Professional Documents
Culture Documents
Power Plant Management
Power Plant Management
Power Plant Management
( )
..2000
, ,
. . 70000 . (02)
4368815 E-Mail anoor@it.egat.or.th
1.1
Content
1.1 Forward
Content
2.1 Plant Overview
2.2 Major Component
2.2.1 Thermal Power Plant Major Equipment
2.2.2 Combined Cycle Power Plant Major Equipment
2.2.3 The Basic of Gas Turbine & Combined Cycle Operation
2.3 Plant Control System
2.3.1 Automatic Boiler Control for Power Plant
2.3.2 Turbine Control
2.3.3 Generator and Exciter
2.3.4 Generator Protection
2.3.5 Transformer Protection
2.4 Station Commissioning
2.5 Plant Operation
2.5.1 Gas Turbine Protection
2.5.1.1 Steam Turbine Protection
2.5.1.2 Heat Recovery Steam Generation (HRSG)
2.6 Plant Maintenance
2.7 Plant Performance
2.7.1 Combined Cycle Power Plant Performance
2.8 Plant Management
2.8.1 Project Management
2.8.2 Safety/Loss
2.8.3 Finance
2.8.4 Human Resource
Index
1.1
2.1-1 to 2.1-9
2.2.1-1 to 2.2.1-54
2.2.2-1 to 2.2.2-35
2.2.3-1 to 2.2.3-33
2.3-1 to 2.3-11
2.3.1-1 to 2.3.1-25
2.3.2-1 to 2.3.2-31
2.3.3-1 to 2.3.3-13
2.3.4-1 to 2.3.4-30
2.3.5-1 to 2.3.5-17
2.4-1 to 2.4-27
2.5-1 to 2.5-8
2.5.1-1 to 2.5.1-19
2.5.1.1-1 to 2.5.1.1-12
2.5.1.2-1 to 2.5.1.2-7
2.6-1 to 2.6-40
2.7-1 to 2.7-34
2.7.1-1 to 2.7.1-20
2.8.1-1 to 2.8.1-5
2.8.2-1 to 2.8.2-9
2.8.3-1 to 2.8.3-24
2.8.4-1 to 2.8.4-29
2.1 - 1
1)
(Peak demand)
09.00 15.00 . 18.00 22.00 .
(Continuous process)
,
90% 45 95%
98%
30 60%
..........
?
1. (Operator)
2. (Maintenance)
3. (Administration)
2.1 - 2
3 Operation 50%
30% 20%
2.1 - 3
2.1 - 4
1)
(Availability)
2)
2 ? 3
(Spare Parts)
120
35 2547
O&m . .
Asset Manager (OWNER) OPERATOR (O&M)
O&M
Product NON STOP NO STOCK WITH
QUALITY (Availability &
Efficiency)
2.1 - 5
()
?
Management Steering Team
Steering Team
(Ground Root) Air Root ?
( . )
/ (
) (JOB DESCRIPTION) /
( ....)
2.1 - 6
()
()
Operation & Maintenance
Operation Operation & Maintenance
(Maintenance
&Process Engineer )
/
(KMKnowledge Management)
2.1 - 7
2.1 - 8
2.1 - 9
1 1 1
A B C
2.2.1 - 1
10
2.2.1 - 2
1 3
Critical Pressure 3208.2 psia
705.47 F Critical Temperature
2.2.1 - 3
2.2.1 - 4
2.2.1 - 5
AVT 10
Chemical cleaning
1.1.2 Clean Up, Light
Off, Steam Admission to Turbine, Initial Synchronize
(Load) 2 (Mode)
1. Wet Mode 25 % Economic Continuous
Rating ( ECR) Drum Type Boiler 25 % ECR
2.2.1 - 6
1 6 Wet Mode
2.2.1 - 7
1 7 Dry Mode
2.2.1 - 8
Quantity
Mitsubishi Supercritical
Sliding Pressure Operation
Once Through Boiler (Mo-SSRR)
1 Boiler
OIL/GAS
Steam Pressure
Design
Superheater Outlet
Design
Reheater Inlet
Reheater Outlet
Steam Temperature
Design
Superheater Outlet
Design
Reheater Outlet
Feed Water Temperature
Economizer Inlet
Air Temperature
Ambient Air Temperature
Steam Flow
Superheater outlet
Reheater Inlet
279 barg
261.0 barg
67 barg
52.7/52.8 barg
50.7/50.8 barg
548
540
582
568
C
C
C
C
294.2 C
27.5 C
2,530,000 kg/H
1,998,600/2,004,390 kg/H
2.2.1 - 9
Firing System
Drafting System
Steam Temperature Control Method
Superheater
Reheater
Steam Temperature Control Range
Superheater
Reheater
2.2.1 - 10
2.2.1 - 11
2. (Steam Turbine)
(Mechanical Machine) (Mechanical
Energy) (Torque) (Heat Energy)
(Kinetic
Energy)
(Primover)
2.1 (Principle of Steam Turbine) 2
(Casing and Stationary Blade)
(Rotor and Moving Brade) (Bearing)
2 - 1
2 1
2 1 3 3 Stage HP Turbine , IP Turbine LP Turbine
(Governor Valve)
2.2.1 - 12
2.2.1 - 13
2.2.1 - 14
2.2.1 - 15
2 4 Root
3. Caulking Piece Root Blade Rotor
2 - 5
2 5 Blade Blade
4. Shroud Blade (Vibration)
Blade Blade 2 - 5
5. Tenon Shroud Blade Revet 2 - 5
6. Lashing Wire Blade Blade LP
Turbine
2.2.1 - 16
2 6 Nozzle Block
2. Interstage Nozzle Blade (Stationary Blade)
Rotating Blade Rotating Blade
Interstage Nozzle 2 (Upper Half)
(Lower Half)
2.3.4 Diaphragm and Blade Ring Stationary Blade Diaphragm
Stationary Blade Ring Stationary 1 Blade Ring
Casing 2 7
2.2.1 - 17
2.2.1 - 18
2.2.1 - 19
2 11 Steam Chest
2.3.9 Stub Shaft HP Rotor
Turbine
1. Governor Impeller
2. Main Oil Pump Impeller
3. Mechanic Overspeed Trip Weight
2.3.10 Coupling
Turbine Generator
2.3.11 Turning Gear Turbine Rotor
1. Turbine Rotor (Inertia) Rotor
2.2.1 - 20
2.2.1 - 21
2 13 Journal Bearing
2. Thrust bearing
Clearance Turbine Generator
(Thrust Force) (Axial Direction)
2 14 Thrust Bearing 1 Flexible Coupling
2 14 Thrust Bearing
2.2.1 - 22
Bearing Turbine Generator 2 15
2.2.1 - 23
2.2.1 - 24
3. (Generator)
(Cooling System)
Cooling Medium 100
MW , Windage Lost H2 Cooling
Medium Cooling Rotor Stator H2
High Speed Hydrogen Inner Cooled Turbine Generator
100 600 MW Cooling
Stator Coil 1,000 MW
Air, H2 Water
2.2.1 - 25
Properties
Density
Thermal Conductivity
Heat transfer coefficient from
Surface to gas
Specific heat
Support of Combustion
Oxidizing agen
Air
1.00
1.00
Hydrogen
0.07
7.00
Water
860
23
1.00
1.00
Yes
Yes
1.35
0.98
No
No
514
3575
No
No
Air H2
Sine Curve Air + H2 5% () 70%
30 35% 70% H2
Air H2 Air Air H2 Co2
H2 control Exhaust Pressure 0.1 0.2 kg/cm2
3.1 ( Principle of Generator )
(Generator) (Michael Faraday)
(Induced Voltage) (Load)
2
Rotor Winding (Excite) Exciter
Stator Winding 3 1
2.2.1 - 26
3 1 Generator
(Rotating Machine)
(Mechanical Energy) (Shalf)
(Mechanical Power) (Turbine)
3.2 (Technical Data)
SERIAL NUMBER
97 AD 3301/97/AD3401
TYPE OF GENERATOR
HORIZONTALLY MOUNTED CYLINDRICAL ROTOR
ROTATING FIELD TYPE
ROTATING SPEED (rpm)
3,000
No. OF PHASE
3
No. OF POLE
2
FREQUENCY
(Hz)
50
VOLTAGE
(V)
24,000
HYDROGEN GAS PRESSURE (bar (g))
5
HYDROGEN GAS PURITY( (%)
97
2.2.1 - 27
9
990,000
841,500
23,816
83 (LAGGING)
WATER COOLED
HYDOROGEN COOLED
F
50 (BASE TEMP 50 C)
50 (BASE TEMP 50 C)
2.2.1 - 28
2.2.1 - 29
2.2.1 - 30
2.2.1 - 31
3 6 Stator Frame
3.3.6 Stator Lamination Stator Core High Quality Silicon Steel Plates Core
Loss Varnish Stator Frame
3 - 7
3 7 Stator Lamination
2.2.1 - 32
2.2.1 - 33
3 9 Flexible Support
3.3.9 Stator Coil Stator Coil Hollow Wire 4 Solid Wire
Cooling Effect Generator
Vortex Loss Cooling Water Hollow Element Rising Temperature
Generate Stator Coil
3 - 10
2.2.1 - 34
3 10 Stator Coil
3.3.10 Dialastic Insulation
(1) Having been impregnated with solventless, heatcuring epoxy resin (diaresin), the
mica tape is thoroughly filled with resin to the extent that no void is lift.
(2) Since diaresin is epoxy resin, it can withstand high voltage.
(3) Because of high tensile strength, elasticity and coefficient of expansion approximate
that of copper, it can be from cracks resulting from the expansion and contraction
of the conductor due to long time operation.
(4) Moisture proof, chemical proof and oil proof.
(5) Since tan is small, the increase or decrease of tan due to changes of
temperatures and voltage is also negligible.
(6) Thermally stable, long life is assured.
2.2.1 - 35
3 11 Dialastic Insulation
3.3.11 Stator Coil Header Part Header Of branching Cooling Water Hollow Wire
Header Cap Hose Joint Element Wire Leak Water
Hose Joint Manifold Non Magnetic Steel 3 - 12
2.2.1 - 36
3.3.12 Support of Stator Coil End Part Coil End Part ( Electromagnetic Force
Short Circuit ) Integral Structure Large Size Resin Cone Segment
Plate Insulation Bolts Axial Direction Slide Mechanism
Absorbing Heat of Expansion Stator Coil Stator Core 3 - 13
2.2.1 - 37
2.2.1 - 38
3 15 Bushing
3.3.15 Rotor Shaft Shaft Material Solid Forging of Ni Cr Mo V Steel
Slots Hold Rotor Coil Trapezoids
Pole Uniform Rigidly Crescent Shapely Supersonic Test
Rotor Coil 3 - 16
2.2.1 - 39
3 16 Rotor Shaft
3.3.16 Rotor Coil Coil Worked Sliver Bearing Capper U 2
H2 3 - 17
2.2.1 - 40
3 17 Rotor Coil
3.3.17 Coil Retaining Ring End Coil Rotor Deformation
Coil Retaining Ring Fix Tangent Axial Non Magnetic
Austenite Steel 3 - 18
2.2.1 - 41
3 19 Blower
2.2.1 - 42
3 20 Bearing
3.3.20 Bearing Bracket Bearing Bracket Weided Construction Fixed Stator
Frame Turbine Excite 2 Mechanical Strength Rib Rib
Bearing Bracket Bearing Gland Sealing Oil Seal 3 21
2.2.1 - 43
3 21 Bearing Bracket
3.3.21 Protection For Shaft Current Shaft Current Bearing Bracket Insulated
Insulation Sheet Shaft Current
Insulation Excited Coupling Gland Seal Bracket Bearing Bracket
Gland Seal Oil Piping Oil Seal Bracket 3 22
2.2.1 - 44
3 23 Gland Seal
3.3.23 Slip Ring Slip Ring Tool Steel Brush
Slip Ring High Pressure Air
3 - 24
2.2.1 - 45
3 24 Slip ring
3.3.24 Brush And Holder ( Brush ) Magazine Type Brush Holder
Normally Pressure Set 120 g/cm2 3 - 25
2.2.1 - 46
3 26 Gas Cooler
2.2.1 - 47
( Thermal Power Plant Major Equipment )
= psia
= . BTU / lb
2. Once Through Boiler High Pressure Drum...
.......................
..............................
3. Phosphate Feed Water Once Through Boiler
.......................
.......................
.......................
4. Once Through
.............................................................................................................................................
........
.......
.......
.......
.......
.......
.......
5. Once Through Boiler Load (Mode)
.......
.......
.......
.......
.......
.......
2.2.1 - 48
6.
. Force Draft Fan .
.......
.......
. Induce Draft Fan .
.......
.......
. Soot Blower ..
.......
.......
. Superheater ..
.......
.......
. Reheater
.......
.......
7. ............................................................
.......
.......
.......
.......
.......
.......
.......
8. (Steam Turbine) .....................................................................
.......................
.......................
.......................
.......................
.......................
.......................
2.2.1 - 49
9.
. Rotor .
.......
.......
. Blade
.......
.......
. Nozzle
.......
.......
. Labyrinth Seal
.......
.......
. Gland Seal .
.......
.......
. Casing .
.......
.......
. Steam Chest ..
.......
.......
10. Steam Valve ..................................................
.......
.......
.......
.......
.......
.......
.......
.......
.......
2.2.1 - 50
2.2.1 - 53
1. Instruction Manual Mitsubishi
- Boiler
- Turbine
- Generator
2. .
- Once Through Boiler
- Supercritical Pressure Boiler
- Steam Turbine Component
- Basic of Power Plant
- Lube Oil System
2.2.1 - 54
2.2.2 - 1
GAS TURBINE
HEAT RECOVERY STEAM GENERATOR (HRSG)
STEAM TURBINE
GENERATOR
1
GAS TURBINE
GAS TURBINE
GAS TURBINE GENERATOR ROTOR
GAS TURBINE COMPRESSOR (COMBUSTION
CHAMBER) 18 CHAMBERS FUEL NOZZLE
(SPARK PLUGS) COMBUSTION ZONE
HOT GASES
COMBUSTION CHAMBER TRANSITION PIECES AFT. END
COMBUSTION CHAMBER LINERS HOT GASES TURBINE SECTION
TURBINE TURBINE GENERATOR ROTOR
GAS TURBINE
1. COMPRESSOR SECTION
2. COMBUSTION SYSTEM
3. GAS TURBINE SECTION
1. COMPRESSOR SECTION
SPECIFICATION
TYPE
NUMBER OF STAGE
MATERIAL
INLET CASING
COMPRESSOR CASING
COMPRESSOR DISCHARGE CASING
AXIAL FLOW
18 ( STAGE 0 STAGE 17 )
DUCTILE IRON
DUCTILE IRON
2.1/4 Cr-Mo
2.2.2 - 2
1 1 COMPRESSOR ROTOR
2.2.2 - 3
2.2.2 - 4
2.2.2 - 6
2. COMBUSTION SYSTEM
SPECIFICATION
TYPE
18 CHAMBER, REVERSE FLOW
NUMBER AND TYPE OF IGNITORS
2 ELECTRONIC
NUMBER AND TYPE OF FLAME DETECTORS 4 ULTRA VIOLET
DESCRIPTION OF NOZZLE
DLN 2+ DUAL WITH WATER INJECTION
TRANSITION PIECE (MAT.)
