Professional Documents
Culture Documents
h44 07 PDF
h44 07 PDF
h44 07 PDF
ABUTMENTS. (2) THESE BRIDGES ARE NOT TO BE USED WHEN POINT BEARING FOR THE ABUTMENT STEEL
PILING WOULD BE OBTAINED ON ROCK AT A DISTANCE LESS THAN 15 FEET FROM THE BOTTOM OF FOOTING. (3) THE ABUTMENT PILING ARE TO BE DRIVEN THROUGH OVERSIZED HOLES PREBORED TO A
MINIMUM OF 10 FEET BELOW THE BOTTOM OF FOOTING. THE PREBORED HOLES SHALL BE IN ACCORDANCE WITH ARTICLE 2501.03, Q, OF THE STANDARD SPECIFICATIONS. THE ELEVATION OF THE BOTTOM OF THE PREBORED HOLE SHALL BE SHOWN ON THE PLANS.
REVI SED 1 1 -09 - THE SPECI FI CATI ON REFERENCES CHANGED. ADDED ADDI TI ONAL SHEET TO THE I NDEX.
THE ABUTMENT FOOTING AND PIER CAP CONCRETE QUANTITIES SHOWN IN THESE PLANS ARE CALCULATED BASED ON A 0.3% GRADE. FOR HIGHER GRADES, THESE CONCRETE QUANTITIES FOR BRIDGES SKEWED AT 15, AND 30 MAY NEED TO BE INCREASED. IN ADDITION, THE LAYOUT OF THE PIER CAP STEP REINFORCING STEEL IS GRADE DEPENDENT FOR BRIDGES SKEWED AT 15 AND 30. SEE SHEETS H44-17-07 AND H44-24-07 TO DETERMINE THE ADDITIONAL CONCRETE QUANTITIES REQUIRED AND FOR THE LAYOUT AND QUANTITY OF THE PIER CAP STEP REINFORCING STEEL.
H44-79-07 H44-80-07
PROVIDE TOP OF SLAB ELEVATIONS AND WING ELEVATIONS A, B AND C AS NOTED ON THE STANDARD SHEETS (LONGITUDINAL SECTION).
VARIOUS TYPES OF PIERS MAY BE USED WITH THESE STANDARDS. IT SHOULD BE NOTED THAT THE DETAILS FOR THE PIER DIAPHRAGM ON THE SUPERSTRUCTURE DEPEND ON THE TYPE OF PIER USED.
THESE BRIDGE PLANS LABEL ALL REINFORCING STEEL WITH ENGLISH NOTATION (5a1 IS INCH DIAMETER BAR). ENGLISH REINFORCING STEEL RECEIVED IN THE FIELD MAY DISPLAY THE FOLLOWING "BAR DESIGNATION". THE "BAR
THE PIERS AND ABUTMENTS FOR THESE STANDARDS HAVE BEEN DESIGNED FOR THE USE OF BOTH FRICTION AND POINT BEARING PILES. IT IS NECESSARY THAT THE TYPE AND LENGTH FOR BOTH THE ABUTMENT AND PIER PILES BE DESIGNATED ON THE FRONT SHEET OF THE PLANS.
DESIGNATION" IS THE STAMPED IMPRESSION ON THE REINFORCING BARS, AND IS EQUIVALENT TO THE BAR DIAMETER IN MILLIMETERS.
ENGLISH SIZE THESE STANDARDS ARE TO BE USED FOR BRIDGES WITH EPOXY COATED REINFORCING. BAR DESIGNATION FOR PIERS SUBJECT TO SCOUR THE DESIGN BEARING SHALL BE OBTAINED BELOW SCOUR ELEVATION. SCOUR ELEVATION SHALL BE SHOWN ON THE FRONT SHEET.
10
11
10
13
16
19
22
25
29
32
36
CONCRETE INTERMEDIATE DIAPHRAGMS SHALL BE USED FOR OVERPASS BRIDGES. THE DESIGNER SHALL ADJUST THE CONCRETE AND REINFORCING QUANTITIES ACCORDINGLY.
DESIGN STRESSES:
DESIGN STRESSES FOR THE FOLLOWING MATERIALS ARE IN ACCORDANCE WITH THE AASHTO LRFD BRIDGE DESIGN SPECIFICATIONS, 4th Ed, SERIES OF 2007.
KEYWAY DIMENSIONS SHOWN ON THE PLANS ARE BASED ON NOMINAL DIMENSIONS UNLESS STATED OTHERWISE. IN ADDITION, THE BEVEL USED ON THE KEYWAY SHALL BE LIMITED TO A MAXIMUM OF 10 DEGREES FROM VERTICAL.
REINFORCING STEEL IN ACCORDANCE WITH LRFD AASHTO SECTION 5, GRADE 60. CONCRETE IN ACCORDANCE WITH LRFD AASHTO SECTION 5, fc = 3,500 PSI. FOR STANDARD PRESTRESSED CONCRETE BEAMS, SEE SHEETS H44-25-07 THRU H44-30-07
APPROVED BY BRI DGE ENGI NEER
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
SPECIFICATIONS:
DESIGN: 1 1 -09 AASHTO LRFD 4th Ed, SERIES OF 2007.
LATEST REVI SI ON DATE
CONSTRUCTION: IOWA DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION, SERIES 2009, PLUS APPLICABLE GENERAL SUPPLEMENTAL SPECIFICATIONS, DEVELOPMENTAL SPECIFICATIONS, SUPPLEMENTAL SPECIFICATIONS AND SPECIAL PROVISIONS SHALL APPLY TO CONSTRUCTION WORK ON THIS PROJECT.
H44-01-07
9/29/2011
2:43:11 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-01-07
11x17_pdf.pltcfg
THE BOXED IN DETAILS IN THE FOLLOWING EXAMPLES SHOW HOW THE INFORMATION SHOULD BE INDICATED ON THE PLANS.
ICE FORCE: ICE FORCES WERE APPLIED AT A HEIGHT OF H/2 + 1-6 ABOVE THE BOTTOM OF THE PIER FOOTING, WHERE H IS THE OVERALL HEIGHT OF PIER. THE EFFECTIVE ICE STRENGTH WAS 24 KSF FOR 1-7 OF ICE DEPTH. A PRIMARY ICE FORCE (F) WAS CALCULATED ACCORDING TO THE LRFD SPECIFICATIONS AND APPLIED TO THE PIER STEM AS FOLLOWS: CASE 1: 100% OF F APPLIED PARALLEL TO THE PIERS LONG AXIS AND 15% OF
G 2 = 0 . 9 5 %
EXAMPLE NO. 1 A STRAIGHT GRADE OF -3.25% WITH THE P.I. STATION OF 103+75.00 AND ELEVATION OF 653.29. THE BRIDGE LENGTH IS 213-10 | TO | OF ABUTMENT BEARINGS WITH 30 SKEW RIGHT AHEAD.
EXAMPLE NO. 2
% 3 6 . 2 +
F APPLIED PERPENDICULAR TO THE PIERS LONG AXIS. CASE 2: 50% OF F APPLIED PARALLEL TO THE PIERS LONG AXIS AND 34% OF F APPLIED PERPENDICULAR TO THE PIERS LONG AXIS.
1 G
STREAM FLOW: | BRIDGE STATION 254+73.00 | TO | ABUT. BRGS. = 213-10 STATIONS | BRIDGE STA. } OF L2 = 105+85.00 } 38.67 106+23.67 + 68.25 P.I. STATION 253+10.00 P.I. ELEVATION = 316.09 FROM SHEET H44-04-07 LENGTH OF VERTICAL CURVE = (20000)(0.0358) = 716 FEET M.O. = (0.0358)(716)() = 3.204 FEET FOOTING GEOMETRY: IT WAS ASSUMED THAT THE PIER FOOTING WILL BE SET APPROXIMATELY 6-0 BELOW THE ADJACENT STREAMBED OR GROUND SURFACE. IT WAS ALSO ASSUMED THAT THERE STATIONS ELEVATIONS ALONG PROFILE GRADE LINE (P.G.L. ELEV.) | ABUT. BRG. = 653.29-[(104+78.08)-(103+75.00)](0.0325) =649.94 | PIER BRG. = 653.29-[( 105+46.33 )-(103+75.00)](0.0325) =647.72 | PIER BRG. = 653.29-[( 106+23.67 )-(103+75.00)](0.0325) =645.21 | ABUT. BRG. = 653.29-[(106+91.92 )-(103+75.00)](0.0325) =642.99 | BRIDGE STA. } OF L2 = 254+73.00 } 38.67 255+11.67 + 68.25 255+79.92 ALL BRIDGES WITH TEE PIERS DETAILED ON THESE STANDARDS ARE INTENDED TO HAVE ONE FIXED PIER AND ONE EXPANSION PIER. THE PILE LAYOUT AND REINFORCEMENT SHOWN ARE THE SAME FOR EITHER FIXED OR EXPANSION PIER. THE ONLY DISTINCTION BETWEEN FIXED PIER AND EXPANSION PIER LIES IN THE SELECTION OF BEARINGS AND PRESENCE OF THE KEYWAY IN THE TOP OF THE CAP. EACH BRIDGE SHALL HAVE ONE SET OF FIXED BEARINGS AND ONE SET OF EXPANSION BEARINGS, WHICH MAY BE USED ELEVATIONS TOP OF SLAB FACING ALONG THE STATIONING ( BEAM SPACING )( TAN. SK. ) = ( 6.84 )TAN 15 = 1.83 ON EITHER PIER 1 OR PIER 2. THE KEYWAY IN THE TOP OF THE CAP SHOULD BE ELIMINATED FROM THE EXPANSION PIER. ARE NO SIGNIFICANT UNBALANCED EARTH PRESSURES APPLIED TO THE PIER. 15 SKEW LEFT AHEAD THE STREAM VELOCITY USED WAS 5 FT/SEC WITH THE C D COEFFICIENT EQUAL TO 1.4. THE RESULTING STREAM FORCE WAS ASSUMED TO ACT PARALLEL TO THE PIERS LONG AXIS. IT WAS ASSUMED THAT SUPERSTRUCTURE ELEMENTS WILL CLEAR HIGH WATER BY APPROXIMATELY 3-0.
