DENSO (DIOR) NEW FACTORY PROJECT AT JHAJJAR, HARYANA HRV CALUCULATION SHEET

AS PER DESIGN Required Condition A/C Room M. Vent


Summer Winter

Room Size X 10.0 15.5 10.0 4.5 Y 8.2 8.2 3.0 Area m2 82.0 82.0 13.5

Room H m 4.2 4.2 4.2 4.2 V m3 344.4 533.8 344.4 56.7

Ventilation Air Change Rate AC 6 6 6 6 CMH 2,066 3,203 2,066 340 Occupant P 34 CMH/P Required CMH

SELECTED EQUIPMENT Marathon Make MODEL GPN30061 GPN30061 GPN30061 GPN30061 QTY 2 3 2 1 TOTAL AIRFLOW CMH 2,400 3,600 2,400 1,200

Remarks

43 20 43 20 43 20 43 20 -

Kaizen Area Maintenanec Room Improvement Welding Room

Supply

2 3 4

8.2 127.1

GPN30061-1200CMH

1 2

Kaizen Area Maintenanec Room Improvement Welding Room DG room

43 20 43 20 43 20 43 20 43 20

10.0 15.5 10.0 4.5 2.5

8.2 8.2 3.0 2.0

82.0 82.0 13.5 5.0

4.2 4.2 4.2 4.2 2.5

344.4 533.8 344.4 56.7 12.5

6 6 6 4 3

2,066 3,203 2,066 454 38

GPN38061 GPN38061 GPN38061 GPN30061

1 2 1 1 1

2,500 5,000 2,500 1,200

8.2 127.1

Exhust

3 4 4

Havel Make- 70CMH

DENSO (DIOR) NEW FACTORY PROJECT AT JHAJJAR, HARYANA HRV CALUCULATION SHEET

AS PER DESIGN Required Condition A/C Room M. Vent


Summer

AS PER SMCCI H.O. CALCULATION SELECTED EQUIPMENT Ventilation Air Change Rate TOTAL AIRFLOW CMH AC CMH Occupant P 26 CMH/P Required CMH MODEL SELECTED EQUIPMENT DAIKIN QTY TOTAL AIRFLOW CMH DAIKIN

Room Size X Y Area m2

Room H m V m3

Ventilation Air Change Rate AC CMH Occupant P 34 CMH/P Required CMH

Winter

28 28 28 -

MODEL

QTY

CPU room Medical room Education room

HRV-1

2 3

HRV-2

Multipurpose room

28

1 2

Meering room1 Meering room2 Guest room1 Guest room2 Lobby

28 28 28 28 28

HRV-3

3 4 5

Office VIP room Financial room Meeting room3

28 28 28 28

HRV-4,5,6

2 3 4

HRV-7

1 2

QA room QA office

25 28

25 20