Cost Break Down Form: Project Name. Rewelding Steel Structure Client: V-TEC
Cost Break Down Form: Project Name. Rewelding Steel Structure Client: V-TEC
TH.S
Checked By
TH.T
Approved By
12.12.12
Date
Item A 1 2 3 4 5 6 7
Description
Q'ty
Unit
Unit P
Amount
Construction cost
Scaffloding work Consumable cost Welding Rod (E7016) Painting Prepare weld & welding NDE test (PT) Mobile Crane 1 1 1 1 1 1 1 Lot Lot Lot Lot Lot Lot Lot 1,450,000 185,000 180,000 55,000 3,250,000 125,000 220,000 1,450,000 185,000 180,000 55,000 3,250,000 125,000 220,000
Note: -This scope are joint prepare ,weld and NDE confirm -This price base on 2500 points only. -Sch of work 75 working days. B Option Price: Reweld&Repair 0-10 M. Reweld&Repair 10-20 M. 1 point = 1 point = Sub Total Cost Sub Total OPT Vat Total NOTE : Cost ( Baht ) Cost 25% 7% 2,100 2,800 THB THB -