walls 143 W St, mid May: Relocate and install fence, relocate parking bumpers, install signs
McMillan Stormwater Storage Project (MSSP) SKJD work at the main mining shaft
Starting in mid May, portions of the West Street alley will be closed for construction of the freeze trench at:
Channing Street mining shaft West side alley at Bryant Street south to Thomas Street
First and V Streets will be closed for construction (see next two pages for details)
Construction Staging Area: Site Prep and Construction Remove tree boxes on First Street at First and V Streets intersection Pave First Street up to existing sidewalks To maintain two-way traffic on First Street as required by DDOT
Construction Staging Area
10
11
TunnelForumConsensusTopics
TomLindberg,DCCleanRiversProject
12
McMillan Reservoir
13
Response to Eliminate No Turn on Red Street Sign at Bryant and First Streets NW
DC Water and DDOT considered the proposal to eliminate the No Turn on Red sign at the intersection of Bryant and First Streets NW DDOT determined:
There is no confusion between the existing No Turn on Red sign and the First Street Detour sign Northbound motorists making a right turn on Bryant St cannot see cars coming from the eastbound direction The No Turn on Red sign must remain for motorists benefit and safety
14
NoiseandVibrationControl,andAirQuality
Scott Hoffman, Skanska-Jay Dee (SKJD)
15
Evaluation of Issue at the Noise & Vibration Source Monitor Complaint Response
Dedicated noise and vibration specialist Detailed monitoring and control plans Restrictions on work hours near sensitive receptors Limits based on DCMR and DC Waters baseline readings Period real-time monitoring DDOT-approved haul routes
Best available control technologies Noise barriers Equipment alternatives Consolidated generators, compressors, and gas-powered looped freeze trench system Equipment maintenance and inspections
TBM support area Freeze plant location Fewer sensitive receptors South and east berms as noise barriers Power generators and compressors sited here Use utility trench to bring power, air, and freeze to CSAs
17
Sound Basics
Sound vs. noise
Sound is a mechanical wave that is an oscillation of pressure transmitted through a solid, liquid, or gas Noise is an unwanted sound; its intensity (loudness) is measured in decibels (dB) Sound Pressure Level (SPL) is the force of sound on a surface area SPL depends on the environment in which the source is located and the listeners distance from the source We hear or perceive sound pressure as loudness SPL is measured in decibels by a sound level meter
Sound Source
18
Sound Basics
Typical range of construction sound at 50 feet
Auger: 8083 dB(A) Concrete mixer: 85 dB(A) Air compressor: 8083 dB(A) Diesel generator: 8085 dB(A) Backhoe: 80 dB(A) Excavator: 85 dB(A) Crane: 83 dB(A) Pneumatic tools: 85 dB(A) Jackhammer: 110 dB(A)
19
Sound Basics
Various sound descriptors (not all noise is created equal)
Instantaneous noise level (Lp): Receivers noise at any moment in time; also known as instantaneous sound level Maximum/minimum noise level (Lmax/Lmin): Highest/lowest instantaneous noise level during a specified time period Equivalent noise level (Leq): Average acoustical energy over a given period of time
The sound pressure level fluctuates from about 60 dB(A) to almost 80 dB(A).
With every strike of the hammer, the noise level rises rapidly and then falls off equally rapidly.
20
Sound Basics
Noise math
Addition: Adding two equal noise sources results in a 3 dB increase 80 + 80 = 160 dBA 80 + 80 = 83 dBA Subtraction: Subtracting one noise source from two equal noise sources results in a 3 dB decrease 80 77 = 3 dBA 80 77 = 77 dBA
21
Vibration Basics
What is vibration?
