(r's determination following suspension)- Clause 42.2 (Failure to give possession)- Clause 50 (Contractor to search)- Clause 65.

5 (Increased costs arising from special risks)- Clause 69.4 (Contractor's entitlement to suspend work)- Clause 70 (Changes in cost and legislation)Additions are provided for without any form of of his costs, that is then a sum to which he is entitledunder the contract. Clause 53.5 (Payment of claims) assists in this argument, asamounts determined by the Engineer as due in respect of claims are to beincluded in any interim payment. The difficulty with clause 53 is to know how itrelates to other provisions of the contract. "Claim" is undefined. It is submitted,however, that there can be no genuine doubt that the Contractor is entitled to bepaid for claims as soon as they have been ascertained in whole or in part.