NIMONIC 263
LINER
HASTELLOY-X/HS-188
COMBUSTION SYSTEM CAN-ANNULAR, REVERSE-FLOW 1-5
COMPERSSOR DISCHARGE AIR TRANSITION PIECE ( INLET AIR
180 HOT GASES ) COOLING
COMBUSTION LINER COMBUSTION LINER
REACTION ZONE
2.2.2 - 7
COMBUSTION SYSTEM
2.1 FUEL NOZZLES
18 NOZZLES
2.2 SPARK PLUG
2
2.3 FLAME DETECTOR
4
2.4 CROSS FIRE TUBES
18
2.5 OUTER COMBUSTION CHAMBER AND FLOW SLREVE
2.6 FUEL NOZZLE END COVER
2.7 CAP AND COMBUSTION LINER
2.8 TRANSITION PLECE
1-6
2.2.2 - 8
2.2.2 - 9
SPECIFICATION
GAS TURBINE
MODEL NO.
SHAFT SPEED
CRITICAL SPEED
OVER SPEED TRIP
TURBINE
NUMBER OF STAGE
MATERIAL
ROTOR AND CASING
COATING MATERIALS
TURBINE WHEEL
FIRST STAGE BUCKET
SECOND STAGE BUCKET
THIRD STAGE BUCKET
FIRST STAGE NOZZLE
SECOND STAGE NOZZLE
THIRD STAGE NOZZLE
MS 9001FA +
3000 RPM.
2059 / 2897 RPM.
3300 RPM.
3
S1-S3GTD-111 DOVETAIL FIT
S1-S3GT33 INT S3 Cr COATING
IN-706 (NICKEL-BASE ALLOY)
GTU-111DS
GTU-111DS
GTU-111DS
FSX-414
GTD-222
GTD-222
2.2.2 - 10
2.2.2 - 11
2.2.2 - 12
2.2.2 - 13
2.2.2 - 14
2.2.2 - 15
2.2.2 - 16
2
HEAT RECOVERY STEAM GENERATOR (HRSG)
HRSG. (HEAT ENERGY)
(EXHAUST GAS) GAS TURBINE
(STEAM TURBINE) GENERATOR
HRSG. (CONVECTION) GAS
TO WATER HEAT EXCHANGER HEAT
EXCHANGER 3 SECTIION
1. ECONOMIZER SECTION SENSIBLE HEAT
(SATURATED WATER)
2. EVAPORATOR SECTION SENSIBLE HEAT
LATENT HEAT
(WET STEAM)
3. SUPERHEATER SECTION SENSIBLE
HEAT (SUPERHEAT STEAM)
SPECIFICATION
1. OPERATION POINT
GAS TURINE OPERATING NUMBER
2
GAS TURBINE LOAD
BASE LOAD
AMBIENT TEMPERATURE
27.8 C
RELATING HUMIDITY
75%
GAS TURBINE FUEL
NATURAL GAS
2. GAS TURBINE EXHAUST GAS AT HRSG INLET
FLUE GAS INLET FLOW
2,722.88 T/hr.
FLUE GAS INLET TEMPERATURE
617 C
FLUE GAS INLET PRESSURE
0.0789 BARG.
FLUE GAS INLET ENTHALPY
692.4 KJ/Kg.
FLUE GAS INLET VELOCITY
11.5 M/S.
3. MAXIMUM TEMPERATURE DESIGN
- HP. SECTION
600 C.
- REHEAT SECTION
590 C.
2.2.2 - 17
- IP SECTION
- LP. SECTION
4. FLUE GAS TEMPERATURE CONDITION
- HP/IP/LP ECONOMIZER INLET
- HP/IP/LP EVAPORATOR INLET
- HP/IP/LP SUPERHEATER INLET
- REHEAT
- CONDENSATE PREHEAT
- HP/IP/LP ECONOMIZER OUTLET
- HP/IP/LP EVAPORATOR OUTLET
- REHEAT
- CONDENSATE PREHEAT
5. CONDENSATE CONDITION
- CONDENSATE FLOW INLET
- CONDENSATE TEMPERATURE INLET
- CONDENSATE PRESSURE INLET
- CONDENSATE TEMPERATURE OUTLET
- CONDENSATE PRESSURE OUTLET
6. HRSG. PERFORMANCE
HP STEAM AT SUPERHEATER OUTLET
- FLOW
- PRESSURE
- TEMPERATURE
REHEAT AT SUPERHEATER OUTLET
- FLOW
- PRESSURE
- TEMPERATURE
REHEAT AT SUPERHEATER INLET
- FLOW
- PRESSURE
- TEMPERATURE
2.2.2 - 18
370 C.
300 C.
335/237/NA. C.
463/271/144 C.
617/340/273 C.
595 C.
143 C.
143/237/171 C.
340/237/171 C.
532 C.
100 C.
387,050 Kg/hr.
44.6 .C
10 BARG.
109.1 C.
6.9 BARG.
270.22 T/hr.
129.3 BARG.
567.9 C.
308.52 T/hr.
24.95 BARG.
505.3 C.
308.52 T/hr.
25.78 BARG.
325.4 C.
44.98 T/hr.
26.62 BARG.
327.8 C.
26.71 T/hr.
6.58 BARG.
264 C.
87.1 %
5/15/40
7/9/7 C.
5/5/3 C.
1539X106 kJ/hr.
333.3/228.2/164.2 C.
117.2/119.4/NA. C.
333.3/228.2/ 164.2 C.
328.3/223.2/NA C.
333.3/228.2/164.2 C.
567.4/327.8/264 C.
HRSG.
2.1 INLET DUCT EXHAUST GAS
HRSG FULL AREA SURFACE HIGH TEMPERATURE GAS
ZONE DIVERTER DAMPER GAS TURBINE
2.2 HRSG FOUNDATION HRSG ANCHOR BOLT
SOLE PLATE
2.3 HRSG BASE FRAME HRSG
HRSG. CASING BASE FRAME HRSG BASE FRAME SELFSTANDING TYPE
2.2.2 - 19
2.2.2 - 20
2.2.2 - 22
2.2.2 - 23
3
STEAM TURBINE
STEAM TURBINE (KINETIC ENERGY)
(ROTATING MECHANICAL ENERGY) STEAM HRSG. TURBINE
BLADE TURBINE
TURBINE BLADE 2 IMPULSE
BLADE REACTION BLADE
SPECIFICATION
STEAM TURBINE
MANUFACTURE / COUNTRY
TYPE AND CYLINDER ARRANGEMENT
2.2.2 - 24
NUMBER
NUMBER
NUMBER
NUMBER
NUMBER
2.2.2 - 25
2.2.2 - 26
2.2.2 - 27
3.2.2 LP. TURBINE ROTOR LP. JOURNAL BEARING NO.3 NO.4 ROTOR
3-4
3-4 LP.
TURBINE ROTOR
2.2.2 - 28
2.2.2 - 29
4
GENERATOR
GENERATOR (ROTATING MECHANICAL ENERGY)
(ELECTRICAL ENERGY) GENERATOR DC
GENERATOR ROTOR DC (MAGNETIC FIELD) ROTOR
ROTOR ROTOR STATIONARY COIL
INDUCED AC. VOLTAGE CURRENT STATIONARY COIL
SPECIFICATION
GENERATOR
LEADING SPECIFICATION OF GENERATOR
Type
Totally enclosed, self-ventilated, forced
Lubricated, hydrogen cooled, cylindrical rotor
Type, synchronous alternator.
Capacity
325,000kVA
Terminal voltage
18.0 kV 5%
Power factor
0.85 lagging
Hydrogen pressure
4.14 barg
Short circuit ratio
Approx. 0.50
Cycles
50 Hz
No. of poles
2
No. of phases
3
Speed
3,000 rpm
Cooling method ;
Stator winding : Indirectly Hydrogen Cooled
Rotor winding : Directly Hydrogen Cooled
Insulation Class
Stator winding : F
Rotor winding : F
Unbalance load capability
Continuous (I2)
8%
Short time (I2 2t) 10 (tmax
120 Sec.)
2.2.2 - 30
2.2.2 - 31
(PORCELIAN
INSULATION) PLATED TERMINAL
4.6 GENERATOR COOLER 4 FRAME
COOLER SEAL GENERATOR FRAME COOLER TUBE
SHEET COOLER
4.7 STATOR VENTILATION ARMATURE CORE ROTOR
FAN
ARMATURE CORE OUTER WRAPPER PLATE
THERMAL STRESS OVERHEAT
4.9 COLLECTOR RING AND CONNECTING PART WITH THE FIELD WINDING
COLLECTOR RING FIELD WINDING
2.2.2 - 33
2.2.2 - 34
2.2.2 - 35
2.2.3 - 1
(Plant Operation)
(The Function of the Power Plant)
2.2.3 - 2
Power System
Tie Lines
(Alternating Current)
Batteries
,
24
(Peak Demand)
Emergency Condition
3
Loss of Flame Combustion
System
(Periodic) System Indicator
Recorders
System
Equipment
General Emergency Action
3
1.
2.
3.
Instrument
Enunciator, Alarm Alarm Plant System
(Level, Pressure, Temperature ) (Set point)
Alarm Ring Enunciator Windows Control Room Alarm
Operator
Alarm
Indicator Support System
()
2.2.3 - 4
2.2.3 - 5
(Energy Conversion)
-Gas/Oil/Coal/Uranium
CHEMICAL
TO
THERMAL
THERMAL
TO
MECHANC
MECHANICAL
TO
ELECTRICAL
(Heat Engine)
Combustion Engine (Fossil, Fuel)
Nuclear Reactor
Solar Energy
Geothermal Energy
Combustion Engine 2
1. External Combustion Engine
Working Fluid
Boiler Steam Turbine
2. Internal Combustion Engine
Working Fluid
2 4
, ,,
Gas Turbine
-Compressor
-Combustion Chamber ()
2.2.3 - 6
-Turbine
Turbine Blade Impulse Turbine
Gas Turbine Brayton Cycle Constant Pressure
Cycle Turbine
(Steady Flow Cycle)
-Stage 1-2 Compression of Air in
COMPRESSOR
-Stage 2-3 Heat Added at Const.
Press. in COMBUSTOR
-Stage 3-4 Expansion though GAS
TURBINE
-Stage 4-1 Exhaust to Atmosphere
-Adiabatic Compression &
Expansion
2.2.3 - 7
Two Shaft
Power Generation
Simple Cycle
Mechanical Drive
Heavy Duty Type
Single-Shaft
Power Generation
Simple Cycle
Regenerative
Cycle
Combined
Cycle
Two Shaft
Mechanical Drive
Simple Cycle
Regenerative
Cycle
2.2.3 - 8
Single Shaft
Peak Load Operation (Peak Load Demand)
Start Up Shutdown
Gas Turbine
Standby (Emergency) Operation
Start up
(Black Out) Gas Turbine Black Start Operation
600-1000 MW Gas Turbine 20 MW Standby Gas Turbine
Start (Starting Mean) Gas Turbine
Start Electric Motor
Gas Turbine
Standby Emergency Diesel
Generator Electric Motor Start up Gas Turbine
Start up
Single Shaft Gas Turbine (Simple Cycle)
Compressor Turbine Turbine Compressor AC
Generator (Load) Compressor
AC Generator (Frequency)
60% Turbine
Exhaust Gas Temp .
Out put Gas Turbine
Combustor Compressor Exhaust Gas
Output
Inlet Guide Vane Compressor Stage
Inlet Guide Vane Exhaust Gas Temp
Output Load (Partial Load Efficiency)
2.2.3 - 9
2.2.3 - 10
HP Turbine Compressor
Power Turbine HP Turbine 5000-6000 RPM
Compressor HP Turbine Shaft Combustor Gas
Generator Hot Gas LP Turbine Gas Turbine GE
Gas Generator Power Turbine Casing
Single Shaft Air Craft Engine Gas
Generator Power Turbine Gas Generator 1 4
Power Turbine Gas Turbine AVON, OLYMPUS ROLLS-ROYCE
LIMITED General Electric MS 5002, MS 7002
Two Shaft Gas Turbine AC Generator Speeds Power Turbine
Gas Generator Output Power
Turbine Power Compressor Single Shaft
Load Single Shaft Centrifugal Compressor, Pump
Speeds Power Turbine Flow Rate Centrifugal Compressor, Pump
Inlet Vane (nozzle) HP Turbine Power Turbine Gas Generator
Mass Flow HP Turbine Output
Single Shaft Turbine Inlet
Temp 10%, Output 25% 25% Output 60%
2.2.3 - 11
Regenerative Cycle
Regenerative Cycle Gas Turbine
Turbine Inlet Temperature Hot Gas Part
( Combustor ,Turbine Blade) Regenerative Cycle Single Shaft Two
Shaft Gas Turbine Heat Exchanger Cycle
75% Exhaust Gas Compressor Combustor
Exhaust Gas 450 oC 260 oC
Compressor 230 oC 400 oC 20%
25% Regenerative Cycle
Gas Turbine Peak Load, Standby
Regenerative Heat Exchanger (
Regenerator) Pressure Loser Exhaust Gas
2.2.3 - 12
2.2.3 - 13
Gas Turbine
Turbine Inlet Temperature
Regenerative Cycle
Inter Cooling Reheating Cycle Regenerative Cycle
Combined Cycle Operation
2.2.3 - 14
Boiler 2
Exhaust Gas Gas Turbine
Boiler Unfired Waste Heat Boiler
2.2.3 - 15
Gas Turbine
Exhaust Gas Bypass Stack Waste Heat Boiler
Waste Heat Boiler Steam Turbine Gas Turbine
(Conventional Thermal Plant)
Gas Turbine Open Cycle Operation Gas Turbine
Open Cycle Full Load 60 MW 12 Combined
Cycle Load 360 MW Cold Start up 4.5 Load 360 MW
= (4 Gas Turbine 4 x 60 = 240 MW) + (1 Steam Turbine 120 MW)
Cogeneration Operation
Gas Turbine Generator Exhaust Gas Gas
Turbine Waste Heat Boiler Unfired Supplementary Fired
, CoGeneration (Process)
Gas Turbine Auxiliary Burner 70-80%
2.2.3 - 16
2.2.3 - 17
Combustion Turbine
(Preparation) , Start up, / Load Shutdown
/ ,
,
Limits Work
Instruction, Technical Paper Manual
Gas Turbine (Start up) Manual Automatic Mode
/ Remote Control Start up Compressor
Starting Means Diesel Engine, Electric Motor Frequency Converter (FC.)