= 105+46.33 68.25
= 104+78.08
106+91.92
= 254+34.33 68.25
= 253+66.08
ELEVATIONS TOP OF SLAB FACING ALONG THE STATIONING (BEAM SPACING)(TAN. SK. )(GRADE) = (6.84)TAN 30(0.0325) = 0.13
ABUTMENT NO. 1 BEAMS PGL ELEV. SK. CORRECT EXTERIOR 649.94 +0.39 -0.38 649.95 -4.74 645.21 INTERIOR 649.94 +0.26 -0.24 649.96 -4.74 645.22 INTERIOR 649.94 +0.13 -0.10 649.97 -4.74 645.23 CENTER 649.94 0.00 0.00 649.94 -4.74 645.20 INTERIOR 649.94 -0.13 -0.10 649.71 -4.74 644.97 INTERIOR 649.94 -0.26 -0.24 649.44 -4.74 644.70 EXTERIOR 649.94 -0.39 -0.38 649.17 -4.74 644.43
PIER NO. 1 BEAMS STATION PGL ELEV. SLAB CROWN TOP SLAB ELEV. -"U" (4-7) BR. SEAT ELEV. EXTERIOR 254+39.82 +313.56 -0.38 313.18 -4.61 308.57 INTERIOR 254+37.99 +313.55 -0.24 313.31 -4.61 308.70 INTERIOR 254+36.16 +313.55 -0.10 313.45 -4.61 308.84 CENTER 254+34.33 313.54 0.00 313.54 -4.61 308.93 INTERIOR 254+32.50 313.54 -0.10 313.44 -4.61 308.83 INTERIOR 254+30.67 313.54 -0.24 313.30 -4.61 308.69 EXTERIOR 254+28.84 313.53 -0.38 313.15 -4.61 308.54
HP10x57 STEEL PILE SHALL BE USED IN THE PILE FOOTINGS OF THE PIERS FOR EITHER FRICTION OR POINT BEARING PILE CONDITIONS. FRICTION BEARING INCLUDES SIDE FRICTION AND END BEARING IN SOIL. POINT BEARING INCLUDES SIDE FRICTION AND POINT BEARING IN ROCK. NOMINAL STRUCTURAL RESISTANCE WAS TAKEN AS 243 KIPS FOR 50 TON FRICTION BEARING PILES AND 365 KIPS FOR 75 TON POINT BEARING PILES. A NOMINAL UPLIFT RESISTANCE OF 42 KIPS PER PILE WAS USED IN THE DESIGN OF THE PIER FOOTINGS. THE PIER SHALL NOT BE USED AT SITES WHERE THIS UPLIFT FORCE CANNOT BE ACHIEVED DUE TO SPECIFIC CONDITIONS SUCH AS SURFACE ROCK LAYERS.
SLAB CROWN TOP SLAB ELEV. -"U" (4-8) BR. SEAT ELEV.
WHEN PIERS ARE USED IN GRADE SEPARATION STRUCTURES, EPOXY COATED REINFORCEMENT MAY BE REQUIRED FOR PIER COLUMNS. CONSULT CURRENT POLICY FOR GUIDANCE ON THE USE OF EPOXY COATED REINFORCEMENT IN SUCH CASES. ADJUST THE d1 COLUMN BAR ELEV. 645.22 ELEV. 645.21 2 3 3 ELEV.645.23 ELEV. 645.20 ELEV. 644.97 1 1 1 1 ELEV. 644.43 ELEV. 308.57 ELEV. 644.70 308.70 ELEV. ELEV.308.84 ELEV. 308.93 ELEV. 308.83 1 308.54 ELEV. 1 ELEV.308.69 PROJECTION INTO THE CAP AND d1/d2 LAP DISTANCE ACCORDINGLY.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
GENERAL INFORMATION
H44-02-07
9/29/2011
2:43:12 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-02-07
11x17_pdf.pltcfg
2" CL.
22'-3 (44'-6 ROADWAY FOR OPEN RAIL) 20'-7 TANGENT ON 2.0% SLOPE 3'-0 PARABOLIC CROWN 3'-0 PARABOLIC CROWN
22'-0 (44'-0 ROADWAY FOR BARRIER RAIL) 19'-0 TANGENT ON 2.0% SLOPE
1'-7
1 " CL.
LEVEL
1 BEVELED 1 x 3 NAILED TO HEADER HEADER CUT TO FIT SHAPE OF CROWN AND DRILLED FOR LONGITUDINAL REINFORCING.
TRANSVERSE REINFORCING STEEL IS TO BE PARALLEL TO AND 1" CLEAR ABOVE BOTTOM OF SLAB. TOP AND BOTTOM REINFORCING STEEL IS TO BE SUPPORTED BY INDIVIDUAL BAR CHAIRS SPACED AT NOT MORE THAN 3'-0 CENTERS LONGITUDINALLY AND TRANSVERSELY, OR BY CONTINUOUS ROWS OF BAR HIGH CHAIRS OR SLAB BOLSTERS SPACED 4'-0 APART. I.M. 451.01 REQUIREMENTS SHALL APPLY FOR BAR CHAIRS, BAR HIGH CHAIRS, AND SLAB BOLSTERS. 1'-9 8 10 5 SP. @ 9" = 3'-9 10 8 TYPICAL 5b1 & 5b2 SPACING ( TOP OF SLAB ) 1'-2 6 SP. @ 9" = 4'-6 1'-2 TYPICAL 5b1 & 5b2 SPACING 6a @ 10" ( BOTTOM OF SLAB ) 2" CL. ROUGHEN JOINT UNDER POST 5j1 BARS AT 10" (`CENTERED BETWEEN 6a BARS IN TOP OF SLAB`) 9 5b1 & 5b2 STRAIGHT LINE BETWEEN BEAMS OPEN RAIL SLAB AREA = 32.45 SQ. FT. BARRIER RAIL SLAB AREA = 31.95 SQ. FT. SLAB AREAS DO NOT INCLUDE THE NOMINAL INCH HAUNCH.
1'-6
4 1'-5
TOP TRANSVERSE REINFORCING STEEL IS TO BE PARALLEL TO AND 2 " CLEAR BELOW TOP OF SLAB. BOTTOM
1 x 8 x 0'-8 8 8 INDENTATION 8 SPACED @ 2'-0 8 1 0" MAX. 9" MI N. 3 " DRIP GROOVE 10 3'-1 FOR DETAILS OF 8 34 3 4 RAIL AND RAIL REINFORCING b3 SPACING SYMMETRICAL ABOUT TOP OF SLAB 5b1 & 5b2 1'-2 6 SPACES @ 9" = 4'-6 1'-2 SEE BARRIER RAIL SHEET H44-32-07 THRU H44-34-07 2 5e1 2 5d2 5e3 5d1 5e4 " x 1'-3 COIL " PREFORMED EXPANSION JOINT FILLER 5d3 & 5d4 5e2 KEYWAY FORMED BY BEVELED 2x8 STRIP " x 1'-3 COIL ROD ROD (BENT) 5 6 5b1 BARS & 5b2 NEOPRENE BEARING PADS * STEEL DIAPHRAGM SEE SHEET H44-31-07 5b1 & 5b2 SPACING
*`" DOUBLE DRIP GROOVE (TYP.) * NOTE: DOUBLE DRIP GROOVES FOR OPEN RAIL OPTION ONLY. 5d5 4t1 0" A, B BEAMS 1" C BEAMS STEP
5 6
1 1
5d2 5d3
CL.
1 "
"U" TOP OF SLAB 8g1 TO BRIDGE SEAT * FOR SLAB THICKNESS OVER BEAMS SEE SYMMETRICAL ABOUT S3 x 7.5 " x 1'-3 COIL ROD KEYWAY FORMED BY BEVELED 2x8 STRIP | ROADWAY UNLESS NOTED TABLE OF SLAB AND HAUNCH THICKNESS AT BEAMS ON SHEET H44-04-07.
3' -6
2" CL.
1 " CL.
AT LOW
| ROADWAY
b3
4 2
GENERAL NOTES:
EXPANSION PIER DIAPHRAGM SHOWN CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR REINFORCING BAR SHALL BE 2" UNLESS OTHERWISE NOTED OR SHOWN. FIXED PIER DIAPHRAGM SHOWN
BOTTOM BARS - LAP OVER BEAMS ( MIN. LAP = 1'-10 ). FORMS FOR THE SLAB AND RAILS ARE TO BE SUPPORTED BY THE PRESTRESSED CONCRETE BEAMS. PAYMENT FOR REINFORCING BARS SHALL BE BASED ON NO SPLICES, AND NO ALLOWANCE SHALL BE MADE FOR THE ADDITIONAL LENGTH OF
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44' ROADWAY, THREE SPAN BRIDGE
BAR REQUIRED FOR THE USE OF SPLICES. WEIGHT OF DRAINS IS INCLUDED IN THE STRUCTURAL STEEL QUANTITY. 06-1 2
LENGTH OF S3 x 7.5
(`ABUTMENT BEAM SEAT`) BEAM BOTTOM FLANGE WIDTH LENGTH OF S3 x 7.5 1'-3 1'-6
THE PIER AND ABUTMENT DIAPHRAGM CONCRETE IS TO BE PLACED MONOLITHICALLY WITH THE FLOOR SLAB.
