Date..
Notice of the discovery of an Item of Geological and/or Archaeological Interest In accordance with Clause 27.1 of the Conditions we write to give you notice of the discovery on site of .. We are complying with the general obligations of Clause 27.1 to take reasonable precautions to protect the find and would ask for your immediate instruction for dealing with this discovery. As a result of this obligation we have to advice you that the works are now being delayed and we shall be seeking an extension of time and reimbursement of our additional costs. Yours faithfully
Contractor Ltd