Compressor (Firing) Combustor
Compressor 20-25% Igniters Burner
Combustion Chamber Turbine Torque Compressor
Torque Starting Mean Turbine
60% Torque Gas turbine
( Sustaining Speeds)
Gas turbine Firing
Gas Turbine (Acceleration) (Rated Speeds) Starting Mean
Gas Turbine 60% ( 70% Rated Speeds)
Rated Speeds Gas Turbine
Rated Speeds Close Generator Circuit Breaker
(Synchronizing)
Stat up Gas Turbine (
Compressor) Start up Controller Speeds Control, Load
Control Temperature Control ( Governor Control) Gas
Turbine
2.2.3 - 18
(Operator Responsibility)
Start up
- Check Sheet
- / Function Test
()
- Start up, Loading
Shutdown
1. (Annunciater Indicator)
(Abnormal Condition)
(Protection System) Low Lube Oil Pressure, Over Exhaust Temperature, Vibration Over
Speeds ()
2.
2.2.3 - 19
2.2.3 - 20
Vibration Limits
Combustion Turbine Vibration Velocity (in/sec)
(Moving Parts) Combustors Vibration
/ Start up (Vibration Speed) , Loading
(Vibration MW) / Major Overhaul
Vibration
Vibration Sensors Turbine / Compressor Blades Restart
Vibration
Load Limit
Load Mode 2 Base Peak
Turbine Turbine Inlet Temperature
(Trouble Free Operation) Turbine Bucket Thermal and Dynamic Stresses,
Compressor/Turbine Wheel Stresses Generator Cooling System
Temperature Control & Protection Control Specification
Overload Nameplate Turbine
Reliability
( : Compartment
)
Combustion System
Combustion
Combustor ( Light Oil), Cover/Casing
/
Combustor Failure
1. EXH. Temperature Spread Limit Alarm
Combustor Trouble High EXH. Temp. Spread Trip Limit
2. Trip Start up
EXH. Temp. Spread
3. Trip EXH. Thermocouple
Combustion Lines, Transition Pieces Fuel Nozzles
4. Thermocouple 1
Alarm Combustion Trouble Trip
Thermocouple 2
Thermocouple 3 (Three Adjacent Thermocouples)
2.2.3 - 22
Turbine Rotor 2
1. Cool down Operation Slow Roll Operator Turbine Rotor
Lube Oil Pressure (OL-6) Torque Converter ( Turbine Wheel)
Sol. Valve 20 TU-2 Cool down Turbine Rotor Shut down
Rotor Rub Check () Start up /
.,
Manual
2.2.3 - 24
2.2.3 - 25
2.2.3 - 26
2.2.3 - 27
2.2.3 - 28
2.2.3 - 29
Plant Operation
1. Substation
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
........................................................................................................................................................
2. Load Dispatcher
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
............................................................................................................................................
3. ........................................................................
4. External Combustion Engine
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
..................................................................................................................................................
5. Gas Turbine
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
....................................................................................................................
2.2.3 - 30
.
7.
Two Shaft Gas Turbine Shaft Compressor Shaft AC Generator
Turbine Compressor ................................................ Turbine AC.
Generator ...........................................................
8. Gas Turbine 3
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
................................................................................................................................................................................
......................................................................................................................................
9. (Limits) 4
4.1.......................................................................................................................................................
4.2.......................................................................................................................................................
4.3.......................................................................................................................................................
4.4.......................................................................................................................................................
10. X
............. Start up Gas Turbine Compressor Starting Mean
.............Gas Turbine Starting Mean Compressor Rated Speed
.............Working Fluid Gas Turbine Combustor
2.2.3 - 31
2.3 - 1
Control Modes
Control Modes
(Feedback Control Loop) Controller
Deviation Final Control Element
Deviation Final Control Element
Control Action 4
o Two Position Control
o Proportional Control
o Reset Control
o Rate Control
Two Position Control
Final Control Element 2
on-off Control Two-Position
Control Capacity
,
Controller
Process Loop Measured Variable Controller
Measured Variable Set Point Deviation Controller
Final Control Element Deviation
Two-Position Control In a Process Loop
Two-Position Control
Two Position
Controller
Steam
Sensor
Steam Trap
Two-Position Control 2
Two-Position Control (Controlled Variable)
(Fluctuate)
M ax
Set point
Tim e
M in
O pen
Valve
Tim e
Close
2. Two-Position Control
Two-Position Control Dead Band Dead Zone
Set point Dead Band
Dead Band Set Point Controller
Limit
Dead Band
Set Point Set Point
Set Point Dead Band
Deviation
2.3 - 3
Max
Dead
Zone
Time
Min
Open
Valve
Time
Close
3. Two-Position Control
Two-Position Control (on-off Control)
o Manipulate Variable
o Final Control Element
Measured Variable Set Point Set Point Range [Dead
Band]
o Mechanism on-off Relay
o on-off Control Dead Band
Small Capacity Relay
Process Large Capacity
Proportional Control
Continuous Control
Two-Position Control
Two-Position Control
Control Action Final Control Element
Set Point
2.3 - 4
Proportional Control
Controller
Final Control Element Deviation
Set Point Final Control Element
Output Bias Deviation
Steam
Valve
Temp
Max
100% Open
Setpoint
50% Open
Min
0% Open
Steam
Valve
Temp
Max
100% Open
Setpoint
50% Open
Min
0% Open
4. Input Output
4. Input Output
Set
Point Deviation Max Min
Set Point Max
Set Point
Heat Exchanger Set Point Set Point
50
Set Point
2.3 - 5
Proportional Band
Proportional Band
Proportional Control Controller Gain Proportional
Band
Proportional Band Input (Deviation)
Output
P.B =
Input x 100 %
Output
500%
100
167%
100%
60%
80
20%
Measured 60
(Span)
% 40
20
0
20
40
60
80
100
Steam
Valve
Temp
Max
100% Open
Setpoint
50% Open
Min
0% Open
6. Proportion Band
P.B. Max
P.B = 200 % 25 %
Full Range Min 75 % P.B
Controller Gain
P.B = 100 x 100 = 200 %
50
2.3 - 7
Valve
Temp
200% Open
Valve
Temp
50% Open
2.3 - 8
Valve
Temp
Max
Setpoint
Min
Valve
Temp
Max
Setpoint
Min
2.3 - 9
Temp
Max
offset
Setpoint
Min
10. Offset
Reset Control
Reset Control
Offset proportional Control
Reset Control Offset Set Point
Proportional PI-Control Reset
Control Integral Control
Max
Setpoint
Min
11. Integral Control
Integral Action & Reset Action
Deviation
Cs
=
1 edt
Ti
2.3 - 10
Cs
=
Integral Action
e
=
Offset Error
Ti
=
Integral Time
Integral Time Output
Proportional Control Integral Time Minute Per Repeat
Rate Control
Rate Control or Derivative Control
Control Action Controlled Variable
Manipulated
Varia ble Set Point
Set point Derivative Control Control Action
Error 0 Controlled Variable
Cs
Td de
dt
Td
=
Derivative Time
Derivative Action proportional Control PD Control
Controlled Variable Batch Process
Proportional Plus Reset Plus Derivative
D. Action Set Point
2.3 - 11
2.3.1 - 1
Combustion Control
1. Energy Balance Single Boiler
Output (load) Boiler Fuel Energy Balance
Boiler Furnace Control
Energy Balance
Process Load Boiler
Energy Balance single element Steam Pressure Control
1 Boiler
Steam Pressure energy balance Steam
Pressure Process
Controller Action Proportional + Integral ( PI Control)
Steam Pressure
Noise Steam Pressure
PID-Control Derivative Pressure Signal Noise
Derivative Control
derivative Steam Pressure Energy Balance
Mass balance Steam flow feed forward
control
2.3.1 - 2
To Stack
AT
LT
Feedwater
FT
Steamto users
Fuel
Air
a) load ( 1-2 )
b) load load Steam Pressure
Set point = 5 10 Single element 2
c)
load =5
Steam Pressure Set point
Steam Pressure
(Fuel) feed forward trim
Steam Pressure Feedback loop feed forward loop
feedback control loop
3
2.3.1 - 3
Steam Pressure
PT
Steam A
Pressure
Control
d/dt
Steam A
Pressure
Control
Process Energy
Demand (Steam Flow)
K
X
2.3.1 - 4
Steam Pressure
Steam Flow
PT
PT
Load Demand
Boiler Stored
Energy Error
K
X
Steam A
Pressure
Control
2.3.1 - 5
2. Furnace Control
firing race demand Energy Balance System
furnace Control
a) (Fuel & Air) Firing Rate demand
b) Fuel / Air Ratio
Fuel / Air Boiler
Fuel / Air Ratio
Fuel / Air Ratio load
c)
load
Start up Shut down Interlock,
Burner Management furnace Control
d) Furnace Pressure
3. Fuel/Air Flow Control
Fuel/Air Flow 2 Positioning Metering Boiler
Fuel/Air Positioning Type
System Fuel Air
Final Control Element
5 Fuel Valve Firing Rate Demand
Air Damper Fuel / Air Ratio
Fuel
Positioning System
Response Firing Rate
2.3.1 - 6
f(x)
Fuel Control Valve
Fuel / Air
ratio adjust
f(x)
Air damper
, ,
Fuel / Air Burner
Positioning System Metering Systems
Fuel Air
Metering Systems Parallel Metering 6
Fuel Flow Interlock Air Flow Interlock
Cross Limiting Flow
Interlock Lead-Lag Parallel-Series Metering System
Steady State Fuel Air Flow Controller
Measurement Set Point Firing Rate Demand, Air Flow Set Point, Air Flow
Measurement, Fuel Flow Ser Point Fuel Flow measurement
Load
Load Firing Rate Demand , Low Selector
Air Flow Ser Point Fuel Flow
Controller High Selector Firing Rate Demand
Fuel flow measurement Set point Air flow controller Set Point
Air Flow Controller Firing Rate Demand Output Air Flow
Controller Air Flow Air Flow Air Flow Measurement
Set Point Fuel Flow Controller Load
Air Fuel
Load Firing Rate Demand
Low Selector Firing Rate Demand Set Point Fuel Flow
2.3.1 - 7
Steam Pressure
Fuel Flow
FT
Air Flow
FT
PT
f (x)
K
A T
Fuel Flow
Controller
Boiler master
pressure
controller
A T
A T
f(x)
Fuel Final operator
Air Flow
Controller
f(x)
Air Final Operator
Basic
Boiler Load
2.3.1 - 8
Fuel Control
Fuel Control
Set point Desired value Fuel oil control output signal
Boiler Master Control Boiler Master Demand Air
Flow Cross Limit Actual Air Flow (Air Demand Corrected) Air
flow control low select circuit Set point Fuel
oil controller Air flow cross limit Boiler
Master output Set point
Fuel flow-Air flow control Controlled Variable 2 Air Fuel
Fuel / Air ratio (Fuel rich) Boiler Master
Demand Fuel flow Air flow
limit Combustion Air
Fuel Actual Air flow feedback
signal (Cross limit Air flow Fuel flow cross
limit)
Measured Variable Desired Value Fuel
flow Fuel oil flow consumption Fuel oil return flow Fuel oil
flow Ignitor oil flow Total Fuel Controller
Set point Boiler Master Output Controller
Fuel oil control valve
2.3.1 - 9
Ig n ito r O il Flo w
FT
K
F u e l o il su p p ly to
fu e l o il h e a te r
te m p c o n tro l
<
R CRT
R CRT
K
M RE PLW
f (x)
f(x)
F u ll c a p a c ity fue l o il
flow c on trol va lve
T o ta l F u e l to
a ir flow c on trol
T ra c k w h e n M /A
in m a n u a l
A la rm
fu e l oil flo w
I/P
f (x)
%
I/P
f(x)
H a lf ca p ac ity fu e l o il
flow c on trol va lve
1. FD. Fan
2.3.1 - 11
AH B air outlet
AH A air outlet
temp Air Flow AH. B temp Air Flow AH. A
TE
FT
TE
TT
Oxygen Analyzer
FT
AT
TT
CO. Analyzer
H/L
Alarm
R CRT
25% MCR
A T A I
AP/T
Purge permit
H/
Air demand
correction to
fuel control
Alarm
CRT
MRE
AP/T
H/
AT
Alarm
/LL MFT Trip
K
fuel / air ratio
/L
f (x)
MRE
Steam
Flow
T A I
R CRT
f (x)
LAG
bias
PLW MRE
I A T A
I A T A I
I/P
f(x)
FD fan A Inlet
Damper
MRE PLW
I/P
Track when
either FD Fan
manual
f(x)
FD fan B Inlet
Damper
solid carryover
Turbine blade Super heat priming
Turbine Super heater drum
Condensate storage tank
drum
Boiler load Feed water Boiler
load Feed water
Swell and shrink drum level Swell
steam bubble Drum pressure steam flow
( load) Thermodynamic Drum pressure Saturation pressure
enthalpy
2.3.1 - 13
Drum
Level
FT
LT
Drum
Pressure
PT
R CRT
Three element
drum level
controller
TT
H/L
Alarm
R CRT
AP/T
AP/T
CRT R
CRT R
Total feed
water flow to
deaerator
Three element
feedwater flow
control
Single element
drum level cont.
