BP Relief Well Diagram - 13-JUN-2010
BP Relief Well Diagram - 13-JUN-2010
!CSG-36
!CSG-28 !CSG-36
!CSG-36
!CSG-28
!CSG-28
!CSG-22
PROGRESS
"#DDII - MC 252 #2
!CSG-22
"#Spudded well - May 16th !CSG-18
"#Set 36" casing at 5,471' !CSG-22
"#Set 28" casing at 6,614'
"#Set 22" casing at 8,576' !CSG-18
"#Currently drilling at 9,022' - 06/13/2010
!CSG-16
!CSG-18 PROGRESS
!CSG-16 !LNR-13 5/8 "#DDIII - MC 252 #3
!CSG-16 "#Spudded well - May 2nd
"#Set 36" casing at 5,494'
CSG-13 5/8" "#Set 28" casing at 6,730'
CSG-13 5/8" "#Set 22" casing at 8,762'
!LNR-11 7/8
"#Set 18" casing at 9,945'
LNR-11 7/8" "#Set 16" casing at 12,057'
!LNR-9 5/8 "#Set 13 5/8" casing at 13,869'
!Planned Intersection Depth: "#Present depth 13,973' - 06/13/2010
18,000 MD-RKB
CSG 7"
OVERVIEW !RESERVOIR
BP intends to drill two wells designed to intersect the
original wellbore above the oil reservoir. This will allow
heavy fluid to be pumped into the well which will stop the
flow of oil from the reservoir. Cement will then be pumped
down to permanently seal the well. 06/13/2010
RWD06132010V3