The document outlines the steps to create task linkages for an RTO license system project in Microsoft Project 2007, including creating tasks such as feasibility study, requirements study, designing, coding, unit testing, and integration testing; setting predecessors for certain tasks; splitting the coding task; and setting a milestone at the implementation task. The output includes a Gantt chart and display of tasks and sub-tasks for the RTO license system.
The document outlines the steps to create task linkages for an RTO license system project in Microsoft Project 2007, including creating tasks such as feasibility study, requirements study, designing, coding, unit testing, and integration testing; setting predecessors for certain tasks; splitting the coding task; and setting a milestone at the implementation task. The output includes a Gantt chart and display of tasks and sub-tasks for the RTO license system.
The document outlines the steps to create task linkages for an RTO license system project in Microsoft Project 2007, including creating tasks such as feasibility study, requirements study, designing, coding, unit testing, and integration testing; setting predecessors for certain tasks; splitting the coding task; and setting a milestone at the implementation task. The output includes a Gantt chart and display of tasks and sub-tasks for the RTO license system.
AIM: To create Task Linkages for RTO License System STEPS: 1. Start 2. Open Microsoft Project 2007. 3. Create tasks and set the duration, start date, end date, predecessor and their resources for each tasks. 4. Create tasks such as Feasibility Study, Requirement study, Designing, Coding, Unit Testing, Integration testing and Implementation. 5. Set predecessors for Designing, Coding, Integration Testing and Implementation tasks. 6. Select Task Information from PROJECT 7. Select Predecessor and set predecessor for Requirements, Admins Requirement, Designing, etc. 8. Designing is led by 1 day and Coding of crime analysis module is lagged by 1 day. 9. Split Task of coding of crime analysis module. 10. Set Milestone at Implementation Task. 11. Stop. OUTPUT:
Fig 4.1 Gantt Chart for RTO License System
Fig 4.2 Tasks and Sub-Tasks for RTO license system