0.0
MRE
V>
MRE
I A T A A I
Drum level
set point
T A I
I/P
I/P
f(x)
f(x)
2.3.1 - 15
T
100%
0.0
2.3.1 - 16
2.3.1 - 17
2.3.1 - 19
Main Steam
Flow
Drum Pressure
PT
ATT SH Outlet
Temp B
TE
Bias press
Alarm
TT
H/L
f(x)
Alarm
f(x)
H/L
CRT
CRT
<
TT
Max. 530C
setpoint
0%
H/L
R CRT
TT
Alarm
H/L
CRT
Set stage A
outlet temp
control
Alarm
LAG
TT
Set stage B
outlet temp
control
-K
>
MRE PLW
MRE PLW
I A T A I
I A T A I
I/P
I/P
f(x)
f(x)
2.3.1 - 21
GRFan Diff
Pressure
Furnaces
Pressure
DP
Alarm
/L
TT
Alarm
H/L
CRT
f(x)
ATT RHOutlet
Temp
TE
TT
TT
Alarm
H/L
CRT
R CRT
A Bias +5C
25%
MRE
I A T A I
25%
<
I/P
50%
MRE
Gas recirc diff
pressure low-low
is close damper
to 0%
T A I
T
MRE PLW
I A T A I
setpoint
I/P
I/P
f(x)
f(x)
f(x)
Stack Control
Damper
GRControl
Damper
0%
V>
2.3.1 - 22
1. Process On-Off
2. Dead Band On-Off Control
3. Proportional Band ? PB
4. Off Set
5. Derivative Control Transient
6. P, I D
7. Combustion Control Series Metering -
8. Combustion Control Lead-Lay -
9. Feedwater Control Single Element, Two Element Three Element
10. Main Steam ,
2.3.1 - 23
2.3.1 - 24
2.3.1 - 25
2.3.3 - 1
(Construction and Principle of Operation)
1.1 GENERATOR
1A Generator Magnetic Field Stationary Coil
Induced Current Voltage Stationary Coil Magnetic Field
DC Rotor DC Magnetic Field Rotor Rotor
Induced AC Voltage Current Stationary Coil
Stator Coil
F
=
N
Frequency
/
F
=
N
=
/
=
60
-
2.3.3 - 2
Stator Coil
N
S
S
N
F
=
N x P (P = Pole)
P Pole (Pair of Pole) Pole 1-Poke Rotor 1
Pole, Rotor 4-Pole Speed 3600 RPM Generator Rotor
4 Pole Speed 1800 RPM
Generator Speed 300 RPM Pole
Frequency 60 Cycle/Sec Rotor 12 Pair of Pole 24 Pole
Generator Hydro Turbine Rotor
Generator Steam Turbine Rotor Bigh Speed
Rotor
1C Turbo-Generator Rotor
2.3.3 - 3
2.3.3 - 4
1 E Stator Frame
1F Stator Iron Core Winding
Copper Conductor Slot Conductor Slot Conductor
Coil 1G
1F Iron Core
Stator (Solid Iron)
Flow Eddy Current Eddy
Current Heat Loss
2.3.3 - 5
Hum
Generator
Copper Bar Slot Insulation Conductor
Iron Core Synthetic Varnish, mica Glass Tape Station Conductor
Slot Strong Wedges
Machine , Conductor Slot H2
, 1 H Stator Coil
Conductor ,
2.3.3 - 6
2.3.3 - 7
1L Insulated Bearing
1.4 EXCITATION
1M Excitation Schematic
Exciter DC Generator Electric Motor DC
Slip Ring Rotor Control Generator
Rotor
(+)
Motor
(-)
Exciter
1M Separately Driven Exciter
2.3.3 - 8
Control
Collector
Ring
(-)
Commutator
Exciter
Brush
(+)
1O DC Generator
DC Generator , Armature Conductor AC
DC Commutator DC Commutator Main Rotor
Electro-Magnetic Field DC
Commutator , Self-Excited DC Generator ( DC Commutator) 1P
Magnetic Field , Out Put Voltage Armature
Magnetic Field Generator
2.3.3 - 9
Field Switch
(+)
Rotor
Slip Ring
(-)
Main Exciter
Pilot Exciter
1P Self-Excited DC Generator
Excitation Main Pilot Exciter
1Q , Main Exciter Pilot Exciter
Main Exciter Field Control Commutator
Field Switch Slip Ring , Field Switch Open Shut Down,
Pilot Exciter Field Manual Automatic
Rotating Magnetic Field Load
Generator Load Generator Steam Turbine
(+)
2.3.3 - 10
Rectifier
AC Exc/Gen
AC
Power Amp
DC
Voltage
Control
Auto
Man.
1R Brushless Excite
Control Field Automatic Manual Voltage Control AC
Armature Main Exciter Rotating Rectifier, DC
Main AC Generator Rotor Brush, Slip Ring
Commutator
Static Excitation Excitation 1S
Rotating Exciter , AC Power Line Main Generator Static
Exciter DC Control Manual
Automatic Voltage Regulator DC Slip Ring Rotor
Excitation 3
2.3.3 - 11
DC (+)
Static Exciter
AC.
1S Static Excitation
2.3.3 - 12
Controller
Generator&Exciter
1. Generator 3000 rpm. 2 Pole
2. Hydrogen Stator Coil Generator
3. Stator
. :
2.3.3 - 13
2.3.4 - 1
Generator Protection
1.1
(Prime Mover)
(Stem Turbine)
(Gas Turbine) (Water Turbine) (Diesel Engine)
(Synchronous
Generator)
(Unit
Generator Transformer)
1.12
1.2
(Exciter) (Turbine) (Condenser) (Boiler)
(Faults)
1. (Stator Faults)
2. (Overload)
3. (Over voltage)
4. (Unbalanced Loading)
5. (Rotor Faults)
2.3.4 - 2
6. (Loss of Excitation)
7. (Loss of Synchronism)
8. (Overheating)
9. (Failure of Prime Mover)
10. (Low vacuum)
11. (Lubrication Oil Failure)
12. (Loss of Boiler Firing)
13. (Over speeding)
14. (Rotor Distortion)
15. (Difference in Expansion Between
Rotating and Stationary Parts)
16. (Excessive Vibration)
1.3
(Insulation)
(Switching)
(Lightning
Arrester) (Surge Diverter)
2.3.4 - 3
(Elasticity) (Carbonized)
(Core Burning)
(Arc)
3
(1) (Earth Faults) 2
(Neutral)
5 20
(Earthling Transformer
Distribution Transformer)
(2) (Phase Faults)
2.3.4 - 4
1.4
(Circuiting Current Differential Protection) 2
(Longitudinal Differential) (Transversal Differential)
1.4.1 (Longitudinal Differential)
1.4.1.1
1.1
GENERATOR
BREAKER
CT1
I2
I1
CT2
A
B
52
Stator Winding
ZE
87
87
87
Differential Relay
High Impedance Type
1.1
GENERATOR
CT1
BREAKER
I1
CT2
52
i2= i
i
i2
i2= i1= i
87
1.2 ()
2.3.4 - 5
GENERATOR
CT1
BREAKER
I1
CT2
52
i1
i1
i1d= i1- i2
i1
i2
A
i2= i1= i
i2
87
i2
1.2 ()
(Relay Voltage Setting)
(Exciting Losses)
(High
Impedance High Sped Relay)
(Stabilizing Resistor)
1.4.1.2 (Percentage Differential Relay)
(Bias Coils) 1.3
I1 I2
(I1 + I2)/2
2.3.4 - 6
GENERATOR
BREAKER
I2
I1
N
i1
CT2
i2
52
Stator Winding
ZE
i1
A
B
i2
R
Restraining Coils
R
87
87
87
Relay
1.3
Operation Area
I1-I2
( I1+ I2) / 2
1.4
1.4.1.1
2.3.4 - 7
1.3 1.4
(Induction)
(Operating Coil)
I1-I2 (Restraining Coil)
(I1-I2 )/2
20% , 25%
(Variable Percent Slop)
1.4.1.3 (Restricted Earth Fault Protection)
1.5
1.5
GENERATOR
BREAKER
CT
CT1
52
64
A
B
C
1.5
1.4.1.4
Y
U
1.6
2.3.4 - 8
Stator Winding
BREAKER
CT
52
A
B
C
87
87
87
1.6 U
1.4.1.5
(Rating)
U / Y 30
Y /U 1.7
(Tap Change)
2.3.4 - 9
52
A
B
C
Generator
Transformer
ZE
87
87
87
R
R
R
1.7
(Magnetizing Inrush)
(Harmanic Restraint)
(Offset Current)
(Voltage
Recovery) (Transient)
2
1 1 1.8
2.3.4 - 10
A
B
52
Transformer
Generator
ZE
87
87
Relay for
Generator
87
87
87
87
Relay for
Transformer
1.8 -
1.4.2 (Transverse Differential Protection)
(Double
Wound Stator)
(Balanced Current) 1.9
(Load Sharing)
ZE
C
87
R
87
R
87
1.9
2.3.4 - 11
(Zero-Sequence Voltage)
(Emf)
1-2 %
1.10
A
N
B
C
Transform er
ZE
O pen Delta
Relay
1.10
U
3
2.3.4 - 12
Setting (Filter)
(Coordinate)
1.5 (Overload Protection)
(MW)
MVA MVAR
(Voltage Regulator)
(Time Characteristics)
(Thermocouples)
(Resistance Thermometer)
(Mill voltmeter)
(Ratiometer) (Multi Way Selector)
(Field
Winding)
1.6 (Over current Protection)
1.5
1.11
2.3.4 - 13
Generator
A
52
B
C
Earth
Fault
Relay
Phase Relay
1.11
(transient)
(Voltage Regulator)
3
1.11
2
(Overload)
(Long Inverse Time)
1.12
()
100
Overload Charge
(normal voltage)
10
Fault Charge
(Low Voltage)
10
100
(A)
1.12
(Shading Loop)
2.3.4 - 15
1.13
Generator
A
N
B
C
CT
64
Earth Fault
Relay
ZE
1.13
(Unrestricted Earth Fault)
(Inverse Time)
1.7.1
1.13
(Instantaneous Relay)
10% (Surge
Current)
5 %
1.7.2
2.3.4 - 16
(Voltage Relay)
1.14
Generator
A
N
B
C
CT
Resistor
Voltage Relay
1.14
1.8 (Overvoltage Protection)
(Surge Voltage)
(Surge Diverter)
(Power Frequency Overvoltage)
()
()
VAR
()
(Governor)
(Turbine Gates)
150 %
2.3.4 - 17
2 (Eddy Current)
10% 15 % MR (Continuous Mean Rating)
(Salient Poles) 40 %
( Thermal Capacity)
=
K
Ti22dt
=
K
I22T
i2
=
I2
=
CMR
T
=
K
=
1.9.1
2.3.4 - 18
(Filter)
1.15
A
B
C
ZA
ZC
Relay
Ia2
Ia1
V XY
VZA
Ic1
VZC
positive
sequence
Ib1
negative
sequence
VZA
Ic2
VZC
Ib2
1.15
A ZA C
A(IZcI IZAI) 0.5 C 60
ZA VZA Ial C
ZC VZC Icl 60 VZA IZCI IZAI
lIall lIall IVZAl IVZVl Vxy 1.15 ()
Vzc Vza
Zxy
U
2.3.4 - 19
1.16
2
(Definite Time Delay)
(Armature Type)
1.10
(Rotor Faults)
(Exiciter)
50-100
(Bearing)
2.3.4 - 20
1.17
Winding
Excitor
Resistor
Voltage
Relay
1.17
(Auxiliary Supply)
5 % (Exciter)
Excitor
AC.
Current
Relay
1.18
2.3.4 - 21
E xc ito r
+
AC.
C u rre n t
R e la y
1.19
(Bias) (Exciter)
1.11
(Failure of Field)
(Induction Generator)
(Wattless Stator Current)
(Turbine Governor)
(Slip Frequency) (Damper Circuit)
2.3.4 - 22
(Excitation)
Winding
Excitor
Shunt
Relay
T1
T2
T1 :
T2 : 2-10
Contact
1.20
50 60 MW
5
500 MW 20 30
(Undercurrent Relays)
1.20
(Directional Distance Relay) (Mho Relay)
1.21
2.3.4 - 23
+X
-R
+R
-X
1.21
(Loss of Synchronism)
1.21
1.12
1.12.1
(1) (Differential Protection)
(5) (Indicaot)
2.3.4 - 24
(2)
(3)
2.3.4 - 25
Example
Generator Protection
Once Through Boiler
Generator
Technical Specification
Serial Number
Type of Generator
: 97AD3301/97AD3401
: Horizontally Mounted Cylindrical Rotor,
Rotating Field Type
Rotating Speed
(rpm)
3,000
No. Of Phase
3
No. Of Pole
2
Frequency
(Hz)
50
Voltage
(V)
24,000
Hydrogen Gas Pressure (bar(g)) 5
Hydrogen Gas Purity (%)
97
Hydrogen Gas Consumption
9
3
(Nm /24 hour Guaranteed)
KVA Output
(kVA)
990,000
KW Output
(kW)
841,500
Current
(A)
23,816
Power Factor (%)
85 (Lagging)
Cooling Method Stator Coil
Water Cooled
Rotor Coil
Hydrogen Cooled
Insuration Class
F
Temp Rise Limit Stator Coil (C) 50 (Base Temp 50C)
At Rated Load
Stator Coil
50 (Base Temp 50C)
Cooling Water
Outlet (C)
Rotor Coil (C) 72.2 (Base Temp 37.8C)
Stator Core(C) 92.2 (Base Temp 37.8C)
2.3.4 - 26
Gas Volume
(m3)
Exciter Type
Excitation Voltage (V)
Excitation Current (A)
130
Static
650
6405
To Discon.
Switch
Aux CT.
GRP - A
51
G1N
87-1
Isolate Phase
Busduct
GRP - A
Excitation
Transformer
To Main Aux.