P-Wave
Vibration is an oscillatory motion which can be described in terms of displacement, velocity, or acceleration In most cases, the response of humans, buildings, and equipment to vibration is more accurately and commonly described using velocity (inches/second) Expressed in in/sec or VdB Three vibration wave types: P, S, and R waves R wave (surface wave) is most difficult to control
S-Wave
R-Wave
22
Vibration Basics
Typical vibration levels of construction equipment at 25 feet
Hydromill: 0.017 in/sec Vibratory roller: 0.21 in/sec Dozer: 0.089 in/sec Auger: 0.090.1 in/sec Truck: 0.08 in/sec Crane: 0.1 in/sec Jackhammer: 0.035 in/sec
23
801
Source: 1) DC Municipal Regulations 2802, Construction 2) EDR noise limit accounts for 3 dBA + ambient 24
Mitigation Measures
Existing berm will remain Additional sound barrier 6 feet above berm Consideration of construction methods Portable sound barriers for specific equipment on-site 1 drill rig in operation at a time 1 loader operating in support of drilling Limited choice of heavy equipment during drill rig operations 2 cranes used during operations; additional heavy equipment use prohibited Limited work hours Case-by-case basis Limited heavy equipment use Use monitoring to determine extent of noise and vibration Limited work hours
25
MitigationsImplemented
FlaglerPlaceNW
26
MitigationsImplemented
27
MitigationsImplemented
28
Air Monitoring
Dust suppression required on-site Based on erosion and sediment plan, no visible dust to leave site Real-time dust monitoring Periodic monitoring especially during heavy earth-moving Real-time monitoring upwind and downwind
29
Evaluation of Issue at the Noise & Vibration Source Monitor Complaint Response
Trees
JohnKennedy,DCCleanRiversProject
RonDavis,DCCleanRiversProject
31
4 at Channing Street CSA 16 at Adams Street CSA 15 at First and V Streets CSA 6 on Thomas Street
DC Water and SKJD will work with DDOT and the Tunnel Forum Group prior to re-constructing each disturbed area Potential collaboration between DC Water and DDOT to plant trees in public right-of-way in the Bloomingdale area during construction DC Waters tree giveaway program can provide small trees to neighborhood residents
65 trees of varying diameter were removed from the Bloomingdale neighborhood earlier this year.
32
TREES ACNI Black Maple ACRU Red Maple ACSA Sugar Maple MAVI Sweetbay Magnolia PLHY London Planetree QUPH Willow Oak SHRUBS AZGP Pink Azalea GAJA Dwarf Gardenia GRASSES LIMJ Big Blue Lilyturf
Flagler Pl NW
33
TREES ACNI Black Maple ACRU Red Maple ACSA Sugar Maple MAVI Sweetbay Magnolia PLHY London Planetree QUPH Willow Oak SHRUBS AZGP Pink Azalea GAJA Dwarf Gardenia GRASSES LIMJ Big Blue Lilyturf
First St NW
34
V St NW New Tree New Planter Box Existing Tree Grass Lirope Muscari Big Blue 35
Grass Kentucky Bluegrass, Fescue, Red Top 36 Grass Lirope Muscari Big Blue
Thomas St NW
First St NW TREES CABE European Hornbeam GIBI Ginkgo Princeton Sentry (fruitless male version) LIST Gum PICH Chinese Pistache GRASSES LIMJ Big Blue Lilyturf 37
ProtectionofStructures
StephenNjoloma,DCCleanRiversProject
38
39
Parking
KevinPilong,DCCleanRiversProject
Stephen Njoloma,DCCleanRiversProject
40
41
42
McMillan Reservoir
43
Channing St NW
Bryant St NW
Bryant St (BS-APA) 56 spaces W St (WS-APA) 21 spaces 143 W St (143W-APA) 21 spaces For a total of 98 alternative parking spaces
BS-APA (56)
nt S Brya
t NW
Flagler St NW
W St NW
First St NW
Adams St NW
W St NW
2nd St NW
Construction Staging Areas are shown as ; these areas are closed to the public Contractor / private parking areas are shown as
V St NW
Elm St NW
First St NW
U St NW
Thomas St NW
de Rho
Old Maple St NW
Isla
nd A
ve
44
McMillan Reservoir
Each resident is assigned a specific APA tag number APA information package is being prepared for mailing
45
McMillan Reservoir
46
McMillan Reservoir
N
Loss of parking due to construction activities should be mitigated with APA implementation
Recommendation:
Continue alternate side of street parking with DPW street sweeping at this time (streets shown as ) Revisit the issue after APAs are implemented
47
Next Steps
DC Water and SKJD to coordinate with DDOT regarding 2-hour parking extension signage Possible new hours for our meetings: suggest changing from 6:308 PM to 78:30 PM to better accommodate your schedule Schedule next Tunnel Forum Meeting Thursday, May 22 or Thursday, May 29 (Memorial Day is Monday, May 26.) Topics:
APA roll-out Status of Construction Staging Areas Suggested topics
48