COST BREAK DOWN FORM

PROJECT NAME. REWELDING STEEL STRUCTURE Client : V-TEC


K.R
Prepared By

TH.S
Checked By

TH.T
Approved By

12.12.12
Date

Item A 1 2 3 4 5 6 7

Description

Q'ty

Unit

Unit P

Amount

Construction cost
Scaffloding work Consumable cost Welding Rod (E7016) Painting Prepare weld & welding NDE test (PT) Mobile Crane 1 1 1 1 1 1 1 Lot Lot Lot Lot Lot Lot Lot 1,450,000 185,000 180,000 55,000 3,250,000 125,000 220,000 1,450,000 185,000 180,000 55,000 3,250,000 125,000 220,000

Note: -This scope are joint prepare ,weld and NDE confirm -This price base on 2500 points only. -Sch of work 75 working days. B Option Price: Reweld&Repair 0-10 M. Reweld&Repair 10-20 M. 1 point = 1 point = Sub Total Cost Sub Total OPT Vat Total NOTE : Cost ( Baht ) Cost 25% 7% 2,100 2,800 THB THB -

5,465,000 5,465,000 1,366,250 478,188 7,309,438