Transformer
3xCT
30000/5A
3xCT
30000/5A
3xCT
30000/5A
GRP - A
60-1
60-2
GRP - B
Generator
87-1
32-1
32-3
46-1
78-1
40-1
32-2
3xCT
30000/5A
27-1
27-2
62-1
GRP - A
3xCT
30000/5A
3xCT
30000/5A
21-1
50-1
49S
40-2
GRP - B
Busduct
To Excite Control
Generator
Transformer
Gen Neutral
Ground Unit
50-1
81-1
81-2
81-3
81-4
GRP-A
Generator Differential Relay (87-1)
Generator Stator Ground Relay (64-1)
Generator Loss of Field Relay (40-1)
Generator Reverse Power Relay TD:3Sec (32-1)
Generator Impedance Relay (21-1)
Generator Excite System Trip
Generator
Generator Transformer
86BF
86BF
SteamTurbine Trip
Bucholz
Winding
Oil
Pressure
87-1
64-1
49S
60-1
40-1
32-1
78-1
Gen. OverfluxingRelay
59/81
59/81
46-1
32-3
27-1
27-2
64R
SEM
SEM
SEM
SEM
TD
SEM
TD
SEM
S
R
SEM
S
R
SEM
SEM
S
R
SEM
SEM
S
R
S
R
S
R
Lock
Reset
Close
OPen
Close
OPen
Close
OPen
87M1
Close
OPen
51-M1G1
System
A O O
B
O O
86GA
86EA
86GB
86EB
Bucholz
Winding
Oil
Pressure
S
R
DAS
Close
OPen
S
R
SEM
Bucholz
Winding
Oil
OLTC.
Pressure
GRP-B
Generator Stator Ground Relay 100% (64-2)
Generator Stator Thermal Relay (49S)
Generator Loss of Field Relay (40-2)
Generator Over Fluxing Relay (24)
Generator Reverse Power Relay TD:30Sec (32-2)
Generator Unbalance Voltage Relay (60-2) Relay Trip
Generator Circuit Breaker 904XX, Trip Exciter Circuit Breaker, Trip 11.5kV Switchgear Main Breaker
A&B Transfer 11.5kV. Relay
(Setting) Relay Trip Generator
Generator Stator Ground Relay (64) Stator Ground Fault
Star Point Generator Low Side Generator Transformer
Generator Loss of Field Relay (40) Loss of Field
Generator Capability Curve Impedance
Generator Reverse Power Relay (32) Generator Motor
Generator Unbalance Voltage Relay (60) PT. AVR
PT. (Potential Transformer)
Generator Negative Phase Sequence Relay (46) Unbalance Load
Setting Thermal Characteristic Rotor
2.3.4 - 29
Generator Protection
1. (Over Voltage)
2. (Unbalance Loading)
3. (Negative Sequence) Rotor
4.
5. (Undercurrent) Relay
. :
10,
2.3.4 - 30
2.3.5 - 1
(Transformer Protection)
(1) (Overhcating)
(2) (Overfouxing)
(3) (Tank-Earth Detection)
(4) (Gas Detection)
(5) (Over current)
(6) (Earth Fault)
(7) (Differential)
3
2.3.5 - 2
(Dial Thermometer)
(Silistor Heat Sensitive Silicon Resistor)
,,,
(Electrolytic Coulometer) 4 4
100 -110
10,000
110 - 120
10,000
120 - 130
1,000
> 130
1,000
1.2 (Over fluxing Protection)
1.2
(Abnormal Operating Conditions)
1 2
(1.1) E/f
= K (E/f)
E/f ( p.u. )
1
E/f
2.3.5 - 3
2
2-5
2 5-30
Howard Protection)
100
(
1.1
64
1.1
1.3 (Gas Detection Protection)
(Local Heating)
,
( Hot Joint)
(Oil Conservator)
(Oil Vapour)
2.3.5 - 4
()
() (Core Bolts)
()
()
()
()
()
1 MVA (
1 MVA )
0.05-0.1
2.3.5 - 5
1.2
1.2
(Turbulence) 5
5 3 3.7
1.1
(MVA)
()
<1
1-10
>10
(.3)
(.3)
(./) (./)
100-120
110
70-130
90
185-215
200
75-140
100
220-280
250
90-160
110
1.1
2.3.5 - 6
(Radiator)
(Viscosity) (Ensitivity)
1.3
2.3.5 - 7
(Silicone Oil)
KVA
25
50
100
200
500
1.4.2
1.31
2.62
5.25
10.5
262
4
6
10
15
30
1.2
3
()
0.17
0.4
1.1
10.0
100.0
100 kVA
(CB) 2
(Earth Fault Protection)
(CT)
(Source in Dance)
1.4
Transformer
Winding
Current
Transformer
3phase
Overcurrent
Relay
1.4
(Instantaneous O/C Relay)
(Thermal Relay)
1.5 (Restricted Earth Fault Protection)
U Y
(Residual)
2.3.5 - 9
1.5
Transformer
Winding
Current
Transformer
Residual
Overcurrent Relay
1.5
Transformer
Winding
Current
Transformer
64
High Impedance
Relay
Current
Transformer
ZE
1.6
1.5
Y
1.2
3.11
(Residual Current) CT3 CT
2.3.5 - 10
(Instantaneous)
E ()
( 1.6)
1.6 (Differential Protection)
(Ampere-Turns)
(Differential Protection) 1.7
3xCT
30000/5A
Generator
Step Up Transformer
990 MVA
FOA Type
525 / 24kV
YNd1 : Vector
87 Transformer
GT Differential Relay
3xCT
30000/5A
1.7
CT I1 = I2 I1
= I2 (p.u.) I1 I2
0.5-10 %
(1) 2 (Two Windings Transformer)
1.8 3
2.3.5 - 11
Transformer
Winding
87
87
87
1.8 2
(2) 3
1.9
87
GT
Transformer
1.9 3
(3) 3 3
() 1.10
2.3.5 - 12
Transformer
O :
B :
87
1.10 3 3
() (Transformer Ratio)
(CT)
20 MVA 115 U/69YkV CT
115 kV C.T. 150/5 Y
69 kV C.T. 250/5 U
()
Y/U 3 (Balanced 3 - )
30 U CT Y U
CT U 1/3 Y
U CT Y
() (Tap-Changing)
CT
1.8 1.10
()
2.3.5 - 13
(Fuse Link Kick Fuse) (Shunt)
Transformer
Through bias
Harmonic bias
Restraint coil
XL
XC
High set unit
Operating Coil
1.11
2 3
3
U Y CT U
2
20 % CT
2
(Filter) (Differential Current)
(Percentage Restraint) 1.11
2.3.5 - 14
2.3.5 - 15
RA
0076
RA
0078
RA
0079
RA
0074
RA
0086
RA
0075
RA
0084
RA
0089
RA
0088
RA
0087
RA
0082
Name
Symbol
OR Gate
AND
Gate
Timer
ANN
TD
ANN
Substation
Trip 6.9kV SWGR 101 Main Breaker
Trip 6.9kV SWGR 102 Main Breaker
Trip 230kV Gen Breaker 800322
Trip 230kV Gen Breaker 800312
Auto - Transfer
Int 6.9kV SWGR 102 Reserve Bkr. Auto- Transfer
Initial 230kV Breaker 800312 Failure
Initial 230kV Breaker 800322 Failure
ANN
Substation
Trip 230kV Gen Breaker 80322
Trip 230kV Gen Breaker 80312
Int. 230kV Gen & RAT Breaker 800322 Failure
Trip 86G1
RA
0077
RA
0085
TD 5s
RA
0081
T2: 2.5s
TD
T1:30s
RA
0130
RA
0091
Trip 86GB1
RA
0092
2.3.5 - 16
Transformer Protection
1.
2. Sudden Pressure Relay
3. (Thermal Relay)
4. (Circuit Breaker)
. :
10,
2.3.5 - 17
2.4 - 1
COMMISSIONING CONCEPT
1.
Commissioning
Commissioning
Commissioning ,
,
, ,
Commissioning
Training (),
Commissioning
Commissioning
2. Commissioning Concept
Commissioning
(Safety)
(Contractor)
(Guarantee)
2.4 - 2
(Instruction
Manual), (Control Logic)
2
o
(Operate), (Maintenance)
o (Drawings)
o (Instruction Manual)
o (Performance)
o ,
o (Spare Parts)
o
(Schedule)
,
3. Commissioning Organization
Commissioning Dynamic
Organization
Commissioning Organization
2.4 - 3
LEAD
ELECTRICAL/
CONTROL & INST
SHIFT 1
SHIFT2
FORMAN
ELECT. #1
ELECT. #2
ELECT. #3
FORMAN
ELECT. #1
ELECT. #2
SHIFT 1
SHIFT 2
C&I. #1
C&I. #2
C&I. #1
GE/REOL
COMMISSIONING
MANAGER
EGAT
CONSTRUCTION
CO-ORDINATOR
GELEAD
COMMISSIONING
T/A
LEAD
MECHANICAL/
OPERATIONS
SUPERVISOR
LEAD DCIS
ADMINISTRATOR
TURNOVER
PACKAGE
DEVELOPMENT
SHIFT 1
SHIFT 2
C&I. #1
C&I. #2
C&I. #1
EGAT
ADMINISTRATION
SUPPORT
SHIFT 1
SHIFT 2
MECHANICAL
COMMISSIONING
ENGINEER/
SHIFT
SUPERVISOR
MECHANICAL
COMMISSIONING
ENGINEER/
SHIFT
SUPERVISOR
MECH. #1
MECH. #2
MECH. #3
MECH. #1
MECH. #2
= GE/REOL COMMISSIONING
= CRAFT SUPPORT
EGAT
COMMISSIONING
GROP
OPERATORS
= EGAT COMMISSIONING
= LINES OF SUPERVISION
= LINES OF COMMUNICATION
GE/REOL
ON SITE TRAINING
2.4 - 4
MECHANICAL
COMMISSIONING
T/A
ELECTRICAL
COMMISSIONING
T/A
FORMAN
MECH. #1
MECH. #2
MECH. #1
ELECTRICAL # 1
HELPER #1
START-UP
COMMISSIONING
T/A
ELECTRICAL #1
HELPER #1
C&I
SUPPORT
AS REQUIREO
COMMISSIONING ORGANIZATION
RATCHABURI COMBINED CYCLE POWER PLANT
EGAT
COMMISSIONING
CO-ORDINATOR
GE/REOL
COMMISSIONING
MANAGER
ELECTRICAL EQUIPMENT
WORKING PARTY
MECHANICAL WORKING
PARTY
ACCEPTANCE TEST
WORKING PARTY
OPERATIONAL FUNCTION
WORKING PARTY
2.4 - 5
ORGANIZATION
(Job Description) Commissioning
1.
Commissioning
(Co-ordinator)
1.
Commissioning ,
(Contractor),
2.
,
Commissioning
(Commissioning Committee)
3.
Plant
Commissioning
5.
Site Note, Deficiency
list
6.
Plant
7.
- Tag
Pad-Lock
8.
,
Contractor
9.
2.4 - 6
1.
(Contract)
2.
Commissioning
Schedule
3.
Start up package
4.
Test
Procedure
5.
Instruction
Manual
Specification
2.
Acceptance Test
3. Commissioning
3. Commissioning
4. Commissioning
1.
1.
Specification & Contract
2. Check Sheet
6. ,
7.
1.
1-4
2.
1.
Performance
Criteria
2.
Performance procedure
1.
2. Instruction
Manual
3. Test Produce
4. Specification
5. Acceptance
Criteria
1. 3
5. Commissioning
Functional operation
6.
5.
,
1.
Operation
Walk down/ Pre-operation-check/
Startup/ Operation Demonstration Test/
Shutdown
2.
Functional Testing
Equipment/System/Plant
Specification & Contract
3.
6.
Site Note, Deficiency list
7.
, ,
8.
Safety Clearance & Tagging
1.
Pre-Cleaning,
2.4 - 8
1.
Equipment,
System plant
Operation Function
2.
Instruction
Manual
3.
Test
Procedure
4.
Acceptance Criteria
Operation
5.
Work
Permit and Safety
Tagging
6.
Start up Package
1.
Contract
Chemical Cleaning
Water Treatment
7. Training
Working Party
8. Safety
Working Party
Chemical cleaning
2.
Water
Treatment, Water Analysis, Sanitary,
Waste Treatment
Laboratory
3.
Process &
Performance Water Treatment plant
4.
Site Note, Deficiency list
5.
, ,
6.
1.
Training
2.
Simulator
(3) (4) (5)
3.
, ,
1.
Commissioning Contractor
2.
3. Site Note, Deficiency List
4. Walk down Inspection Pre Test
5.
2.4 - 9
2.
Instruction
Manual
3.
Specification
4.
Acceptance
Criteria
1.
2.
Instruction
Manual
3.
Specification
4.
Acceptance
Criteria
1.
2.
Acceptance
Criteria
3.
Specification
4.
4.2 Commissioning
4.2.1 ERECTION COMPLETENESS CERTIFICATE (ECC)
PRELIMINARY TEST (WITHOUT
MAIN VOLTAGE AND FLUID) Walk down Inspection
Contractor
Major Exception Item ECC Minor
4.2.2 SAFETY CLEARANCE CERTIFICATE (SCC)
System Preliminary Test Contractor
Exception Items Walk down Inspection
System Function Test Contractor SCC
Exception Item ()
2.4 - 10
2.4 - 11
Performance Test 2
Simple Cycle ( Gas Turbine) Performance Test Combined Cycle Performance Test
Performance Test Simple Cycle
Gas Turbine
Combined Cycle Steam Temperature Heat Recovery Steam
Generator, Steam Turbine
4.3 COMMISSIONING (SAFETY)
Commissioning Staff Plant
, Tag, Pad
Lock Work Permit
2.4 - 12
Safety Safety
, Work Permit, Tagging System
Test Report/ Reference Standard System Test,
Calibrate Package
Valve line up List and Check Sheet
Contractor
1
,
4.5
Commissioning Objective /
, , Instrument
, Functional Operation, Performance Commissioning
Panel Reference
2.4 - 13
Alignment
Equipment on Base
Preliminary Test
No Load Test
ECC.
Issue
WALK
DOWN
INSP.
- Flushing
Electrical, Instrument
Calibration Test
- Hydro Test
Initial Operation
Capability Test
POC.
Issue
SCC.
Issue
WALK
DOWN
INSP.
Function Test
Chemical Cleaning
Blow Out
Performance Test
2.4 - 14
Commercial Operation
Work Step
1) , Foundation, ( Anchor Bolt) &
2)
,
3)
, ,
4)
Flushing Piping Hydrostatic Test
5)
(Preliminary Test)
6)
System Functional Test
7)
Chemical Cleaning, Blow Out
8)
Initial Operation Function Test, Heat Run Test
9)
Capability Test , Function Test
10)
Performance Test
Commissioning
, Instruction Manual, Drawing
(Standard)
Commissioning Package
o
Check sheet Instruction
Manual, Drawing, , Spare Part, Tool
o
Instruction Sheet ,
o
Technical Data
o
Program
Exceptional Items
Site note Turnkey
Contractor
Site note
, Performance
Commissioning
2.4 - 15
2.4 - 16
Erection
Complete
Synchronization
Performance Test
Commercial
Operation
Provisional
Acceptance
Final
Acceptance
Trial Operation
Warranty Period
Extended Warranty
For component Defect.
if required
Finish
Commercial Operation
2.4 - 17
COMMISSIONING
Program
and
Commissioning Network
2.4 - 19
2.4 - 20
2.4 - 21
2.4 - 22
Commissioning Schedules
2.4 - 23
2.4 - 24
2.4 - 25
2.4 - 26
1.
