Example Schedule Simulation - Updated
Example Schedule Simulation - Updated
A
B
C
D
E
F
G
Distribution
Triangular
Uniform
Normal
Uniform
Triangular
Normal
Uniform
Start
0
7.344
7.344
7.344
12.357
13.830
21.468
L
4
4
8
6
6
5
5
M
6
6
2
9
8
1
7
U
8
11
-
Duration
7.3440
5.0126
6.4857
6.0040
9.1110
4.6262
6.4320
C (3,5,8)
C
Mean
St. Dev.
Mean St. Error
Minimum
First Quartile
Median
Third Quartile
Maximum
Skewness
26.306
1.664
0.053
21.497
25.067
26.261
27.382
32.699
0.243
End
7.344
12.357
13.830
13.348
21.468
18.456
27.900