Foreword
H. A. MANN, Chairmen, National Harbours Board
To a City on an island, a bridge is a vital trafic artery. Montreal
Ho foekesl and the construction of Champlain Bride bas pro-
vided an additional efficient link with the developing communities
bn the South Shore of the St. Lawrence River, with the Eastern
Townships of Quobecand wih the bighvay network of the United
tates.
Champlain Bridge spans the St. Lawrence River, the historic
route of the explorers and fur traders. Tt also crosses the St.
Lawrence Seaway, the new waterway, which connects Montreal
‘with the vast Great Lakes system of this Continent. It is a bridge
of unusual design and one which called for the use of unique
construction methods,
‘AS Chairman of the National Harbours Board, the Agen
ponsible for the planning, construction and operation of Cham-
plain Bridge, I take a measure of pride in the finished structure,
My colleagues and 1 commend the efforts of the Board's Chief
Engineer, Mr. L. R. Stratton; the Port Manager, Montreal Harbour,
‘Mr. Guy Beaudet, and bis staff; the Consulting Engineer, Mr.
HLH. L- Pratley and bis Associates, Lalonde and Valois. We also
‘pay tribute to the many contractors and their work forces for the
{oil skill and devotion to duty which overcame countless obstacles
fand culminated in the construction of this bridge which stands
fas a monument to their labour. I feel tbat it is appropriate that
the tremendous effort which went into the construction of Cham-
plain Bridge should be commemorated in tangible form. In the
Production of this fine volume, "The Champlain Bridge”, Porcu-
pine Publications Limited bas performed this task admirably.
UsoA general description
‘The Champlain Bridge in Montreal, which opened to
traffic on June 28, 1962, is a $35,000,000 toll bridge
providing a sixlane 60 m.p.h. highway crossing of the
St, Lawrence River and the Seaway between Montreal
and the South Shore. At the date of opening the bridge
connected to Wellington Street on the Montreal side
and to the existing Highways No. 3 and No, 9B on
the South Shore. However, work is proceeding on two
additional controlled access approach roadways on
the Montreal side, also a South Shore Expressway, an
Eastern Townships Expressway, and a widened High-
‘way No. 9B, all three of which will link up with the
South Shore approaches to the bridge as shown on
diagram 1. Upon the completion of these projects the
‘bridge willfully realize its purpose to relieve the heavily
‘congested Jacques Cartier and Victoria Bridges and
provide a modern high-speed connection between
Montreal and the South Shore free of the delays often
experienced at peak travelling hours on the older
bridges.
In 1955 the Canadian Government began studies for a
bridge to be built through the Department of Trans-
port with the National Harbours Board acting 2s
‘by ROGER DORTON
agents. The National Harbours Board had previously
built the Jacques Cartier Bridge in Montreal, and at
this time owned and operated this bridge. The National
Harbours Board appointed Dr. P. L. Pratley of Mont-
real as Consulting Engineer for the design and super-
vision of construction of the mew bridge, and in 1958,
upon the death of his father, Mr. H. H. L. Pratley was
appointed to continue and complete the work. The
Consulting Engineer subsequently engaged as Associ-
ates, Mr. P. Ewart as Traffic Consultant, and Lalonde
‘and Valois for work on the Montreal approaches and
for supervision of concrete construction. National
Harbours Board staff were engaged in electrical work
and on the administration building. The site had been
established to cross from Montreal to the South Shore
via St. Paul Island, or Nuns’ Island, as this island
close to Verdun is more commonly known, hence the
proposed crossing was initially known as Nuns’ Island
Bridge. The Government gave the official name of
Champlain Bridge in 1958, after Sarsuel de Champlain,
the founder of Quebec.
‘A Technical Committee was set up by the National
Harbours Board on which the various municipalityand government departments concerned with the
bridge were represented. These included the Provincial
Roads Department, the St, Lawrence Seaway Authority,
Hydro-Quebec, the cities of Montreal and Verdun,
and the South Shore communities of LaPrairie, Pre-
ville, and Brossard. The Committee served as both a
source of information as to present and future require-
ments of the bridge and future development plans for
the area, as well as a means of keeping the interested
organizations informed as to progress on the bridge
and seeking their opinions and approval on layouts.
In 1956 borings were taken in the river, the proposed
bridge line was established in the field, preliminary
layouts were studied and discussed and land expropriae
tion procedures were started. The proposed location,
line, profiles and clearances were approved in 1957
enabling final designs and drawings to proceed. Pre-
liminary studies were based on four traffic lanes with
provision for future widening to six lanes, However,
traffic and cost studies and future development plans
for the area led to the immediate adoption of the full
sit-lane scheme in 1958. The basic bridge width pro-
vides two 37 ft. roadways in each direction separated by
@ concrete median divider.