2.
3.
4.
5.
?
WALKDOWN INSPECTION?
CAPABILITY TEST PERFORMANCE TEST?
(SAFETY) Commissioning ?
Commissioning
?
2.4 - 27
2.5 - 1
(Energy Balance)
(Control Panel) Computerised Mean
1
Working Fluid ( ) Ranking Cycle
(Turbine) Generator
Condenser
(Load)
Fluid Flow Load
(
, , , , Biomass ) (Boiler)
2
Mass Flow Mass Flow
Control Parameter
2.5 - 2
2.5 - 3
1.
Flow
2. (Emergency Operation)
2
2.1
Parameter
2.2
Parameter
Design
3. (Plant Start Up)
(Procedure)
Boiler, Turbine / Generator
3.1 Boiler
3.1.1
(
) , ,
Interlock
Fuel System
Control / Service Air
Pump, Valve, Damper, Sulenoid, Level
Switch
Air Heater, Induced Draft Fan, Forced Draft Fan
Boiler Circulating Water Pumps
2.5 - 4
Steam
Start Up Turbine
220C / ,
Turbine Rotor Heat Soak
Step
Load Speed Turbine
Confirm Parameter
- Differential Expansion
- Bearing & Shaft Vibration
Load Load Turbine / Generator
Parameter
Main Turbine
Boiler
3.2.2 Turbine Generator
Turbine Generator Start Up
Loading Load
Turning Gear
4. Routine
Load Load
4.1
(Log Book) Trouble
Report
, Fuel Gas,
4.2 (Preventive Maintanace)
4.3 Function Function
Function
2.5 - 6
5.1
5.2
Take Action .
5.3
5.4
5.5
5.6
5.9
Bearing
Battery Backup
Lighting
Steam
2.5 - 7
1. Modern Power Station Practice
2nd Revised and Enlarged Edition Volume7 Operation and Efficiency
Published on Behalf of the Central Electricity Generating Board
2. Combustion Fossil Power
A Reference Book on Fuel Burning and steam Generation Editor. Joseph G. Singer, P.E. 1991
2.5 - 8
2.5.1 - 1
2.5.1 - 2
- Fire prot release aux relay zone #1 Fuel gas Compartment , Turbine
Compartment
- Fire prot release aux relay zone #2 No.2 Bearing Tunnel
- Fire prot release aux relay zone #3 Lube Oil /Hydralic Compartment
- Fire prot release aux relay zone #4 Liquid Fuel /Atom Air Module
- Fire prot release aux relay zone #5 BAC Module
- Fuel Gas Temp > High High ( L26HHFTG ) Temperature
Fuel Gas Shutdown Alarm
2.5.1 - 3
2.5.1 - 4
2.5.1 - 5
2.5.1 - 6
- Low Lube oil Pressure Trip ( L63QT ) Lube Oil Pressure Disch.
2.5.1 - 7
2.5.1 - 8
2.5.1 - 10
2.5.1 - 11
2.5.1 - 12
2.5.1 - 13
2.5.1 - 14
2.5.1 - 15
2.5.1 - 16
2.5.1 - 17
2.5.1 - 18
2.5.1 - 19
2.5.1.1 - 1
Steam
Combustion
Boiler
Generator
Steam Turbine
Generator
Gas Turbine
Exhaust
Shaft Gas turbine Generator Steam Turbine
Generator Shaft Ratio 1 : 1 , 1 : 2 , 1 : 4
Multi Shaft Combined Cycle Power Plant
2.5.1.1 - 2
Gen
1 Gas Turbine
Gen
1 Boiler / HRSG
1 Steam Turbine
Combined Cycle Ratio 1 : 1
Steam
Gen
Generator
GAS Turbine - 1
Boiler / HRSG-1
Steam Turbine-1
Gen
Gas Turbine-2
Boiler / HRSG-2
GAS Turbine - 1
Boiler / HRSG-1
Gas Turbine-2
Generator
Boiler / HRSG-2
Steam Turbine-1
Gas Turbine-3
Boiler / HRSG - 3
Gas Turbine-4
Boiler / HRSG -4
2.5.1.1 - 4
Gas Turbine
Protection
Boiler / HRSG
Protection
Steam Turbine
Protection Trip
Device
Generator &
Electrical Trip
Device
Block Diagram Function Steam Turbine Protection Combined Cycle Power Plant
Gas Turbine Master Protection Trip
Shut Down Gas Turbine
Gas Turbine Trip
Boiler Steam Turbine Combined Cycle
Single Shaft Multi Shaft Ratio 1 : 1 1 Gas turbine , 1 HRSG 1 Steam
Turbine Trip GasTurbine Trip Steam Turbine Combined
Cycle Multi Shaft Ratio 2 : 1 2 Gas turbine , 2 HRSG 1 Steam
Turbine Trip Gas Turbine Trip Steam Trip HRSG (Heat
Recovery Steam Generate ) Boiler Gas Turbine Steam Turbine
2.5.1.1 - 5
2.5.1.1 - 6
2.5.1.1 - 7
2.5.1.1 - 8
2.5.1.1 - 9
2.5.1.1 - 10
2.5.1.1 - 11
Gas turbine
Steam Turbine
2.5.1.1 - 12
2.5.1.2 - 1
Boiler Pressure Superheat ,Reheat ,Evaporator ,Economizer ,Preheater ,Drum Safety Valve
Boiler Structure
Boiler ,Expansion Joint ,Bellow Seal Drum
Steam 3
Steam drum separation (a) gravity , (b) mechanical primary (Baffler) and secondary (screen) , (c) centrifugal
3 Drum
Boiler Protection
Boiler Overpressure
Overheat
4 Relief Valve
2.5.1.2 - 3
5 Safety Valve
2.5.1.2 - 4
(Water Level)
Boiler
(Minimum Safe Limit) (Over heating )
Steam
2 2
2
TRIP BOILER
-All Boiler Feed Pump Not Running
-All Circulating Water Pump Not Running
-All Condensate Pump Not Running
-Gas Turbine Trip
-Boiler Bypass Stack Temp. High-High (648 oC)
-Boiler Stack Temp. High-High (154 oC)
-Main Steam Temp. High (575 oC)
-Hot Reheat Steam Temp. High (575 oC)
-Drum Level Low-Low
-Drum Level High-High
-Condenser Hot well Level High-High (458 mm)
-Emergency Close
2.5.1.2 - 5
2.5.1.2 - 6
2.5.1.2 - 7
2.6 - 1
(CONDITION
BASED MAINTENANCE CBM)
2.6 - 2
1.1.
2.6 - 3
1.2
(Breakdown) (Urgent Repairs)
(Productivity) (Quality)
2.6 - 4
:
(High Capacity)
1.3
?
?
2.6 - 5
1. (Availability Performance)
(Equipment Effectiveness) (Technical
Lifetime)
2.6 - 6
2.
?
1.4.
(Maintenance Costs)
1.4.1
2.6 - 7
(Cost) (Result)
2.6 - 8
Maintenance
Capital
Costs
Energy
Losses
Quality
Losses
Work
Environment
Capacity
Losses
Production
Losses
Lost Market
Increased
Investments
(Quality Losses)
( Energy Losses )
(Capital Costs)
35 %
2.6 - 9
(Buffer Stock)
(Just in Time JIT)
(Production Losses)
(Capacity Losses)
(Work Environment)
(Lost Market)
(Increased Investments)
2.6 - 10
2.6 - 11
1.5.1
(Preventive Maintenance) (Corrective Maintenance) (Condition
Monitoring) (Improvement Maintenance)
1.5.2 (Corrective Maintenance)
2.6 - 12
(Fixed Time Maintenance
FTM)
(Condition Monitoring) (Condition Based Maintenance
CBM)
1.7. (Subjective and Objective Condition
Monitoring)
(Subjective Condition Monitoring)
(Objective Condition Monitoring)
2.6 - 14
2
1. (Off-line Condition Monitoring)
2. (On-Line Condition Monitoring)
2
(Unplanned Corrective Maintenance)
(Planned Corrective Maintenance)
2.6 - 15
1.9
1.9.1 ?
2.6 - 16
-
-
-
1.9.2
Mean Time To Failure
MTTF
MTTF
1.9.3 (Maintenance Support Performance)
Mean Waiting Time MWT
MWT
MTTR
2.6 - 17
MTTF
MDT
MWT
A
Tup
Tdm
=
=
=
A=
(Availability performance)
(Time Up)
(Down Time due to maintenance)
Tup
Tup + Tdm
MTTF
MTTF + MDT
MTTF
MTTF + MTTR + MWT
=
2.6 - 18
MTTR
1.9.6
100%
100%
Production
2.6 - 19
1.9.1
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1.9.7
24
24 (Utilization Factor)
16 16/24 = 0.66
8 8/24 = 0.33
3.2
2.6 - 20
1.9.2 %
()
%
%
0
100
8760
730
24
50
50
4380
365
12
80
20
1752
146
4.8
90
10
876
73
2.4
99
1
87.6
7.3
14.4
99.9
0.1
8.76
43
1.4
99.99
0.01
53
4.3
8.6
99.999
0.001
5.3
26
0.86
99.9999
0.0001
32
2.6
0.086
1.9.8
2.6 - 21
A
MTTF
MWT
MTTR
Or
=
=
=
=
X 100 %
X 100 %
MDT = Tdm / a
hours/failure
Tup1
Tdm1
Tup2
Tdm2
Tup3
Tdm3
Tup4
Tdm4
Tup5
T = (Calendar time)
Prod.
Tup
Stop
Tdm
2.6 - 22
MTTF =
1. (Tup)
2. (Tdm)
3. (a)
Tup
Tdm
a
= 940
= 160
= 70
MTTF =
MDT =
940
70 + 1
160
70
= 13.2
= 2.3
MTTR = 0.7
MWT = 1.6
Tup
Tup + Tdm
MTTF
MTTF + MDT
= 85%
940
940 + 160
= 0.85
MTTF
MTTF + MTTR + MWT
2.6 - 23
13.2
13.2 + 0.7 + 1.6
= 0.85
a = -
- FTM
= 70
-
MTTR = 0.7 ..
MWT = 1.6 ..
-PM
MDT = 2.3 ..
-
(MTTR+MWT)
-
-
(Optimistic)
Tdm = a xMDT = 30 x 1.5 = 45 ..
Tup = T-Tdm = 1100 45 = 1055 ..
A=
1055
1055+45
(Optimistic)
a = 30
MTTR = 0.7 ..
MWT = 0.8 ..
MDT = 1.5 ..
= 0.96 = 96%
- 0.85 = 12.9% +
Production = 0.960.85
(Less Optimistic)
Tdm = a xMDT = 50 x 1.9 = 95 ..
Tup = T-Tdm = 1100 95 = 1005 ..
A=
1005
1055+95
= 0.91 = 91%
Production =
0.91 - 0.85
0.85
= 7.1% +
2.6 - 24
(Less Optimistic)
a = 50
MTTR = 0.7 ..
MWT = 1.2 ..
MDT = 1.9 ..
100%
100%
1.
2.
3.
Overall Equipment Effectiveness, OEE = AxPxQ
A = (Availability Performance)
P = (Production Speed Performance)
Q = (Quality Performance)
2.6 - 25
Stoppages
Speed Losses
x 100%
x 100%
x 100%
x 100%
OEE = A x P XQ
2.6 - 26
x 100%
x 100%
x 100%
1.10.
1.10.1
2.6 - 27
(Maintenance Windows)
Production Planning
Production
Maintenance Planning
2.6 - 28
(Production Loss)
100,000 3
300,000
CHANGE
OF
TOOLS
CHANGE
OF
PRODUC
T
SHIFT
CHANGE
STOP
FOR
CLEANING
PRODUCTION PLANNING
MARKET
2.6 - 29
1.10.2
(FTM) (a1) PM PM PM
(b1) PM
2.6 - 30
(C1)
PM
(d1) (a1), (b1) (c1)
(d1) PM
PM
.d1
.a1 PM
.c1
.b1
-.
2.6 - 31
(FTM) (CBM)
CBM FTM
.d1
.a1 PM
.c1
.b1
PM with FTM
-.
PM with CBM
PM FTM
PM CBM
2.6 - 32
TIME UP
WAITING
TIME
REPAIR
TIME
CBM
TIME UP
WITH REPAIR
TIME
PREPARE
AND PLAN
FIND FAILURE
3
( ) 1
2.6 - 33
(Production loss)
( 1
3 )
1.11
OTBD
OTBD
1.11.2 (Fixed-time maintenance FTM )
(FTM ) OTBD
FTM
2.6 - 34
LTE
1.12.
2.6 - 35
1.12.1 ?
1.12.2 ?
1.12.3 ?
1.12.4 ?
( FTM )
1.12.5 ?
1.12.6 ?
1.12.7 (OTBD )
2.6 - 36
1.13.1.
(Random failures - ) (Regular failures- )
1.13.2. ( Failure developing time )
( on-line )
( off-line )
2.6 - 37
1.13.3
1.13.3.1 -
( online )
1.13.3.2 -
1.13.3.3 -
1.13.3.4 -
(FTM )
2.6 - 39
MMEC Maintenance Management Education Center
- ..
- .
- .
- .
- ..
2.6 - 40
2.7 - 1
(Plant Performance)
3
1.
2. ,
3.
d
e
c
1
1
70 80%
,
10%
50% Condenser Unit
Output
39 %
2 Sankey Diagram
500 MW
MECHANIC
2.7 - 2
Carnot
Rankine Cycle
Thermodynamic Power Plant
Boiler Combustion
Performance
Boiler Efficiency and Optimisation
Turbine Performance
Condenser Performance
Feed Water Heater Performance
Cooling Tower
Boiler Efficiency Turbine
Efficiency
1. Boiler Efficiency 2
Boiler efficiency ( B) =
output
* 100
input
input - loss
* 100
input
Test Instrument
Boiler efficiency ( B) = 100 -
Loss
* 100
input
Composition Lab
4 .