ALL REINFORCING STEEL IS TO BE GRADE 60. 1'-5 COST OF ALL PREFORMED EXPANSION JOINT FILLER MATERIAL IS TO BE INCLUDED IN THE PRICE BID FOR "STRUCTURAL CONCRETE (BRIDGE)". 1'-8
SUPERSTRUCTURE DETAILS
H44-03-07
5/14/2012
2:38:04 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-03-07
11x17_pdf.pltcfg
WAS EXTENDED TO A 1 -0 DI STANCE. THE DATA FOR ONE DRAI N QUANTI TI ES WERE ADJUSTED FOR THE ADDI TI ONAL DRAI N LENGTH.
ABUT.
1 G +
M.O. SLAB
G 2
BEAM
| PIER
| PIER
|-| ABUT. BRG. "L" 138-10 151-4 163-10 176-4 188-10 201-4 213-10 226-4 243-0
A | ABUT. 1
C | PIER 1 1 1 1 2 1 1
15 AND 30 SKEW
| PIER
SITUATION SKETCH
(SHOWING DRAIN LOCATIONS)
0 1 = R
3 1" DEPRESSION IN SLAB CONCRETE AT DRAIN
1 1
LENGTH OF VERTICAL CURVE REQUIRED = (20,000)(G1-G2) M.O. = (G1-G2)(LENGTH OF V.C.) 8 (G1-G2) IS THE ALGEBRAIC DIFFERENCE OF THE APPROACH GRADES EXPRESSED IN DECIMAL FORM. G1 NEED NOT HAVE THE SAME VALUE AS G2. MAXIMUM VALUE OF G1 OR G2 IS 5%. LENGTH OF CURVE AND M.O. ARE IN FEET. " DOUBLE DRIP GROOVE STRAIGHT LINE 5 6 1 x x 0-10 { WELDED ON OPPOSITE SIDES OF DRAIN TO SERVE AS ANCHOR.
BOTH SIDES OF DRAIN WITH 2 - " HOLES IN EACH OUTSTANDING LEG FOR NAILING TO FORMS.
TOP OF SLAB
PI ER
SLAB |
DRAIN DETAILS
" DRIP 3 USE FOR BARRIER RAIL ONLY. NOT REQUIRED FOR OPEN RAIL. STRAIGHT LINE NOTE : DRAINS ARE TO BE GALVANIZED AFTER FABRICATION. GROOVE
BEAM HAUNCH L1 L2
L1
INTERIOR BEAMS
WEIGHT OF DRAINS IS INCLUDED IN THE QUANTITY FOR "STRUCTURAL STEEL" . WEIGHT IS BASED ON ROLLED TUBE.
THE BEAM
HAUNCH DETAIL
* FOR SLAB THICKNESS OVER BEAMS SEE " SLAB THICKNESS DETAILS " ON THIS SHEET. ( KEEP)
MI N.
G 1
ABUT.
1 0
1 -0
MAX.
1 2 2 1 2
2 "
MAX.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
"
1 0-1 1
G1 MAY HAVE A + OR - SIGN. THE MINIMUM NUMERICAL VALUE OF THE GRADE IS 0.3% AND THE MAXIMUM VALUE IS 5%.
THICKNESS OVER THE BEAM AT THE MIDPOINT OF THE SPANS (POINTS B, D AND F) TO A MAXIMUM OF " EMBEDMENT IN THE SLAB. IF MORE THAN " EMBEDMENT IS REQUIRED OR IF THE HAUNCH EXCEEDS 2" THE GRADE LINE IS TO BE REVISED.
1 "
SUPERSTRUCTURE DETAILS
H44-04-07
9/30/2011
3:11:54 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-04-07
11x17_pdf.pltcfg
47-2 CONSTANT 1-7 LEVEL 44-0 ROADWAY 1-7 LEVEL TOP OF SLAB 1 -1 1" CHAMFER DEPTH 3" PVC PIPE 5k1 8g3 8g1 TOP OF SLAB
-1 1
1 -1
1 -3
5d7
5d2
1 -3
5h2
(1) HAIR AND JUTE RUG PADDING, RUBBERIZED ON BOTH SIDES, AND WEIGHING NOT LESS THAN 47 OZ. PER SQ. YD.
3 -0
STEEL H-PILE
2 -0
(2) BONDED URETHANE OR BONDED POLYFOAM WITH A MINIMUM DENSITY OF 5 LBS. PER CU. FT. AND SHALL BE AT LEAST IN. THICK, (MATERIAL LESS THAN IN. IN THICKNESS MAY BE RUG 1-6 1-6 PADDING USED, BUT WILL REQUIRE ADDITIONAL WRAPS FOR A TOTAL OF AT LEAST ONE INCH).
TOP OF PI LE
CL.
3-0
TOP OF PI LE
CL.
3-0
47-2
COIL ROD
3 -0
4t1
S3 x 7.5
1 -6
" x1-3
|-|
138-10 151-4 163-10 176-4 188-10
ABUT. BRG.
1 -6
ABUTMENT NOTES:
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR REINFORCING BAR IS TO BE 2" UNLESS PI LES 1 2 H-PI LES 1 PLACE 5h2 BAR AT 1:6 SLOPE TO MATCH TRAFFIC SIDE OF ABUTMENT WING FACE. (BOTH SIDES 2 WOOD WI TH OTHERWISE NOTED OR SHOWN.
"B" (FT. - IN.) "C" (FT. - IN.) "D" EQUAL SPACES NO. OF PILES PER ABUT. PILE BEARING (TONS) STRENGTH I DESIGN LOAD (KIPS) "A" PILE SPACES "B" (FT. - IN.) STEEL WI TH "C" (FT. - IN.) "D" EQUAL SPACES NO. OF PILES PER ABUT. PILE BEARING (TONS) STRENGTH I DESIGN LOAD (KIPS)
8g1 5h2
8g1
IF NECESSARY TO PREVENT DAMAGE TO THE END OF THE BRIDGE DECK OR BACKWALL FROM CONSTRUCTION EQUIPMENT, AN APPROPRIATE METHOD OF PROTECTION APPROVED BY THE ENGINEER SHALL BE PROVIDED BY THE BRIDGE CONTRACTOR AT NO EXTRA COST TO THE
1-3
1-3
TYP.
8g1
TYP.
GUTTER LINE
COUNTY OR STATE.
PART SECTION A - A
ABUTMENT PILES ARE TO BE DRIVEN TO THE DESIGN BEARING VALUE AS GIVEN IN THE ABUTMENT PILE SPACING TABLE.
GUTTER LINE
"C"
| PILE 8f1
| PILE
| PILES
APPROVED BY BRI DGE ENGI NEER
1 -6
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
3 -0
1 1 -09
5p1
1 -6
5p1 1-0 1-0 "D" EQUAL SPACES 1-0 1-0 5p1 DOUBLE HOOP SPACING
ABUTMENT DETAILS
0 SKEW A & B BEAMS
H44-05-07
47-2 CONSTANT 1-7 LEVEL 44-0 ROADWAY 1-7 LEVEL 1 -1 TOP OF SLAB 5d8 (TRAFFIC FACE) 5d9 (BACK FACE) C
ABUTMENT NOTES:
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR REINFORCING BAR IS TO BE 2" UNLESS OTHERWISE NOTED OR SHOWN.
-1 1
1" CHAMFER
1 -1
A 3" PVC 8g1 3" PVC PIPE (FRONT FACE & BACK FACE)
5d8
IF NECESSARY TO PREVENT DAMAGE TO THE END OF THE BRIDGE DECK OR BACKWALL FROM CONSTRUCTION 8g 1 MI N.EMBED. EQUIPMENT, AN APPROPRIATE METHOD OF PROTECTION APPROVED BY THE ENGINEER SHALL BE PROVIDED BY THE BRIDGE CONTRACTOR AT NO EXTRA COST TO THE COUNTY OR STATE. 5d7 5d2
PIPE 6g4
5d9
MI N.EMBEDMENT
6g 4 BARS
1 -3
1 -3
5d6
ABUTMENT PILES ARE TO BE DRIVEN TO THE DESIGN BEARING VALUE AS GIVEN IN THE ABUTMENT PILE SPACING TABLE.
S3 x 7.5
5h4
5h2
1 -9
8f3 & 8f4 5p2 2 CL. 2 CL. 5h2 (BACK FACE) 3" CL. 5h4 (TRAFFIC FACE) FIELD BEND 5h4 BAR 6p3
NOTE: THE SPIRAL AT THE TOP OF EACH PILE TO BE 7 TURNS OF NO. 2 BAR, 21" DIAMETER, 3" PITCH WITH 3 - L x x SPACERS PUNCHED TO HOLD SPIRAL.
