Please include the tests shown in red in your test schedule. With these comments the test schedule is approved as per the contract.
Sr. No 1
DAY DAY 1
Measurement of Insulation resistance at 20,60,120 and 600 sec, calculation of Absorption Ratio & PI.PI shall be at least 2.
CL. 16.6
DAY 1
3 4 5
Vector group test. Load loss and impedance voltage measurement No load loss measurement at 90%,100%,110% of rated voltage and no load amp. measurement
Measurement of winding resistance at different taps in ascending order & descending order
CL 16.2
DAY 1
7 8 9 10 11 12
Measurement of transformer oil breakdown voltage Separate source voltage withstand test Induced overvoltage withstand test. Report preparation and signature Magnetic Balance test Capacitance & Tan delta test on T/F winding with LV set / HV set
13 14
CT Polarity test of all CTs Insulation Resistance Measurement of Core insulation with 2kV AC/DC
15 16 17
2kV test on Marshalling Panel Functional test of Buchholtz, OTI,WTI,CCU,PRV etc Please show the incorporation of JSL/Mecon comments on the T/F to JSL inspector
18
Please note that all test instruments/equipments have valid calibration certificates traceable to National Laboratories and shall be made available to JSL inspector.