Steady state 1 .
Test condition
System isolation , soot blower, boiler blow down, Fan angle, Draft balancing ,
burner tilt , burner damper
Equipment condition Running, cleaning
Heat in feedwater
Output
2.7 - 5
3600
Heat Consumption =
where Ms
H1
Hr
MR/H
H2
H3
his
Mir
hir
Pg
=
=
=
=
=
=
=
=
=
=
2.7 - 6
2.7 - 7
Performance Assessment
Performance
Survey
1.
2.
3.
4.
Performance Assessment
Performance Assessment
1. Performance Assessment
Performance Assessment
- Performance
- Performance
- Performance
- Performance Performance
- Performance
2. Performance Assessment
Performance Assessment
2.1
2.2
2.3
2.4 Performance
2.5
2.6 Performance
3.
3.1
2.7 - 8
- P&I Diagram
- Design Data
- Performance Data
Reference Heat Rate
Actual Heat Rate
3.2
Instrument Performance Assessment
Performance Instrument
Location
Pressure
Main Steam
First Stage
Cold Reheat
Hot Reheat
Crossover
Condenser
Feed Water Heater Extraction
Feed Water Heater Inlet
Feed Water Heater Outlet
Feed Water Shell Pressure
Feed Water Heater Drain Outlet
Final Feed Water
Condensate
Circulating Water Inlet / Outlet
Economize Gas Exit
Air Heater Inlet / Outlet (Gas and Air)
Amblent
Superheat Spray
Reheat Spray
()
()
2.7 - 9
Temperature
Flow
()
()
Auxiliary Steam
Make Up Water
Fuel
GT. Exhaust
HRSG. Inlet / Outlet Gas
Include :
Exit Gas O2, CO2, CO Instrument
Electrical Generation Instrument
Auxiliary Electrical Power Consumption Instrument
Instruments in Plant Audit Section
3.3
Performance Performance
Performance 3
-
- Performance Test Report
-
Plant Heat Rate Uncontrollable Parameter
Ambient Condition, Fuel Properties Correct Standard Condition
Design Condition
3.4 Performance
Performance Reference
Data Plant Performance
- Performance (Actual Performance)
Performance (Reference Performance) Uncontrollable
Parameter Ambisnt Condition, Fuel Properties Correct
Standard Condition
- Loss
Performance
Loss
- Performance Test
- Equipment Performance Test
- Heater Balance Code Program
- Performance Tutorial
- Performance Parameter Diagnostic
- Heat Rate Logic Tree
3.6
Performance Assessment
- Performance Performance
- Performance Boiler, Turbine, Cooling
Tower etc. Performance
- Performance
- Performance
4. Performance Assessment
Performance Assessment Report
1.
,
2.7 - 11
2.
3.
4.
5.
Design Data
(Target) Thermal Kit
6.
7.
2.7 - 12
Plant Cycle
Cycle
1. Plant Cycle
2. Enthalpy
3. Steam Quality Enthalpy Exhaust Steam
4.
5. Turbine Cycle Efficiency
6. Turbine Cycle Efficiency
7. Turbine Cycle Efficiency Condenser Back Pressure
8. Boiler Efficiency
9. Overall Plant Efficiency
10. Gross Net Plant Heat Rate
11. Factor Boiler Efficiency
2.7 - 13
2.7 - 14
2.7 - 15
Segment B
Turbine 1 HG abs (Back Pressure
hr
=
Enthalpy (Sensible Heat)
hfg
=
Enthalpy Steam / Water Mixture (Latent Heat)
Steam Table :
=
48.02 BTU/LB
hr
hfg
=
1048.6 BTU/LB
hsteam =
48.02 + (0.9) 1048.6 BTU/LB
=
48.02 + 943.74 BTU/LB
=
991.76 BTU/LB
Turbine Enthalpy Steam
Turbine 1439.7 991.76 = 447.94 BTU/LB
Mass Flow Rate 100,000 LB/HR Turbine 44.8 106
BUT/HR 13.126 MW (1 BTU = 0.000293 KW-HR.) Mechanical Electrical
Loss
Steam Turbine Condenser
(Latent Heat) Circulating Water
Turbine 80 F. ( Saturation Temperature
1HG. (0.5
PSIA) Moisture Content 10%, Latent Heat 943.74 BTU/LB
2.7 - 16
447.94
= 0.3225 32.35%
1389.5
= 67.75% Condenser
Turbine Cycle Boiler
2.7 - 17
Segment C (Part I)
2 (FIG.1C.1) Main Steam 850 F 1000 F
Turbine 1519.6 BTU/LB 850 F
(1439.7BTU/LB)
Turbine = 80F Enthalpy = 991.76 BTU/LB
Turbine
1519.6 991.73 = 527.84 BTU/LB
Feedwater Fluid Boiler
1519.6 50.2 = 1469.4 BTU/LB
Turbine Cycle =
527.84
= 35.9%
1469.4
2.7 - 18
521.6
= 37.9%
1,375
2.7 - 19
1,389.5
= 1,635 BTU/LB
0.85
Boiler 10 5 / Boiler
163.5 10 6 BTU/HR
Boiler
Heating Value = 10 5 BTU/LB 16,350 LB/HR
(8.175 TON/HR) Fuel Oil Heating Value 18,000 BTU/LB Fuel Oil 9,100
LBS/HR 1137.5 Gallon/HR ( Fuel Oil 8 LB = 1 Gallon)
Boiler
A.
B. Heating Value
C. Boiler ( Leak Flow Steam Flow )
D. (Enthalpy) Feedwater Boiler
E. Enthalpy Steam Boiler
Boiler =
2.7 - 20
Plant Efficiency =
448
= 0.274 (27.4%)
1,635
2.7 - 21
Segment D
Boiler = 85% Loss 15%
A.
B. (ASH)
C. Boiler Blow Down
D. Soot Blowing
E. Heat Radiation
1D.1 Turbine Generator 70 MW Boiler 550,000 LB/HR
1,200 PSIA, 950F Feedwater = 370F
70 MW 40,000 LB/HR Fuel Oil Heating
Value 180,000 BTU/LB Boiler = 720 10 6 BTU/HR
Stack Loss Gas Stack
Boiler Fuel Gas Fuel Oil
Boiler
(Carorific Value) 2 Higher Heating
Value Low Heating Value
Lower Heating Value Vapor Loss
()
Boiler Heating Value
Lower Heating Value Boiler
2.7 - 23
Segment E
Excess Air Boiler Boiler
Loss Stack Loss Exhaust Gas Stack
Stack Loss
Excess Air Exhaust Gas Stack Loss
1. Carbon
2. Hydrogen
3. Sulfer
, , ()
C + O2 - - - > CO2 + Heat (14,600 BTU)
1 2.66 3.66
14,600 BTU
1 8 61,500 BTU
2H + O2 - - - > H2O + Heat (61,500 BTU)
1 4,000 BTU
Corrosion
1. Heating Value
2. ( Ideal)
2.7 - 24
(CO)
C (1 LB) + O2 (1.333 LB) - - - > CO (2.33 LB) + 4,400 BTU)
Boiler (Pulverized Coal)
(Atomized Fuel Oil)
Ideal
Combustion Air ( 23%
77% )
Boiler Force Draft Fan
Boiler Stack
( Combustion Air)
Flue Gas Excess Oxygen 3-4%
2.5-3%
Stack
(ASH)
Flue Gas
2.7 - 25
2.7 - 26
2.7 - 27
2.7 - 28
2.7 - 29
2.7 - 30
2.7 - 31
Segment A
1. (Energy Loss)
2.
3. () Steam Table 315C 105 bar(a)
Superheated Steam
Segment B
Percentage Steam / Water
Turbine 482C 61.2 bar(a) Turbine 26.7C
1HG abs. 12% Moisture Content, Steam Flow Rate 90.7 ton/hr
Enthalpy Steam Turbine
[hsteam = hr + (x) hfg]
Useful Turbine Work
Segment C (Part I)
(, ) 1-4
1. Main Steam Turbine Cycle ............( / )
2. Main Steam Turbine Cycle ............( / )
2.7 - 32
3.
4.
5.
6.
Segment D
2.
3.
4.
5.
B. Loss Boiler
Boiler
..................
1 ..............
............................(, )
(Lower, Higher) Heating Value Vapor Loss
Segment E
1. (Fossil Fuel)
3
A. .
B. .
C. .
2. 1
A. .
B. .
C. .
3. () Boiler
4. ..............
5. ...............
6. () Heating Value
7. Boiler Furnace
2.7 - 34
2.7.1 - 1
(COMBINED CYCLE POWER PLANT PERFORMANCE)
1
HEAT RATE, EFFICIENCY OUTPUT
HEAT RATE
Heat Rate =
Heat Consumption
Energy Output
2.7.1 - 2
Efficiency =
Energy Output
Heat Consumption
1
100%
Heat Rate
3413
BTU
)
Heat Rate : (
kWh
860
kCal.
)
Heat Rate : (
kWh
100%
100%
2.7.1 - 3
2
3
4
First Generation
Second Generation
Third Generation
50 90 MW
70 250 MW
Gas Turbine Small Size
& Heat Recovery Feedwater Heat Recovery Feedwater
Application Repowering
Cogeneration From 1949 Heating CC From 1968 Heating CC In The 1990s
1968
1999
Steam Cycle Non-Reheat Single Or Non-Reheat, Single , Two Reheat , Three Pressure
Two Pressure
& Three Pressure
None
GT Water And Steam DLN Combustion With
Emission
Injection Plus SCR Natural Gas And Wtr /
Control
Installed In The HRSG Steam Inj With Oil Fuel
Gas Path For NOX Plus SCR Installed In
Control
HRSG
Distillate Oil / Natural Natural Gas / Distillate Oil Natural Gas / Distillate Oil
Fuel
Gas
/ Low BTU Gas / Oil
/ Low BTU Gas
3
2.7.1 - 4
2.7.1 - 5
8 T-S P-V
2.7.1 - 6
2500
FIRST STAGE TURBINE NOZZLE GENERAL ELECTRIC
FIRING TEMPERATURE 9
9 FIRING TEMPERATURE
FIRING TEMPERATURE
10
FIRING TEMPERATURE
FIRING TEMPERATURE
10
2.7.1 - 7
2.7.1 - 9
2.7.1 - 10
2.7.1 - 11
COMPRESSOR EVAPORATIVE COOLING 20
CHILLING
2.7.1 - 12
2.7.1 - 13
2.7.1 - 14
27 RANKINE CYCLE
2.7.1 - 16
2.7.1 - 17
2.7.1 - 18
1 HEAT RATE
HEAT RATE
2 FIRING TEMPERATURE
3 PRESSURE RATIO
4 OUTPUT HEAT RATE
8 THROTTLE PRESSURE
10 CONDENSOR PRESSURE
2.7.1 - 19
2.8.1 - 1
10%
10% 90%
-
- /
-
- OPERATION
-
-
1)
(Treat)
2) (TERMINATE)
3)
(TOLERATE)
4) (TRANSFER)
2.8.1 - 2
INFORMATION & COMMUNICATION
2.8.1 - 3
2.8.1 - 4
?
Boss
/ Loss Loss of People
Loss of Property
Loss of Process
Loss of Environment
? (Ground Root)
2.8.1 - 5
2.8.2-1
(OMA) (Owner)
(Operator)
20 80%
2.8.2-2
1.
2.
3.
85%
/
(THE MORE ADVANCED TECHNOLOGY THE MORE SAFETY DEVELOPMENT)
2.8.2-3
1.
(
)
Material
Environment
Risk
- inadequate
knowledge/standard
- inadequate Engineering Design
- Lack of Prevention Maintenance
- inadequate knowledge and
nature Harzard
- inadequate standard control
- Season
- Political/Law
- Community
2.8.2-4
(BRAND)
2.
4
1. (Management Concept)
2. (Management Information System)
3. (Performance Standard)
4. (Measurement and Evaluation System)
2.1 (Management Concept)
(
)
(Input activities)
(Output activities)
(Loss Control) (Total
Management)
2.8.2-5
2.8.2-6
3.
ISO
9001:2000
Distributed
Control System (DCS)
(DCS)
(Interlock)
Critical Process Task Analysis
,
,
,
Balance Score Card
Suggestion, QCC, 5 .
Task Analysis
2.8.2-7
Specific Audit
, ,
5.
3
1. ,
, Specific Audit, ,
, QCC, , 5 ., / ,
, , ,
, , , , /
,
2.
, ,
3.
,
2.8.2-8
? Risk/Loss
/
1. Operating/Financial
(Identify Work)
2. /
(Standard Set)
3.
(Measurement)
4.
(Evaluating)
5.
(Commendation & Correction)
2.8.2-9
2.8.3 Finance
2.8.3 - 1
(Financial Management)
1.
1.1
1.2
1.3
2.
2.1
2.2
2.3
2.4
3.
3.1
3.2
3.3
4.
4.1
4.2
5.
5.1
5.2
5.3
5.4
2.8.3 - 2
(Financial management) :
1.
2.
3.
4.
5.
1.
1.1
- (Cash
Flow)
(Liquidity)
1.2
,
,
1.3
2
1.
2.
(Risk)
2.8.3 - 3
2.
2.1
2.2
1.
2.
3.
4.
5.
2.3
1.
2.
3.
2.4
2
2.8.3 - 4
-
, ,
,
-
,
-
-
-
-
-
-
-
-
2.8.3 - 5
3.
3
1.
2.
3.
4.
1.
2.
3.
4.
5.
6.
3.1
3.2
2.8.3 - 6
3.3
1. (Money measurement)
2. (Business entity)
(1 .. 31 ..)
5. (Going concern)
2.8.3 - 7
6. (Cost)
7. (Realization)
2
(1)
(2)
8. (Matching)
9. (Accrual)
2
10. (Consistency)
11. (Disclosure)
2.8.3 - 8
12. (Conservatism)
13. (Materiality)
2.8.3 - 9
4.
4.1
1. (Balance Sheet)
2. (Income Statement)
3. (Statement of Changes in chair holders equity)
4. (Statement of cark flow)
4.1.1 (Balance Sheet)
-
-
- ( )
-
-
-
-
2.8.3 - 10
4.1.2
4.1.3
4.1.4
4.2
1.
2.
35
1.
2.
3.
4.
5.
3.
1. ... 1 59
7
2.8.3 - 11
2. ... 1 58 2
2
3. .. 30 .. 31 .. 40
()
15
4. ... 50 68 69
150
1
5. ... 51 67
2 6
... 51
... 51
6 6
1-5
2.8.3 - 12
6.