CONSTR. JOINTS
8f4 5p2
5p1
2 CL. 3-0
2 CL.
47-2 3-1 6 BEAM SPACES @ 6-10 = 41-0 3-1 SPACING FOR: 3 2 @ 0-8 KEYWAY FORMED B | ABUT. 8g1 " x 1-3 1 -6 COIL ROD 5d5 8g1 6 1 -6 S3 x 7.5 4t1 BRG. 8g1 5d2 & 5d3 5d5 BY BEVELED 2x8 1-6 SAME SPACING BETWEEN BEAMS 1-0 4 SPA. @ 1-2 6-10 1-0 1-6 2 @ 0-8 3 41- 8g1 BACK FACE 36- 8g1 FRONT FACE 37- 8g3 BACK FACE 39- 5k1 & 5k2 BACK FACE "C"
PART SECTION B - B
23-8 "A" PILE SPACES @ "B" 23-8 "C"
1-0 1-0
1-0 1-0
3 -0
5p1
1 -6
REVI SED 01 -1 2 - ADDED FI ELD BEND 5h4 BAR TO AVOI D PI LE I N ABUTMENT WI NG NOTE.
4 SPA.@ 1 -0 = 4 -0
FIELD BEND 5-6g 4 EACH FACE 8g1 8g1 5k1 & 5k2 8g3 6 -6 5d7-(MIN. LAP AT | = 2-2) 3" PVC PIPE 5d9 1 -6
8f4 | ABUTMENT & | ROADWAY BACK FACE OF ABUTMENT
6 -6
8f3 1 -6
5 -0
5d6-(MIN. LAP 3" PVC PIPE 6g4 KEYWAY FORMED BY BEVELED 2x8 B AT | 2-2)
6g4
8f4
8f4
PART SECTION A - A
GUTTER LINE
2 -1 0
TYP.
1-4 22-0
GUTTER LINE
*
5c3
5c14
ABUT. BRG.
8
APPROVED BY BRI DGE ENGI NEER
5d9
5d8
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
2 CL.
6g4
1 2
ABUTMENT DETAILS
0 SKEW C BEAMS
H44-06-07
12/28/2011
1:15:41 PM
tsorens
W:\Highway\Bridge\NewStandards\Jan_2012_Release\H44-07.dgn
h44-06-07
11x17_pdf.pltcfg
GUTTER LINE
1 -6
5p2
1 -0 1 -0
5p2
5 -0
TYP.
5 -0
1-3
1-3
TYP.
8f3
5p1
1 -6
3 -0
NOTE: BRIDGE IS SYMMETRICAL ABOUT | 7-0 BARRIER RAIL END SECTION FACE TO FACE OF BARRIER RAIL END SECTIONS 5e4 BARS (SEE BARRIER RAIL LAYOUT SHEET) 4" MI N.CL. A D PARALLEL TO THE THEORETICAL | GRADE
6c4 BARS
~ 5c5-10
1 -6
~ 6c4 5b1 & b3 ELEV. A BEAM PRESTRESSING STEEL STRANDS 5d5 ~ 6c3 3 ~ 5c5-10 ELEV. B 1 x 8 x 0-8 INDENTATION SPACED @ 2-0
5e1 &
2 -3 MI N.
3 EQ.SPS.
5k1
6 -6 ( BBEAM
6 -2 ( ABEAM
5d2
5b1 5e1
5d2
5s1 2 CL.
5k2 5d3 8g3 5d6 4t1 " x 1-3 COIL ROD S3 x 7.5 | BEARINGS SEE DETAIL "A" 5e3
D 2 EQ. 4 8 5s1
5h2
SECTION D-D
~ NOTE: SPS. 5h2 SEE END SECTION DETAILS IN THESE PLANS FOR DETAILS OF BARRIER RAIL END SECTION. REINFORCING BARS 6c3, 6c4, 5c5-10, 6d2 & 4t1 ARE INCLUDED IN THE SUPERSTRUCTURE QUANTITIES.
8g1
8g1
MIDWAY BETWEEN | ABUTMENT BEARING NOTE: PLUG 3" PVC PIPE WITH EXPANDING FOAM PRIOR TO BACKFILLING BEHIND ABUTMENTS. BEAM BEARINGS
8g1
SECTION A-A
MIDWAY BETWEEN BEARINGS 1" HOLE (TYP.) A
| TO | BEAM BEARINGS
1-6
EXPANSION PIER
| ABUTMENT BEARING TO | PIER | PIER | ABUTMENT BEARING TO | ABUTMENT BEARING (REQUIRED AT ONE PIER, ONLY IF TEE PIERS ARE USED)
" RADIUS
FI XED PI ER
EXPANS.PI ER
1 -1 1
ABUTMENT
FIXED PIER
| WEB
3 5
COIL TIE
COIL TIE
DETAIL "C"
" x 1-3 COIL ROD 9 (BENT 6 ) | PIER 6 1 -7 5d4 6
ABUTMENT
PIER
1 -7
5e2
1 -0
END OF 5d4 3 EQUAL SPACES 4-5e3 SEE SHEET H44-31-07 6 -1 0 5d3 5e1 BEAMS 2 4 6
| BEAM BEARINGS
| ABUT. BRG.
44 -0 ROADWAY
DETAIL "A"
1-3
1-6
1-6 5e3
| PIER
" PREFORMED EXPANSION 1" THICK STRIPS OF PREFORMED EXPANSION 4-0 2-0 1-0 JOINT FILLER.
1 -0
JOINT FILLER AROUND BEARINGS, FACE OF STEPS, SIDES AND ENDS OF KEYWAYS.
SECTION B-B
5c10
PART PLAN
1 -7
1 -7
~
APPROVED BY BRI DGE ENGI NEER
6c3
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 -7
1 1 -09
LONGITUDINAL SECTION
0 SKEW A & B BEAMS
H44-07-07
9/29/2011
2:43:20 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-07-07
11x17_pdf.pltcfg
NOTE: BRIDGE IS SYMMETRICAL ABOUT | 7-0 BARRIER RAIL END SECTION FACE TO FACE OF BARRIER RAIL END SECTIONS 5e4 BARS SEE BARRIER RAIL DETAILS FOR BARS AND BAR SPACING A D (SEE BARRIER RAIL LAYOUT SHEET) 4" MI N.CL. PARALLEL TO THE THEORETICAL | GRADE
~ 5b1 & b3 5d8 (TRAFFIC FACE) 5d9 (BACK FACE) BEAM PRESTRESSING STEEL STRANDS ELEV. A 3" PVC PIPE ~ 6c3 3 ELEV. B ~ 5c5-10 ELEV. C 6c4 1 x 8 x 0-8 INDENTATION SPACED @ 2-0
5e1 &
5 EQ.SPACES:5d
3" PVC PIPE 5d2 5d7 7 -3 5k2 8g3 5d6 5d3 5e3 5d4 5d3 4t1 5b1 5e1 5d5 D C C
2 CL. 3" PVC 5d9 PIPE 5d8 6g4 5h4 1 -9 MI N. FI XED PI ER EXPANS.PI ER | WEB 3 5 PIER 5 | PIER TYP. JOINT FILLER. EMBED.
5d2
8g1
8g1 6g4 MIDWAY BETWEEN BEAM BEARINGS MIDWAY BETWEEN BEAM BEARINGS 1-6 9 9 " PREFORMED EXPANSION JOINT FILLER A 5h2 (BACK FACE) 2-1 5h4 (TRAFFIC FACE) 5h1 (BACK FACE)
SPS. :5h
4t1
5s1
2 EQ. 4
5h2
| ABUTMENT BEARING NOTE: PLUG 3" PVC PIPE WITH EXPANDING FOAM PRIOR TO BACKFILLING BEHIND ABUTMENTS.
| TO | BEAM BEARINGS
EXPANSION PIER
6c4 BARS | ABUTMENT BEARING TO | PIER | PIER | ABUTMENT BEARING TO | ABUTMENT BEARING (REQUIRED AT ONE PIER, ONLY IF TEE PIERS ARE USED)
SECTION A-A
ABUTMENT
FIXED PIER
1 -6 ~ 6c4 ~ 6d2
2 -3 MI N.
) ~ NOTE:
5e2 1 -7
SECTION D-D
SEE END SECTION DETAILS IN THESE PLANS FOR DETAILS OF BARRIER RAIL END SECTION. REINFORCING BARS 6c3, 6c4, 5c5-10, 6d2 & 4t1
REVI SED 01 -1 2 - ADDED FI ELD BEND 5h4 BAR TO AVOI D PI LE I N ABUTMENT WI NG NOTE.
1 -1
" RADIUS 3 EQUAL SPACES 5d4 | ABUTMENT BEARING SEE SHEET H44-31-07 6 -1 0 5d3 5e1 4-5e3
&
44 -0 ROADWAY
| PIER 6
5d4 6
4-5e1
1-3
1-6
1-6 5e3
| BEAM
DETAIL "C"
| PIER
1" MIN.
| BEAM
PRESTRESSED STRANDS
1 -1
1" THICK STRIPS OF PREFORMED EXPANSION JOINT FILLER AROUND BEARINGS, FACE OF 4-0 2-0 1-0 STEPS, SIDES AND ENDS OF KEYWAYS.
