PROJECT REPORT

ON

UPGRADATION OF ROAD FROM KACHNUMBAL TO CHATTERGUL


SUBMITTED BY GULZAR AHMAD (ST-436558-0) (BRANCH CIVIL)

UNDER THE ESTEEMED GUIDANCE OF

DR O.N.WAKHLU (FIE)

Pavement Design Saloora to Hajam mohalla Daribal

Assuming a uniform traffic growth rate r And the design life N (Cumulative ESAL) n

= = = T0 X

6% 10 years 365 X (1+0.01r)n -1 x L 0.01r

Where L= lane distribution factor & L=1 for Single Lane T0


=

No of commercial vehicles per day in the year of opening X VDF

Traffic Details No of HCV No of MCV T0 ESAL = = = 14 , HCV(L)=308/440*10=7, HCV(UL)=.7*10=7 40 , MCV(L)=.7*29=20, MCV(UL)=.7*29=20

(7x2.86+7x0.31+20x0.34+20x0.02) =29.39 = 4811 x = 29.39 = 1,41,395

Recommended CBR of KM Ist ,2nd,3rd

5.0% (T-4 Category) 300mm = 300mm = = = = 125mm 75mm 50mm 25mm

Thickness required from the fig no 4 of SP 72= Thickness provided Details of Pavement GSB WBM II 50mm BM equivalency Value 100mm Semidence

Assistant Executive Engineer

Executive Engineer Ganderbal