The bridge exceeds four miles in length overall and for
convenience in reference and for calling tenders, the
bridge was split into eight sections, The adopted
bridge centreline, while running from Montreal to the
so-called South Shore, actually lies close to a West-
East line. Starting from Montreal, on the left side of
diagram 2, the bridge sections are as follows
Section 1. Montreal approaches west of Wellington
Street
Section 2. Approaches between Wellington Street
and the west bank of the St. Lawrence
River.
Section 3. Crossing of secondary river channel to
Nuns" Island
Section 4, Roadway and plaza on Nuns’ Island
Section 5. Main river crossing between Nuns’ Island
and the Seaway
Section 6. Crossing of the Seaway
Section 7. East approach structure
Section 8. Approach roadways on the South Shore,
Jn Section 1 the four-lane approaches run on open
sound beside the Canadian National Railway track.
An interchange at Atwater Avenue will provide access
to the Atwater Tunnel and hence to the downtown
area of the city of Montreal, as well as to La Vérendrye
Boulevard for the west end of the city. Section 1 was
not completed for the 1962 opening and is at present
under construction, A further spproach roadway in
Section 1 is being planned jointly by the National
Harbours Board and the City of Montreal to serve
the downtown area more directly. This four-lane
approach will be located north of the main bridge
centreline and will ink St, James Street and St. Antoine
Street directly to Section 2 of the bridge. In Section 2
the approach runs on embankment fill over the old
city dump, with two-lane roadways and overpasses
Providing access to Wellington Street in Verdua.
‘The bridge in Section 3 crosses the river at low level,
and in Section 4 cuts across the north end of Nuns!
Island on a low embankment. The plaza on the island
widens out to nine lanes in each direction at the auto-
matic toll collection booths. The administration build-
ing is located in the centre of the plaza at the toll booths,
from which National Harbours Board staff control the
bridge operation. The island was bought by Quebec
Homes and Mortgage Corporation from the religious
order whose buildings and farm occupied the island,
for which @ residential community of some 35,000
Persons is now planed as part of Verdun, The Cham-
Plain Bridge was designed considering this future
island development, and provision was made for
access roads from the bridge at the west side of the
island. A sidewalk is provided on the bridge between
Verdun and Nuns’ Island, this being the only section
where pedestrians are allowed. The island is subject
to extensive flooding in the winter and will require
diking before being developed for housing, The plaza
embankment was designed high enough to clear thefloodwaters before the island is diked, but at the same
time not obstruct the view from the island when it is
fully developed.
From the island the bridge climbs up a 0.85% grade
for the long crossing of LaPrairie Basin, Section 5,
bringing the bridge to a sufficient height in Section 6
to provide the required 120 ft. vertical clearance over
the Seaway Channel which rans close to the east bank
of the river, The 120 ft. clearance is maintained to the
‘underside of the steel main span for the full 300 ft
‘width of the Seaway Channel. Section 7 comes down
to the South Shore on a 3% grade, crossing Highway
No. 3 and joining the Section 8 embankment and
roadways.
‘Two-lane turn off roadways in Section 8 join the bridge
to Highway No. 3 to serve the expanding residential
area in Brossard. Highway No. 3 is the site of a pro-
posed sixlane South Shore Expressway, and when this
is constructed by the Province a full interchange will
be built for the bridge approaches. The main bridge
roadway has been extended beyond Section 8 by the
Provincial Roads Department to link up with an inter-
chaage at Highway No. 9B, as shown on diagram 1
‘Highway No. 9B leading to the United States is to be
‘widened to six lanes by the Province, which is also
planning an Eastern Townships Expressway to join
in at this Highway No. 9B interchange. When all these
South Shore roadway schemes are completed traffic
from the United States, the Eastern Townships, and
local traffic will all have direct high-speed access to
the Champlain Bridge.
‘The first of the many contracts for construction of the
bridge was let in 1957. Detailed descriptions by some
contractors of their particular sections of the work
appear in subsequent chapters. The main embank-
ment fill in Section 2 was placed early, under the
first contract, so that settlement of the poor dump
‘material on which it was placed would have a chance
to ocour before the paving had to be done. Excava-
tion for the Seaway Channel was being carried out
in 1957 and advantage was taken of the availability
cof good fill material from this excavation by letting
a contract for the main embankment fill in Section
8 at this time, The first structural contract was also
let in 1957 for the construction of the four main
span piers, Section 6, diagram 5. This contract was
awarded in advance so that the two piers inside
the Seaway dike could be constructed in the dry,
before the Seaway channel was flooded. All four piers
‘were founded on the Utica shale bedrock which ex-
tends the full width of the river. The shale has little
depth of overburden in Sections 5 and 6 but is over-
Jain with dense glacial till in Sections 3 and 7.