5
2.8.3 - 13
POWER PLANT
31 2546 2545
2546 ()
2545 ()
639,956,833.73
32.44%
621,023,555.48
34.29%
3,511,300.00
0.18%
3,511,300.00
192,895,935.78
167,807,317.48
0.18%
9.78%
8.51%
3,511,300.00
84,323,060.78
87,834,360.78
187,531,064.72
156,852,461.59
0.19%
4.66%
4.85%
10.35%
8.66%
22,573,558.33
24,117,533.20
1.14%
1.22%
17,748,008.06
21,322,406.06
0.98%
1.18%
46,691,091.53
2.37%
39,070,414.12
2.16%
53.27% 1,092,311,856.69
60.31%
1,050,862,478.52
160,000,000.00
30,000,000.00
71,200,000.00
8.11%
1.52%
3.61%
30,000,000.00
71,200,000.00
1.66%
3.93%
261,200,000.00
644,631,430.88
15,878,041.99
130,327.27
13.24%
32.68%
0.80%
0.01%
101,200,000.00
597,802,119.58
19,580,293.79
301,720.30
5.59%
33.01%
1.08%
0.02%
921,839,800.14
46.73%
718,884,133.67
39.69%
1,972,702,278.66
2.8.3 - 14
POWER PLANT
31 2546 2545
2546 ()
2545 ()
1,673,766,812.60
98.91%
1,587,856,629.43
99.02%
10,540,334.89
0.62%
10,441,412.66
0.65%
7,964,442.74
0.47%
5,194,515.11
0.32%
18,504,777.63
1.09%
15,635,927.77
0.98%
1,692,271,590.23
100.00%
1,603,492,557.20
100.00%
945,950,515.17
55.90%
888,211,566.20
55.39%
320,876,162.98
18.96%
318,782,750.20
19.88%
2,690,458.09
0.16%
9,078,760.49
0.57%
1,269,517,136.24
75.02%
1,216,073,076.89
75.84%
422,754,453.99
24.98%
387,419,480.31
24.16%
63,168.09
0.00%
352,718.22
0.02%
112,418,972.98
6.64%
118,552,974.71
7.39%
310,272,312.92
18.33%
268,513,787.38
16.75%
8.62
7.46
36,000,000
36,000,000
2.8.3 - 15
POWER PLANT
31 2546 2545
1 2545
360,000,000.00 615,600,000.00
31 2545
360,000,000.00 615,600,000.00
31 2546
360,000,000.00 615,600,000.00
2.8.3 - 16
565,252,261.07
1,540,852,261.07
268,513,787.38
268,513,787.38
(162,000,000.00)
(162,000,000.00)
671,766,048.45
1,647,366,048.45
310,272,312.92
310,272,312.92
(162,000,000.00)
(162,000,000.00)
820,038,361.37
1,795,638,361.37
POWER PLANT
31 2546 2545
2546 ()
()
()
()
()
2545 ()
310,272,312.92
268,513,787.38
83,714,020.22
2,506,431.37
2,063,398.84
(534,146.69)
3,224,604.78
(6,592.97)
68,058,968.49
253,119.26
1,887,315.66
(21,682.30)
9,078,760.49
-
(7,872,161.39)
(13,018,254.73)
(7,991,404.80)
171,393.03
13,490,693.92
2,128,790.22
(22,045,201.90)
1,062,063.28
(10,107,757.99)
(6,047,758.47)
(9,910,231.84)
27,638,361.00
388,149,084.72
328,359,743.06
(160,000,000.00)
1,296,325.66
84,323,060.78
(130,457,136.08)
(853,500.00)
212,033.64
(139,729,492.14)
(204,837,749.64)
(140,370,958.50)
(2,378,056.83)
(162,000,000.00)
(3,311,070.63)
(162,000,000.00)
(164,378,056.83)
(165,311,070.63)
18,933,278.25
621,023,555.48
639,956,833.73
22,677,713.93
598,345,841.55
621,023,555.48
80,896.37
117,682,894.29
377,532.19
107,756,214.20
2.8.3 - 17
5.
5.1
1.
2.
3.
4.
2.8.3 - 18
5.2
5.3
1.
2.
3. (Static-nature)
(Dynamic nature)
4.
5.
6.
7.
2.8.3 - 19
5.4
1. (Horizontal analysis)
2. (Vertical analysis)
3. (Ratio analysis)
1
2
2.8.3 - 20
4
1. (Liquidity ratios)
2. (Profitability ratios)
3. (Efficiency ratios)
4. (Financial policy ratios)
2.8.3 - 21
= 365x ()
= ()
= 365x ()
= ()
= 365x ()
Cash Cycle
= +
()
= x100
=
x100
= x100
= x100 (%)
2.8.3 - 22
x100 (%)
= ()
2.8.3 - 23
:
1.
2.
3.
4.
5.
6.
: /
1
:
1 : . / .
: . / . .
:
:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
2.8.3 - 24
2.8.4 - 1
(Operator Ranking)
Local Board Shift Charge
1
1.
1.1 1 (Auxiliary Plant Operator) 3
1.1.1 (Local Plant Operator)
1.1.2 (Flue Gas
Desulfurization Plant Operator)
1.1.3 (Water Treatment Plant Operator)
1.2 2 3
1.2.1 (Board Operator)
1.2.2
1.2.3
1.3 3 Shift Charge, Assistant Shift Charge , Shift Supervisor
2
(1) 1
(2) 2
(3) 3
(4) 4
1
3
3.1
3.1.1
2.8.4 - 2
3.2
3
3.2.1
3.2.2
3.3 (Certificate)
3.4
A = 100-86
B = 85-71
C = 70-56
D = 55-50
F 50
4
4.1
4.2 6
4.3 6
4.4 (Certificate)
5 1
5.1
5.1.1 4
5.1.1.1 General Introduction , Power Plant Orientation
Plant Safety
5.1.1.2
C
5.1.1.3
4
2.8.4 - 3
5.1.2 3
5.1.2.1 4
5.1.2.2 Power Generation Transmission
2 Power Principle 3
5.1.2.3 4
6
5.1.2.4
C
5.1.2.5
3
5.1.3 2
5.1.3.1 3
5.1.3.2 Power Plant System Description
4.1 ( ) 4.2 (
) Power Plant Attendant 5
5.1.3.3 3
6
5.1.3.4
C\
5.1.3.5
2
5.1.4 1
5.1.4.1 2
1
1
5.1.4.2 Simulator
) 6.2 (
) C
5.1.4.3 2
6
1
1
1 1
5.1.4.4 ,
5.1.4.5
B
5.1.4.6
1
5.2
5.2.1 4
5.2.1.1 General Introduction , Power Plant Orientation
Plant Safety
5.2.1.2
C
5.2.1.3
4
5.2.2 3
5.2.2.1
4
5.2.2.2 Flue Gas Desulfurization Description
Power Generation Transmission 2
5.2.2.3
4 6
2.8.4 - 5
5.2.2.4
C
5.2.2.5
3
5.2.3 2
5.2.3.1
3
5.2.3.2 Power Principle 3
Power Attendant
5.2.3.3 Simulator RBTP.
Simulator Operation Interface System (OIS.)
C
5.2.3.4
3 6
5.2.3.5
C
5.2.3.6
2
5.2.4 1
5.2.4.1
2
5.2.4.2 Power Plant System Description
4.2
5.2.4.3 Simulator Simulator
Beginning Level 6.2
C
5.2.4.4
2 6
2.8.4 - 6
5.2.4.5 ,
5.2.4.6
B
5.2.4.7
1
5.3
5.3.1 4
5.3.1.1 General Introduction , Power Plant Orientation
Plant Safety
5.3.1.2
C
5.3.1.3
4
5.3.2 3
5.3.2.1 4
5.3.2.2 Water Treatment Description Power
Generation Transmission
5.3.2.3 4
6
5.3.2.4
C
5.3.2.5
3
5.3.3 2
5.3.3.1 3
2.8.4 - 7
2.8.4 - 8
6 2
6.1
6.1.1 4
6.1.1.1 1
1
6.1.1.2 Power Plant Execution
6.1.1.3
1. Modern Safety Management (MSM.)
2. ISO 14001
3. ISO 9001:2000
4.
6.1.1.4
6 (
)
6.1.1.5
6.1.1.6
B
6.1.1.7
4
6.1.2 3
6.1.2.1 4
6.1.2.5
6.1.2.6
B
6.1.2.7
3
6.1.3 2
6.1.3.1 3
6.1.3.5
A
6.1.3.6
2
6.1.4 1
6.1.4.1 2
6.1.4.2
2 2
6.1.4.3
6.1.4.4 ,
2.8.4 - 10
6.1.4.5
A
6.1.4.6
1
6.2
6.2.1 4
6.2.1.1
1 1
6.2.1.2 Power Plant Execution
6.2.1.3
1. Modern Safety Management (MSM.)
2. ISO 14001
3. ISO 9001:2000
4.
6.2.1.4
B
6.2.1.5
4
6.2.2 3
6.2.2.1
4
6.2.2.2 Advanced Operator Training (AOT)
6.2.2.3
1. Operation And Maintenance Agreement (OMA.)
2. Power Purchased Agreement (PPA.)
6.2.2.4
4 1
2.8.4 - 11
6.2.2.5
B
6.2.2.6
3
6.2.3 2
6.2.3.1
3
6.2.3.2
3 1
6.2.3.3
B
6.2.3.4
2
6.2.4 1
6.2.4.1
2
6.2.4.2
2 1
6.2.4.3 ,
6.2.4.4
A
6.2.4.5
1
2.8.4 - 12
6.3
6.3.1 4
6.3.1.1 1
1
6.3.1.2 Power Plant Execution
6.3.1.3
1. Modern Safety Management (MSM.)
2. ISO 14001
3. ISO 9001:2000
4.
6.3.1.4
B
6.3.1.5
4
6.3.2 3
6.3.2.1 4
2.8.4 - 13
6.3.3 2
6.3.3.1 3
6.3.3.2
3 1
6.3.3.3
A
6.3.3.4
2
6.3.4 1
6.3.4.1 2
6.3.4.2 2
1
6.3.4.3 ,
6.3.4.4
A
6.3.4.5
1
7 3
7.1 4
7.1.1 1
2
7.1.2 Turbine & Boiler
7.1.3
3
3
2.8.4 - 14
2.8.4 - 15
7.3 2
7.3.1 3
7.3.2 3 2
7.3.3 30
20
7.3.4 Technical Paper 2
7.3.5 Trip 2,190
1 Trip
7.3.6 ,
7.3.7
A
7.3.8
2
7.4 1
7.4.1 2
7.4.2 2 2
7.4.3 30
20
7.4.4 Technical Paper 2
7.4.5 ,
7.4.6
A
7.4.7
1
2.8.4 - 16
2.8.4 - 17
1
4
2
3
2.8.4 - 18
2.8.4 - 19
POWER PRINCIPLE
1 Personnel Safety
2 Fire Safety
3 Hazardous Substance
4 Safety In Electrical Maintenance
5 Respiratory Protection
6 Plant Science
7 Plant Cycle
8 Plant System
9 Plant Auxiliary
10 Boiler
11 Turbine
12 Basic Power Plant Operation
13 Fuel & Combustion
14 Plant Instrumentation
15 Instrumentation & Control
16 Basic Electricity
17 Power Generation
18 Plant Protection
19 Electrical System & Equipment
20 Gas Turbine & Diesel
21
22
23
2.8.4 - 20
4.1
2.8.4 - 21
4.1
Programmable Logic Control
Gas System ( H2 & CO2 )
Mark V. Overview & Software Usage
Mark V Hardware Configuration
Gas Turbine Control
Ventilation & Lighting
Gas Turbine Protectiion
Water & Waste Water Treatment Plant
Close Circuit TV. & Radio
Telephone & Intercom
Generator Maintenance
Air Condition
2.8.4 - 22
4.1
2.8.4 - 23
4.2
Introduction One Through Boiler
Fuel Oil & Fuel Gas System
Combustion Air & Fuel Gas System
Boiler Feed Water System
Information System
Boiler Vant & Drain
Soot Blower System
Burner Management System
Auxiliary Boiler
Boiler Operation
Steam Turbine Component
Lube Oil System
Service & Control Air System
CW Cooling System
CCCW System
Make Up & Condensate System
Condenser Polishing System
HP / IP / LP Stop & Control Valve
Turbine Supervisory
Condenser Vacuum System
Turbine Governer Control ( EHC )
Condenser Tube Cleaning System
HP / IP / LP Bypass Valve
Power Distribution System
Grounding & Lighting Protection
Generator Construction & Monitoring
Generator Gas Supply & Cooling Water System
Generator Operation
2.8.4 - 24
4.2
2.8.4 - 25
In - Plant Safety Rule
Work Order System
Power Plant Diagram
Plant System Operation ( Gas Turbine )
Plant Equipment Operation ( Steam Turbine )
Plant Equipment Operation ( HRSG )
General Plant Arrangement
Plant Equipment Operation ( Instrument & Control )
Plant Equipment Operation ( Electrical Equipment )
Report Writing
Emergency Procedure
Work Permit & System Isolation
Plant System
Plant Protection
Plant Science
Plant Cycle
Maintenance Concept
2.8.4 - 26
6.1
2.8.4 - 27
6.2
2.8.4 - 28
1.
2.
3. Ratio ?
4.
2.8.4 - 29
Power Station Engineering & Economy by Bemhardt G.A. Skrotzki and William a.Vopat
Applied Thermodynamics by P.L. Ballaney
A Course in Electrical Power by Soni, Gupta & Bhatnagar
A Text Book of Electrical Technology by B.L. Theraja
Steam its generation and use 40 th Edition by Babcock & Wilcox , aMcDermott Company, ABB Asea Brown
Boveri
Combustion Fossil Power by Joseph G. Singer, PE Forth Edition
Modern Power Station Practice Third Edition, Incorporating Modern Power System Practice British
Electricity International, London
Hand Book For Thermal & Nuclear Power Engineer, Thermal & Nuclear Power Engineering Society
Practical Coss Control Leadership/The property Damage Accident by Frank E. Bird, Jr. George L. Germain
Ratchaburi Thermal Power Plant Instruction Manual by Mistubishi Heavy Industries, LTD.
Ratchaburi Combined Cycle Power Plant Gasturbine Manual by General Electric Company