Weekly Report

Site Code: Site Name: Site Manager:

NTI KEDOYA ANTON MS

Date : Contractor : SKM CM :

08 October 2012 PT. KALTIM CIPTAYASA Mr. GURUH

Paving block

Paver Block Site Visit by SKM Guruh,Andry.Noval.Rowena,Jimmy

Piling Works at Canopy Area, Tank Area

Backfilling,Compaction

Installation of Ground Water

Perimeter Fence,V-Crimp Foundation

Column spreader

Connected Beam Foundation Tank Area Column Spreader

Concreting at C-Store Foundation at

Installation of Slot Drain

Installation of HSSE Refresher Training a.Ladder b.Body Harness c.Manual lifting Perimeter drainage

HSSE Initiatives Energy Drink

1Work Progress Plan Actual

Wk01 Start 21/09/12 21/09/12 30/09


10%

Wk02 07/10
25%

Wk03 14/10

Wk04 21/10

Wk05 28/10

Wk06 04/10

Wk07 11/10

Wk08 18/10

Wk09 25/10

Wk10

Wk11

Wk12

Wk13

Wk14

Finish

T&R

22/11/12

HSSE
CTR hours this week CTR hours this month CTR hours Cumulative CTR hours Cumulative Total plan 2968 1056 4024 25000

Major Tasks This Week


V-Crimp Foundation Filling and Compaction

Major Tasks Next Week


Piling Works at Tank Area, Sales Building and Canopy Instalation of perimeter Drainage Excavation at Tank Area Canopy Area Pile Cap

Comments

RAINY CUMMULATIVE THIS WEEK= 0 hours, COMMULATIVE TILL NOW = 0 hours THIS WEEK NMPI : 3 REPORT CUMMULATIVE : 4 REPORT