Early in 1958 a temporary causeway between Verdun
‘and Nuns’ Island was constructed crossing Section 3
close to the bridge centreline. This causeway was
required to provide access to Nuns’ Island for construc-
tion of Sections 4 and 5, and was also used for access
during the construction of the piers in Section 3. The
causeway was of rock fill construction, with pipe
culverts placed in it to permit the required flow of
water to take place in the secondary channel of the
river. When Section 3 was ready for traffic the cause-
‘way Was removed and the rock fill reused as permanent
fill material on other parts of the job. In the summer
of 1958 work started on the eleven piers and two
abutments for the 1,536 ft. river crossing of Section 3.
Excavation for the piers was carried out inside earth
fill cofferdams connecting to the temporary causeway.
All the substructure was founded on the shale bedrock
which required removal of about 10 ft. of the dense
glacial till overburden at most piers.
‘The major structural contracts were all let in the summer
of 1959. The largest single contract on the project was
for the construction of piers and superstructure for
8,096 ft. of bridge in Sections 5 and 7A awarded in
June for a price of $8,319,000. The low bid featured
forty-six prestressed concrete spans of approximately
176 ft. each supported on “T”-shaped piers founded
on the shale bedrock, diagram 4, This contract repre-
sented the largest application of prestressed concretein the country both in individual span length and
quantity of work, and is described in detail and fully
illustrated in the next chapter. The successful bid was
not only the lowest of twenty-eight received in pre-
stressed concrete, steel and reinforced concrete, but
also required the shortest time for completion, and
came at a time when prestressed concrete was sti
relatively new construction method in Canada. Each
span consists of seven precast beams 10 ft. deep at 12
ft. 234 in. centres with two intermediate diaphragms
and a transversely stressed slab. The beams were pre-
cast on Nuns’ Island for Section 5,,transported on
tracks and erected with a launching truss. The stressing
of the beams, diaphragms and deck was performed with
twelve-wire Freyssinet cables, The circular pier footings
were poured in the dry inside sheet pile cofferdams
and slipforms were used for the shaft construction.
‘The pier capping beams were poured in formwork
supported. by steel trusses sitting on the tops of the
pier shafts,
‘The work was scheduled so that all operations were
performed simultaneously with construction of foot-
ings, shafts, pier caps, beam placing, slab pouring and
transverse stressing all proceeding with an interval
of a few spans between each. At the peak period the
contractor was working at the rate of two completed
spans per week. Work progressed cast from Nuns’
Island toward Section 6, and when this was completed
the beam casting yard and the launching truss were
transferred to the South Shore and work proceeded
from Highway No. 3 west toward Section 6. The con-
tract was completed just over two years after the award,
even though work had to shut down during the winter
months.
‘The superstructure contract for Section 3 was awarded
in July 1959 for a prestressed concrete scheme of twelve
spans of 128 ft. each for a sum of $1,044,000. These
beams were also precast on Nuns’ Island and erected
with a launching truss advancing in a westerly direction
from the island. The beams are 7 ft. 2 in. deep placed
at 8 ft, 94 in, centres, and beams and diaphragms
were stressed with twelvewire Freyssinet cables. The
deck consists of a 63 in. thick reinforced concrete
slab placed on top of the beams and acting compositely
with them,
“The contract for the Section 6 steel superstructure and
reinforced concrete roadway slab was awarded in
‘October 1959 for a sum of $5,907,000. This contract was
for the main three-span cantilever unit crossing the
Seaway Channel and four 252 ft. simple truss flanking
spans, giving a total length of just over 2,500 ft. and a
‘weight of stesl of approximately 11,000 tons. The
282 ft. spans are deck trusses with four trusses spaced
fat 23 ft. 4 in, centres in each span. The cantilever
unit, diagram 5, is of through truss design to pro-
vide minimum depth of construction below road
level over the Seaway, and consists of three trusses
spaced at 43 ft. 6 in. centres. The anchor arms have
385 ft. 6 in, span and the central clear span of 706 ft.