SECTION B-B
NOTE: SEE SHEET H44-37-07 FOR EXPANSION PIER
END OF BEAMS 2 4 6
5c10
5d8
PART PLAN
DETAIL "A"
~ 6c4
5h1
5s1
6c3
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
2@7
3 @ 6 01 -1 2
1 -7
2@7 ~ 6c4
5 SPA. @ 6
6 SPA. @ 5
LONGITUDINAL SECTION
0 SKEW C BEAMS
H44-08-07
PART PLAN
12/28/2011
1:15:42 PM
tsorens
W:\Highway\Bridge\NewStandards\Jan_2012_Release\H44-07.dgn
h44-08-07
11x17_pdf.pltcfg
| - | ABUTMENT BRGS.
| PIER - | PIER
"X"
CONSTR. JOINT
"X"
b3
TOP REINFORCING
b3
6a1 44 -0 ROADWAY
188-10
BOTTOM REINFORCING 1 -7 | PIER | PIER 11 REVI SED 1 0-1 1 - THE ESTI MATED QUANTI TI ES FOR THE STRUCTURAL STEEL WI TH DRAI NS WAS CHANGED. "D" SPACES @ 10": 6a1 11 BOTTOM SLAB REINFORCING BARS "S" OUT TO OUT OF SLAB
SLAB LAYOUT
NOTE: CONCRETE DECK SLAB SHALL BE PLACED IN SECTIONS AND SEQUENCES INDICATED. ALTERNATE PROCEDURES FOR PLACING SLAB CONCRETE MAY BE SUBMITTED FOR APPROVAL TOGETHER WITH A STATEMENT OF THE PROPOSED METHOD AND EVIDENCE THAT THE CONTRACTOR POSSESSES THE NECESSARY EQUIPMENT AND FACILITIES TO ACCOMPLISH THE REQUIRED RESULTS.
ESTIMATED QUANTITIES
(SUPERSTRUCTURE PLUS INTEGRAL ABUTMENTS) STRUCTURAL CONCRETE SUPERSTRUCTURE (INCLUDES ABUTMENT WINGS)
151-4
163-10
176-4
188-10
201-4
213-10
226-4
243-0
GENERAL DATA
VERTICAL CURVE
151-4
163-10
176-4
1 -7
213-10
226-4
243-0
C.Y. C.Y. C.Y. C.Y. NO. NO. L.F. LB. LB. LB. LB. LB. LB. LB. LB. NO. NO. L.F. L.F.
232.3 234.8 36.7 38.4 7-A50 14-A42 311.7 5429 4749 6683 6003 66,476 67,141 66,662 67,327 30 14 300 140
247.1 249.8 36.7 38.4 7-A55 14-A46 336.7 5429 4749 6683 6003 70,884 71,505 71,070 71,691 30 14 300 140
271.7 274.7 36.4 38.4 7-B59 14-B50 361.7 5517 4749 6771 6003 76,051 76,819 76,021 76,789 34 14 340 140
286.9 290.1 36.4 38.4 7-B63 14-B55 386.7 5517 4749 6771 6003 81,260 82,204 81,207 82,151 34 16 340 160
302.3 305.8 36.3 38.4 7-B67 14-B59 411.7 5517 4749 6771 6003 85,889 86,763 85,728 86,602 36 16 360 160
330.2 333.7 ----46.4 7-C71 14-C63 456.7 5467 4619 6948 6100 --------93,492
345.4 349.1 ----46.4 7-C75 14-C67 481.7 5467 4619 6948 6100 ---------
361.3 365.3 ----46.4 7-C80 14-C71 506.7 5467 4619 6948 6100 ---------
382.1 386.3
TOP OF SLAB TO ABUT. CONSTR. JT. AT C.L. ABUT. BRG. TOP OF SLAB TO PIER TOP AT C.L. PIER* TOP OF SLAB TO ABUT. CONSTR. JT. AT C.L. ABUT. BRG. TOP OF SLAB TO PIER TOP AT C.L. PIER*
"U" "U" "U" "U" KIPS KIPS "B" "D" "S" "X"
3-8 3-6 3-8 3-6 471.8 264.7 169 168 141-10 6-7
3-7 3-6 3-7 3-6 509.8 274.5 184 183 154-4 7-1
4-2 4-1 4-2 4-1 583.3 283.9 199 198 166-10 7-7
4-2 4-1 4-2 4-1 623.5 293.1 214 213 179-4 8-1
4-2 4-1 4-3 4-2 663.8 302.2 229 228 191-10 8-8
4-8 4-7 4-8 4-7 799.8 311.0 244 243 204-4 9-2
4-8 4-7 4-8 4-7 845.3 322.9 259 258 216-10 9-8
4-9 4-7 4-9 4-8 891.2 341.9 274 273 229-4 10-2
4-9 4-7 4-10 4-8 936.0 362.6 294 293 246-0 10-2
STRUCTURAL CONCRETE ABUTMENTS (w/ WOOD PILES) STRUCTURAL CONCRETE ABUTMENTS (w/ STEEL H PILES) PRETENSIONED PRESTRESSED CONCRETE BEAM, CENTER SPAN PRETENSIONED PRESTRESSED CONCRETE BEAM, END SPAN CONCRETE RAIL (BARRIER OR OPEN) STRUCTURAL STEEL (w/ PILE BENT PIERS & DRAINS) STRUCTURAL STEEL (w/ PILE BENT PIERS & NO DRAINS) STRUCTURAL STEEL (w/ TEE PIERS & DRAINS) STRUCTURAL STEEL (w/ TEE PIERS & NO DRAINS) EPOXY COATED REINF. STEEL (w/ WOOD PILES & BARRIER RAIL) EPOXY COATED REINF. STEEL (w/ WOOD PILES & OPEN RAIL) EPOXY COATED REINF. (w/ STEEL H PILES & BARRIER RAIL) EPOXY COATED REINF. (w/ STEEL H PILES & OPEN RAIL) NO. OF WOOD PILES, TREATED FOR TWO ABUTMENTS NO. OF STEEL H-PILES FOR TWO ABUTMENTS (HP 10 x 57) PREBORED HOLES (W/WOOD PILES) PREBORED HOLES (W/STEEL H-PILES)
----46.4 7-C80 14-C80 D.L. PIER REACTION (D.L. + F.W.S.) 540.0 5467 4619 6948 NO. OF SPACES FOR 6a1 BARS (BOTTOM) AND 5j1 BARS (TOP) 6100 --------OUT TO OUT OF SLAB SLAB TRANSVERSE CONSTR. JT. DISTANCE FROM C.L. PIER L.L. PIER REACTION (HL93) NO IMPACT NO. OF SPACES FOR 6a1 BARS (TOP) STRAIGHT GRADE
*
138-10 151-4 163-10 176-4 188-10 201-4 213-10 226-4 243-0
VALUES SHOWN ARE FOR FIXED PIERS ONLY AND ALLOW FOR INCH DEFLECTION OF THE 1 INCH
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
NEOPRENE BEARING PAD. AT EXPANSION PIER 128.8 130.1 47.3 48.0 49.0 49.5 7.2 36.7 38.4 137.4 138.8 51.1 51.9 51.4 51.9 7.2 36.7 38.4 152.0 153.6 54.9 55.7 57.2 57.8 7.6 36.4 38.4 160.8 162.5 58.7 59.6 59.8 60.4 7.6 36.4 38.4 169.6 171.5 62.3 63.3 62.8 63.4 7.6 36.3 38.4 188.0 189.9 66.4 67.4 67.4 68.0 8.4 ----46.4 197.0 199.0 70.2 71.2 69.8 70.5 8.4 ----46.4 206.4 208.6 74.1 75.2 72.4 73.1 8.4 ----46.4 227.2 229.6 74.1 75.2 72.4 73.1 8.4 ----46.4 ** WINGWALLS APPLY ONLY TO BRIDGES USING "C" BEAMS. LOCATIONS ADD 3 INCHES TO "U" VALUES SHOWN. 1 0-1 1
SUPERSTRUCTURE DETAILS
0 SKEW
H44-09-07
9/29/2011
2:43:23 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-09-07
11x17_pdf.pltcfg
369 46-10
429 46-10
SLAB LONGITUDINAL, TOP & BOTT. SLAB LONGITUDINAL, TOP & BOTT., ENDS SLAB LONGITUDINAL, TOP @ PIERS SLAB LONGITUDINAL, TOP @ PIERS SLAB LONGITUDINAL, TOP @ PIERS
212 212 98
212 212 98
318 212 98
318 212
40-0 33-6
13,267 7,407
318 212
40-0 39-9
13,267 8,789
424 212
40-0 27-0
17,689 5,970
424 212
40-0 33-3
17,689 7,352
424 212
40-0 39-6
17,689 8,734
530 212
40-0 28-10
22,112 6,376
98
15-10
3,172
98
17-0
3,405
98
18-0
PIER DIAPH. ENDS PIER & ABUT. DIAPH. LONGIT. PIER & ABUT. DIAPH. LONGIT. PIER DIAPH. LONGIT. ABUT. DIAPH. ENDS ABUT. DIAPH. LONGIT. B.F. PAVING NOTCH LONGIT. ABUT. DIAPH. WING EXT. LONGIT. ABUT. DIAPH. WING EXT. LONGIT. PIER DIAPH. HOOPS PIER DIAPH. TIES ENDS PIER DIAPH. TIES PIER DIAPH. HOOPS ENDS
12 108 36 4 12 16 8
12 108 36 4 12 16 8
12 108 36 4 12 16 8
12 108 36 4 12 16 8
12 108 36 4 12 16 8
12 108 36 4 12 16 8 24 24
3-6 5-11 5-0 22-10 5-0 24-6 24-2 10-9 10-8 10-8 2-7 2-9 10-6
12 108 36 4 12 16 8 24 24 48 4 48 4
3-6 5-11 5-0 22-10 5-0 24-6 24-2 10-9 10-8 10-8 2-7 2-9 10-6
12 108 36 4 12 16 8 24 24 48 4 48 4
3-6 5-11 5-0 22-10 5-0 24-6 24-2 10-9 10-8 10-8 2-7 2-9 10-6
12 108 36 4 12 16 8 24 24 48 4 48 4
3-6 5-11 5-0 22-10 5-0 24-6 24-2 10-9 10-8 10-8 2-7 2-9 10-6
48 4 48 4
421 11 138 34
48 4 48 4
421 11 138 34
48 4 48 4
484 11 138 40
48 4 48 4
484 11 138 40
48 4 48 4
484 11 138 40
48 4 48 4
36
25-10
2,483
36
25-10
2,483
36
25-10
2,483
36
25-10
2,483
36
25-10
2,483
36 16 16
36 16 16
36 16 16
36 16 16
ABUT. VERT. ABUT. DIAPH. VERT. B.F. ABUT. DIAPH. WING EXT. VERT.
158 74
6-8 15-3
2,812 3,013
158 74
6-8 15-3
2,812 3,013
158 74
7-3 15-3
3,058 3,013
158 74
7-3 15-3
3,058 3,013
158 74
7-3 15-3
3,058 3,013
154 74 40
154 74 40
154 74 40
154 74 40
ABUT. WING HORIZ. B.F. ABUT. TO WING ANCHOR ABUT. WING HORIZ. TRAFFIC FACE ABUT. TO WING ANCHOR TOP OF SLAB TRANSV. (AT RAIL) PAVING NOTCH PAVING NOTCH
28 56 28
28 56 28
28 56 28
28 56 28
28 56 28
36 12 36 12
36 12 36 12 518 78 78
36 12 36 12 548 78 78
36 12 36 12 588 78 78
338 78 78
368 78 78
398 78 78
428 78 78
458 78 78
488 78 78
120/152
10-6
1314/1665 136/152
10-6
1489/1665 136/148
10-6
1489/1621 144/148
10-6 1577/1621
156 24 32
144 24 36
144 24 36
144 24 36
5s1
WING VERT.
64
5-10
389
64
5-10
389
64
6-2
412
64
6-2
412
64
6-2
412
64
6-11
462
64
6-11
462
64
6-11
462
64
6-11
462
4t1
14
4-6
42
14
4-6
42
14
4-6
42
14
4-6
42
14
4-6
42
14
4-9
44
14
4-9
44
14
4-9
44
14
4-9
44
#2
PILE SPIRAL (WOOD/STEEL)* SPIRAL SPACERS, L 7/8 x 7/8 x 1/8 x 0.70 (WOOD/STL.)* *EPOXY COATING NOT REQUIRED SUB TOTAL W/ WOOD PILES** SUB TOTAL W/ STEEL H-PILES** **RAIL REINFORCING NOT INCLUDED
30/14 90/42
38-6 1-10
193/90 116/54
30/14 90/42
38-6 1-10
193/90 116/54
34/14 102/42
38-6 1-10
219/90 131/54
34/16 102/48
38-6 1-10
219/103 131/62
36/16 108/48
38-6 1-10
231/103 139/62
20 60
38-6 1-10
129 77
22 66
38-6 1-10
141 85
22 66
38-6 1-10
141 85
22 66
38-6 1-10
141 85
58,261 58,447
62,096 62,282
66,704 66,674
71,381 71,328
BARRIER RAIL OPEN RAIL 3 -3 A, B BM. 3 -9 C BM. 2-5 10 2-0 6-8 3-10
3 1 0
8,788 9,409 6
9,347 10,115
9,879 10,823
10,478 11,352
11,445 13,289
12,003 13,756
12,576 14,526
13,312 15,308
3 0
2 -7
2 -7
3 -6
2 -1 0
4 -0
1-8
8g3
D=3
2 -2
D=2
D=8
D=2
1 1
1 1
2 -7
1 1
1 4
5d1
12-0
6p3
4t1
0 3
4 1
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 0
D=3
5d5
D=2
2 -6
8f3, 8f4
D=6
2 1 0
5h3
2-7 2-8 5p1 1 -0 1 -0 5p2 1 -0 3-9
D=2
5d8
5 D=3
2 1 0
5h4
D=3
5k2
5 1
3-11
1-6
5e2 5e3
1-6 1-8
8f3 8f4
7-7 6-0
D=2
2-9
7-11
5k1
H44-10-07
47-2 CONSTANT 1-7 LEVEL 44-0 ROADWAY 1-7 LEVEL TOP OF SLAB 1 -1 1" CHAMFER DEPTH 3" PVC PIPE 5k1 8g3 8g1 TOP OF SLAB
-1 1
1 -3
1 -1
PVC PIPE
5d7
5d2
1 -3
5d6 5k2
1-3 5h2 4t1 COIL ROD S3 x 7.5 KEYWAY FORMED BY BEVELED 2 x 8 5p1
4t1
S3 x 7.5 3 -3 8f1
WOOD PILING 2 -0
(1) HAIR AND JUTE RUG PADDING, RUBBERIZED ON BOTH SIDES, AND WEIGHING NOT LESS THAN 47 OZ. PER SQ. YD.
2 -0
STEEL H-PILE
3 -0
(2) BONDED URETHANE OR BONDED POLYFOAM WITH A MINIMUM DENSITY OF 5 LBS. PER CU. FT. AND SHALL BE AT LEAST IN. THICK, (MATERIAL LESS THAN IN. IN THICKNESS MAY BE RUG 1-6 1-6 PADDING USED, BUT WILL REQUIRE ADDITIONAL WRAPS FOR A TOTAL OF AT LEAST ONE INCH). 3-0
CL.
5d5
4t1
TOP OF PI LE
1-6
1-7
THE SPIRAL AT THE TOP OF EACH PILE TO BE 7 TURNS OF NO. 2 BAR, 21" DIAMETER, 3" PITCH WITH 3 - L x x SPACERS PUNCHED TO HOLD SPIRAL.
1 0 4 S P A . @ 1 2 1 3
8g1 S3 x 7.5 8g1 5h2 3" PVC PIPE. EACH WING. DESI GN LOADS CHANGED TO LRFD. ABUT.WI NG SHAPE CHANGED. 8g1 KEYWAY FORMED BY BEVELED 2x8 1-3 1-3 TYP. 5d5 3 -1 GUTTER LINE 5d2 & 5d3
1 1
SPACING FOR: 3 43- 8g1 BACK FACE 36- 8g1 FRONT FACE
2 @ 0-8
TOP OF PI LE
CL.
37- 8g3 BACK FACE 39- 5k1 & 5k2 BACK FACE
|-|
138-10 151-4 163-10 176-4 188-10
ABUT. BRG.
B 5d6 (MIN. LAP 8g1 FIELD 5k1 & 5k2 5d7 (MIN. LAP AT | = 2-2) 23-7 8g3
T Y P . 3
NOTE:
AT | 2-2)
ABUTMENT NOTES:
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR REINFORCING BAR IS TO BE 2" UNLESS OTHERWISE NOTED OR SHOWN.
NO. OF PILES PER ABUT. 1 2 PILE BEARING (TONS) STRENGTH I DESIGN LOAD (KIPS) "A" PILE SPACES "B" (FT. - IN.) H-PI LES 1 2 STEEL WI TH "C" (FT. - IN.) "D" EQUAL SPACES NO. OF PILES PER ABUT. PILE BEARING (TONS) STRENGTH I DESIGN LOAD (KIPS)
SHIFT 8g1 BARS IN F.F. AS NECESSARY TO MISS BEAMS. PLACE 8g3 BARS PARALLEL TO LONGIT. STEEL.
BEND
5h2 IF NECESSARY TO PREVENT DAMAGE TO THE END OF THE BRIDGE DECK OR BACKWALL FROM CONSTRUCTION EQUIPMENT, AN APPROPRIATE METHOD OF PROTECTION
PART SECTION A - A
GUTTER LINE
" C "
APPROVED BY THE ENGINEER SHALL BE PROVIDED BY THE BRIDGE CONTRACTOR AT NO EXTRA COST TO THE COUNTY OR STATE.
ABUTMENT PILES ARE TO BE DRIVEN TO THE DESIGN BEARING VALUE AS GIVEN IN THE ABUTMENT PILE
3 -1
SPACING TABLE.
" B "
PLACE 5h2 BAR AT 1:6 SLOPE TO MATCH TRAFFIC SIDE OF ABUTMENT WING FACE. (BOTH SIDES TYPICAL)
1 -6
2
3 -0
5p2
1-0
1 0
1 -6
" C "
| PILES
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
3 -1
| ABUTMENT
1 5
| ROADWAY
ABUTMENT DETAILS
15 SKEW A & B BEAMS
H44-11-07
47-2 CONSTANT 1-7 LEVEL 44-0 ROADWAY 1-7 LEVEL 1 -1 TOP OF SLAB 5d8 (TRAFFIC FACE) 5d9 (BACK FACE) C
-1 1
1" CHAMFER
1 -1
ABUTMENT NOTES:
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE 8g 1 MI N.EMBED. TO NEAR REINFORCING BAR IS TO BE 2" UNLESS OTHERWISE NOTED OR SHOWN. 5d7 5d2
PIPE 6g4
5d8 5d9
MI N.EMBEDMENT
3" PVC
6g 4 BARS
1 -3
1 -3
IF NECESSARY TO PREVENT DAMAGE TO THE END OF THE BRIDGE DECK OR BACKWALL FROM CONSTRUCTION EQUIPMENT, AN APPROPRIATE METHOD OF PROTECTION APPROVED BY THE ENGINEER SHALL BE PROVIDED BY THE BRIDGE CONTRACTOR AT NO EXTRA COST TO THE COUNTY OR STATE.
5d6
S3 x 7.5
5h4
5h2
1 -9
ABUTMENT PILES ARE TO BE DRIVEN TO THE DESIGN BEARING VALUE AS GIVEN IN THE ABUTMENT PILE SPACING TABLE.