9 in. is made up of two cantilever arms of 160 ft 74 i
‘and a suspended span of 385 ft. 6 in. The roadway
follows a parabolic vertical curve for the length of the
suspended span. The trusses are fixed at the two main
piers and the 9 in. temperature movement for the central
span is all taken up at a finger-type expansion joint at
the east end of the suspended span, The maximum truss
depth of 104 ft. occurs over the main piers, reducing to
35 ft atthe ends of the suspended span. The truss chords
have depths of up to 41 in. with a maximum cross-
sectional area of 221 sq. in. and a maximum design
load of 2,125 tons. Extensive use was made of high
strength low alloy steel in the more heavily loaded
truss members, The three-truss layout for the main
span is an unusual one, but showed considerable
in bracing and floor beam stecl compared to a more
usual two-truss layout for which these members would
hhave had to span over 80 ft. The outside trusses were
designed for the maximum stresses in the usual manner
but it was found that deformation considerations
governed the design of the centre truss. The centre
truss was proportioned so that corresponding panelpoints on all three trusses would have the same defiec-
tion both during erection and under final dead load.
‘The Seaway was open to shipping before erection of the
Section 6 superstructure started in July 1960. As false~
work and flosting equipment were not permitted in
the Seaway Channel for erection purposes, the central
span was erected by cantilevering out from the main
piers on each side and closing the steel in the centre,
using a top chord travelling crane to place the steel.
‘The anchor arms, which are outside the Seaway Channel,
‘were erected using falsework bents at three positions.
‘The travelling crane, of 35-ton capacity, had an adjust-
able working platform that could be kept Jevel as the
crane travelled along the chords of changing slope.
‘The three-truss scheme required a constant check on
truss alignments and relative deflections during erection,
and adjustments were made a5 required. The two
halves of the main span were closed using equipment
located at the ends of the cantilever arms, consisting
of band-operated wedges to move the bottom chords
and toggle mechanisms operated by bydraulic jacks
for the top chords. Operation of the wedges and toggles
enabled the closure panel points to be adjusted both
horizontally and vertically from both sides. The travel-
fing cranes were backed off the suspended span to
reduce the load on the adjusting equipment and the
span was closed and swung on September 25, 1961.
Placing of the 634 in. thick reinforced concrete road-
‘way slab did not commence until all the steel was erected
in the main span and was completed in June 1962.
A contract for the substructure and prestressed concrete
superstructure for a further four spans in Section 7
cast of Highway No, 3 was awarded in June 1960. These
spans were not included in the earlier Sections 5 and
7A contract as the location of the proposed Highway
No. 3 development was not established at this time.
Alternative prestressing methods were allowed in
bidding on the 172 ft. beam spans, and the contractor
elected to use “GTM” stranded cables instead of the
Freyssinet parallel wire cables shown on the tender
drawings. Of six contracts awarded for prestressed
concrete beams to date on Champlain Bridge this is the
only contract where Freyssinet cables were not used.
‘These spans, like those of Section 3, $ and 7A, were
designed on a grid analysis allowing for the actual
oad distribution through the diaphragms instead of
applying the factors found in standard specifications
which would have given a less economic design, There
are five intermediate diaphragms and a slab designed
by the ultimate load theory, all transversely stressed.
‘The spans are at relatively Jow level above the ground
and the beams were poured in steel forms supported
on tubular steel scaffolding.
In Section 2, a four-span prestressed concrete overpass,
1 three-span prestressed concrete overpass, and two
reinforced concrete “W”-leg overpasses, completed the
‘bridge structures required for the 1962 opening. All four
of these structures are supported on steel Hcpiles driven
through variable dump material to bedrock. The pre-
stressed beams were precast and placed on bearing pads
‘on the piers. Natural rubber bearing pads were used om
the four-span overpass and on, the three-span overpass,
‘whereas laminated neoprene bearing pads were used
throughout Sections 3, 5 and 7. One of the “V"-leg.
overpasses was poured on a ground slab then excavated
after completion of the frame structure.
‘The remaining contracts for roadways, lighting, build~
ings, toll booths and signs were let in 1961 and 1962.
Separate road contracts were let for work in Sections
2, 4 and 8, and these contracts included asphalting
‘the concrete deck of the structures in Section 3, 5 and 7
respectively. The decks of the prestressed concrete
spans in Sections $ and 7 were waterproofed prior to
asphalting to give added protection, as the deck forms
fan integral part of the main load carrying beams and
thus cannot be replaced if damaged. As an added
safeguard against structural damage, salt, and other
chemicals will not be used to melt snow on the
bridge. The permanent roadways on fill have 2 9 in.
thick reinforced concrete slab covered with an asphalt