2 -0 TOP
5p2 2 CL. 5h2 (BACK FACE) 5h4 (TRAFFIC FACE) 3" CL. 6p3
OF PI LE
CONSTR. JOINTS
8f4 5p2
5p1
2 CL. 3-0
2 CL.
NOTE: THE SPIRAL AT THE TOP OF EACH PILE TO BE 7 TURNS OF NO. 2 BAR, 21" DIAMETER, 3" PITCH WITH 3 - L x x SPACERS PUNCHED TO HOLD SPIRAL.
PART SECTION B - B
23-8 23-8
" C "
4t1
6-10
3-1
1"
=4 2 5
1-6
1-7
8g1 5 S3 x 7.5
1 -6 1 2 4 S P A . @ 1 1 1 5
4 SPA.@ 1 -0 = 4 -0
8f1
3 -0
" B "
2 @ 0-8
4 -1 1
3" PVC 6g4 PIPE KEYWAY FORMED BY BEVELED 2x8 8g1 1-3 1-3 TYP.
5 p 1D O U B H L O E O P S 1 P 0 A C 1 I N 0" G D "E Q U A L
6 -6
5p1
S P A C E S1 0
" C " 1 0
REVI SED 01 -1 2 - ADDED FI ELD BEND 5h4 BAR TO AVOI D PI LE I N ABUTMENT WI NG NOTE.
8f3
5d5 3 -1 B 5d6 8g1 FIELD 5k1 & 5k2 5d7 5d8 3-0 NOTE: SHIFT 8g1 BARS IN F.F. AS NECESSARY TO MISS BEAMS. PLACE 8g3 BARS PARALLEL TO LONGIT. STEEL. 6g4 3" PVC
GUTTER LINE 8f4
2 -1 0
TYP.
1 -6
(MIN. LAP
| ABUTMENT
4 9 8 f 1M I N . L A P
5p4
8f5
PART SECTION A - A
*
5c3
5c14
|-|
201-4 213-10 226-4 243-0
GUTTER LINE
| PILE
ABUT. BRG.
8 5-6 2-6 3
1-4
1-7
1"
5d9
5d8
1 -6
5d8
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
2 11 50 146 CL.
6g4
1 2
01 -1 2
ABUTMENT DETAILS
15 SKEW C BEAMS
H44-12-07
QUANTITIES.
12/28/2011
1:15:44 PM
tsorens
W:\Highway\Bridge\NewStandards\Jan_2012_Release\H44-07.dgn
h44-12-07
11x17_pdf.pltcfg
1 -6
5 -0
NOTE: BRIDGE IS SYMMETRICAL ABOUT | 7-0 BARRIER RAIL END SECTION FACE TO FACE OF BARRIER RAIL END SECTIONS 5e4 BARS (SEE BARRIER RAIL LAYOUT SHEET) 4" MI N.CL. A D PARALLEL TO THE THEORETICAL | GRADE
6c4 BARS
~ 5c5-10
1 -6
~ 6c4 5b1 & b3 ELEV. A BEAM PRESTRESSING STEEL STRANDS 5d5 ~ 6c3 3 ~ 5c5-10 ELEV. B 1 x 8 x 0-8 INDENTATION SPACED @ 2-0
5e1 &
2 -3 MI N.
3 EQ.SPS.
5k1
6 -6 ( BBEAM
6 -2 ( ABEAM
5d2
5b1 5e1
5d2
5s1 2 CL.
5k2 5d3 8g3 5d6 4t1 " x 1-3 COIL ROD S3 x 7.5 | BEARINGS 8g1 SEE DETAIL "A" 5e3 5d4 5d3 4t1 D 2 EQ. 4 8 5s1
5h2
SECTION D-D
~ NOTE: SPS. 5h2 SEE END SECTION DETAILS IN THESE PLANS FOR DETAILS OF BARRIER RAIL END SECTION. REINFORCING BARS 6c3, 6c4, 5c5-10, 6d2 & 4t1 ARE INCLUDED IN THE SUPERSTRUCTURE QUANTITIES.
8g1
3" PVC MIDWAY BETWEEN | ABUTMENT BEARING NOTE: PLUG 3" PVC PIPE WITH EXPANDING FOAM PRIOR TO BACKFILLING BEHIND ABUTMENTS. | ABUTMENT BEARING TO | ABUTMENT BEARING | ABUTMENT BEARING TO | PIER | PIER BEAM BEARINGS MIDWAY BETWEEN BEAM BEARINGS 1-6 9 9 " PREFORMED EXPANSION JOINT FILLER 5h2 2-1 PIPE
8g1
SECTION A-A
MIDWAY BETWEEN BEARINGS 1" HOLE (TYP.) A EXPANS.PI ER 5
| TO | BEAM BEARINGS
EXPANSION PIER
(REQUIRED AT ONE PIER, ONLY IF TEE PIERS ARE USED)
ABUTMENT
FIXED PIER
5 ABUTMENT " x 1-3 COIL ROD 9 (BENT 6 NEOPRENE BEARING PAD (9 x 1 x 1-3)
3 1
PIER
1-3
DETAIL "C"
| PIER 6
5d4 6
5d4
1 -4
PRESTRESSED STRANDS
6 -1 0
| ABUT. BRG.
5d3 5e1
END OF BEAMS 2 4
| BEAM BEARINGS
44 -0 ROADWAY
3 1
| BEAM 6 BEARING
1 3
8 1
1 6
11
11
4-5 e1
1 6
5e3
| BEAM
DETAIL "A"
4-0 2-0 1-0
1" THICK STRIPS OF PREFORMED EXPANSION JOINT FILLER AROUND BEARINGS, FACE OF STEPS, SIDES AND ENDS OF KEYWAYS.
SECTION B-B
1 -4
PART PLAN
5c10
~ 6c4
5h1
5s1
6c3
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 -7
2@7 ~ 6c4
5 SPA. @ 6
6 SPA. @ 5
1 1 -09
2@7
3 @ 6
LONGITUDINAL SECTION
15 SKEW A & B BEAMS
PART PLAN
H44-13-07
9/29/2011
2:43:29 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-13-07
11x17_pdf.pltcfg
11
11
FI XED PI ER
1 -1 1
9 9
NOTE: BRIDGE IS SYMMETRICAL ABOUT | 7-0 BARRIER RAIL END SECTION FACE TO FACE OF BARRIER RAIL END SECTIONS 5e4 BARS SEE BARRIER RAIL DETAILS FOR BARS AND BAR SPACING A D (SEE BARRIER RAIL LAYOUT SHEET) 4" MI N.CL. PARALLEL TO THE THEORETICAL | GRADE
~ 5b1 & b3 5d8 (TRAFFIC FACE) 5d9 (BACK FACE) BEAM PRESTRESSING STEEL STRANDS ELEV. A 3" PVC PIPE ~ 6c3 3 ELEV. B ~ 5c5-10 ELEV. C 6c4 1 x 8 x 0-8 INDENTATION SPACED @ 2-0
5e1 &
5 EQ.SPACES:5d
3" PVC PIPE 5d2 5d7 7 -3 5k2 8g3 5d6 5d3 5e3 5d4 5d3 4t1 D 5b1 5e1 5d2 5d5 C C
2 CL. 3" PVC 5d9 PIPE 5d8 6g4 5h4 1 -9 MI N. | WEB COIL TIE 5 PIER 3 JOINT FILLER. EMBED.
8g1
8g1 6g4 MIDWAY BETWEEN BEAM BEARINGS MIDWAY BETWEEN BEAM BEARINGS 1-6 9 9 " PREFORMED A 2-1 5h2 (BACK FACE) 5h4 (TRAFFIC FACE) 5h1 (BACK FACE)
SPS. :5h
4t1
5s1
2 EQ. 4
5h2
| PIER 6
5d4 6 NOTE:
| ABUTMENT BEARING
| TO | BEAM BEARINGS
PLUG 3" PVC PIPE WITH EXPANDING FOAM PRIOR PRESTRESSED STRANDS TO BACKFILLING BEHIND ABUTMENTS. | ABUTMENT BEARING TO | ABUTMENT BEARING | ABUTMENT BEARING TO | PIER | PIER
EXPANSION PIER
(REQUIRED AT ONE PIER, ONLY IF TEE PIERS ARE USED)
SECTION A-A
MIDWAY BETWEEN BEARINGS
ABUTMENT
END OF BEAMS 2 4 | BEAM BEARINGS
FIXED PIER
COIL TIE
DETAIL "A"
MIDWAY BETWEEN 1 -7 BEARINGS 5e4 11 5e2 1 -7 10 1-3 2-2 " x 1-3 COIL ROD 9 (BENT 6
DETAIL "C"
3 5 ABUTMENT ) 11 11 4
REVI SED 01 -1 2 - ADDED FI ELD BEND 5h4 BAR TO AVOI D PI LE I N ABUTMENT WI NG NOTE.
4-0 ~ 5c10
2-0
5d4
1 -5
6 -1 0
5d8 1 -7
5e1
| ABUT. BRG.
5d3
1 -7
40 -0 ROADWAY
1 3
4-5 e1
1 6 1 6
5e3 11 11
3 1
5d9 ~ 5c5-10 3
~ 6c4
5h1
5s1
| BEAM BEARING
6c3
8 1
| BEAM
2@7
3 @ 6
1 -5
1" THICK STRIPS OF PREFORMED EXPANSION JOINT FILLER AROUND BEARINGS, FACE OF STEPS, SIDES AND ENDS OF KEYWAYS.
SECTION B-B
NOTE: SEE SHEET H44-37-07 FOR EXPANSION PIER
2@7 ~ 6c4
5 SPA. @ 6
6 SPA. @ 5
PART PLAN
" x 1-3 COIL ROD 6c4 BARS
BEARING DETAILS
| PIER
CONSTRUCTION JOINT
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 -6
~ 6c4 ~ 6d2
2 -3 MI N.
~ NOTE: SEE END SECTION DETAILS IN THESE PLANS FOR 3" PVC PIPE DETAILS OF BARRIER RAIL END SECTION. REINFORCING BARS 6c3, 6c4, 5c5-10, 6d2 & 4t1
5s1 2 CL.
LONGITUDINAL SECTION
15 SKEW C BEAMS
PART PLAN
H44-14-07
SECTION D-D
12/28/2011 1:15:45 PM tsorens W:\Highway\Bridge\NewStandards\Jan_2012_Release\H44-07.dgn h44-14-07 11x17_pdf.pltcfg
| - | ABUTMENT BRGS. | ABUT. BRG. - | PIER | PIER - | PIER "J" SPACES @ 10": 5j1 10 "E" SPACES @ 10": 6a1 10 | PIER - | ABUT. BRG. 13 SPACES @ 10": 6a2 7 TOP SLAB REINFORCING BARS
"X"
"X"
CONSTRUCTION JOINT
"X"
"X"
5j1
b3
TOP REINFORCING
6a2 (43-4)
5b1 6a1 6a1 6a3 (44-11) PERMISSIBLE TRANSVERSE CONSTRUCTION JOINT 6a3 (44-11) | ROADWAY
4 BOTTOM
6a3 (4-6)
| ABUT. BRG. 10
10 1-0
13 SPACES @ 10": 6a3 REVI SED 1 0-1 1 - THE ESTI MATED QUANTI TI ES FOR THE STRUCTURAL STEEL WI TH DRAI NS WAS CHANGED.
SLAB LAYOUT
(LEFT AHEAD SKEW SHOWN, RIGHT AHEAD SKEW SIMILAR)
NOTE: CONCRETE DECK SLAB SHALL BE PLACED IN SECTIONS AND SEQUENCES INDICATED. ALTERNATE PROCEDURES FOR PLACING SLAB CONCRETE MAY BE SUBMITTED FOR APPROVAL TOGETHER WITH A STATEMENT OF THE PROPOSED METHOD AND EVIDENCE THAT THE CONTRACTOR POSSESSES THE NECESSARY EQUIPMENT AND FACILITIES TO ACCOMPLISH THE REQUIRED RESULTS.
ESTIMATED QUANTITIES
(SUPERSTRUCTURE PLUS INTEGRAL ABUTMENTS) STRUCTURAL CONCRETE SUPERSTRUCTURE (INCLUDES ABUTMENT WINGS)
151-4
163-10
176-4
188-10
201-4
213-10
226-4
243-0
GENERAL DATA
VERTICAL CURVE
151-4
163-10
176-4
188-10
1 -7
REINFORCING
201-4
6a1
1 -7
213-10
226-4
243-0
C.Y. C.Y. C.Y. C.Y. NO. NO. L.F. LB. LB. LB. LB. LB. LB. LB. LB. NO. NO. L.F. L.F.
238.3 240.8 38.3 40.0 7-A50 14-A42 311.9 5689 5009 6943 6263 66,715 67,380 66,900 67,565 30 14 300 140
294.1 297.3 38.0 40.0 7-B63 14-B55 386.9 5777 5009 7031 6263 81,500 82,444 81,446 82,390 34 16 340 160
309.7 313.2 37.9 40.0 7-B67 14-B59 411.9 5777 5009 7013 6263 86,127 87,001 85,966 86,840 36 16 360 160
338.2 341.7 ----47.8 7-C71 14-C63 456.7 5742 4894 7223 6375 --------93,737
353.4 357.1 ----47.8 7-C75 14-C67 481.7 5742 4894 7223 6375 --------99,278
369.3 373.3 ----47.8 7-C80 14-C71 506.7 5742 4894 7223 6375 ---------
390.1 394.3
TOP OF SLAB TO ABUT. CONSTR. JT. AT C.L. ABUT. BRG. TOP OF SLAB TO PIER TOP AT C.L. PIER* TOP OF SLAB TO ABUT. CONSTR. JT. AT C.L. ABUT. BRG. TOP OF SLAB TO PIER TOP AT C.L. PIER*
"U" "U" "U" "U" KIPS KIPS "E" "H" "J" "S" "X"
3-8 3-6 3-8 3-6 481.4 264.7 155 154 167 141-11 6-7
4-2 4-1 4-2 4-1 635.1 293.1 200 199 212 179-5 8-1
4-2 4-1 4-3 4-2 675.5 302.2 215 214 227 191-11 8-8
4-9 4-7 4-10 4-8 948.7 362.6 280 279 292 246-1 10-2
----47.8 7-C80 14-C80 D.L. PIER REACTION (D.L. + F.W.S.) 540.0 5742 4894 7223 NO. OF SPACES FOR 6a1 BARS (BOTTOM) 6375 --------NO. OF SPACES FOR 5j1 BARS (TOP) OUT TO OUT OF SLAB SLAB TRANSVERSE CONSTR. JT. DISTANCE FROM C.L. PIER L.L. PIER REACTION (HL93) NO IMPACT NO. OF SPACES FOR 6a1 BARS (TOP) STRAIGHT GRADE
PRETENSIONED PRESTRESSED CONCRETE BEAM, CENTER SPAN PRETENSIONED PRESTRESSED CONCRETE BEAM, END SPAN CONCRETE RAIL (BARRIER OR OPEN) STRUCTURAL STEEL (w/ PILE BENT PIERS & DRAINS) STRUCTURAL STEEL (w/ PILE BENT PIERS & NO DRAINS) STRUCTURAL STEEL (w/ TEE PIERS & DRAINS) STRUCTURAL STEEL (w/ TEE PIERS & NO DRAINS) EPOXY COATED REINF. STEEL (w/ WOOD PILES & BARRIER RAIL) EPOXY COATED REINF. STEEL (w/ WOOD PILES & OPEN RAIL) EPOXY COATED REINF. (w/ STEEL H PILES & BARRIER RAIL) EPOXY COATED REINF. (w/ STEEL H PILES & OPEN RAIL) NO. OF WOOD PILES, TREATED FOR TWO ABUTMENTS NO. OF STEEL H-PILES FOR TWO ABUTMENTS (HP 10 x 57) PREBORED HOLES (W/WOOD PILES) PREBORED HOLES (W/STEEL H-PILES)
14-A46 14-B50 336.9 5689 5009 6943 6263 361.9 5777 5009 7031 6263
71,451 76,291 72,072 77,059 71,529 76,260 72,150 77,028 32 14 320 140 34 14 340 140
VALUES SHOWN ARE FOR FIXED PIERS ONLY AND ALLOW FOR INCH DEFLECTION OF THE 1 INCH NEOPRENE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
138-10
151-4
163-10
176-4
188-10
201-4
213-10
226-4
243-0
3 INCHES TO "U" VALUES SHOWN. 130.2 131.5 47.3 48.0 53.6 54.1 7.2 38.3 40.0 138.8 140.2 51.1 51.9 56.2 56.7 7.2 38.1 40.0 153.6 155.2 54.9 55.7 62.8 63.4 7.6 38.0 40.0 162.4 164.1 58.7 59.6 65.4 66.0 7.6 38.0 40.0 171.2 173.1 62.3 63.3 68.6 69.2 7.6 37.9 40.0 189.8 191.7 66.4 67.4 73.6 74.2 8.4 ----47.8 198.8 200.8 70.2 71.2 76.0 76.7 8.4 ----47.8 208.2 210.4 74.1 75.2 78.6 79.3 8.4 ----47.8 229.0 231.4 74.1 75.2 78.6 79.3 8.4 ----47.8 *** SEE SHEET H44-17-07 FOR ADDITIONAL CONCRETE REQUIRED IN ABUTMENT FOOTINGS. ** WINGWALLS APPLY ONLY TO BRIDGES USING "C" BEAMS. 1 0-1 1
SUPERSTRUCTURE DETAILS
15 SKEW
H44-15-07
9/29/2011
2:43:32 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-15-07
11x17_pdf.pltcfg
C BEAM LENGTH 46-10 VARIES VARIES WEIGHT 32,428 973 1,039 NO. 491
C BEAM LENGTH 46-10 VARIES VARIES WEIGHT 36,649 973 1,039 NO. 561 28 28
28 VARIES 28 VARIES
28 VARIES 28 VARIES
28 VARIES 28 VARIES
28 VARIES 28 VARIES
28 VARIES 28 VARIES
28 VARIES 28 VARIES
SLAB LONGITUDINAL, TOP & BOTT. SLAB LONGITUDINAL, TOP & BOTT., ENDS SLAB LONGITUDINAL, TOP @ PIERS SLAB LONGITUDINAL, TOP @ PIERS SLAB LONGITUDINAL, TOP @ PIERS
212 212 98
318 212 98
318 212 98
318 212
40-0 33-7
13,267 7,426
318 212
40-0 39-10
13,267 8,808
424 212
40-0 27-1
17,689 5,989
424 212
40-0 33-4
17,689 7,371
424 212
40-0 39-7
17,689 8,753
530 212
40-0 28-11
22,112 6,394
98
15-10
3,172
98
17-0
3,405
98
18-0
PIER DIAPH. ENDS PIER & ABUT. DIAPH. LONGIT. PIER & ABUT. DIAPH. LONGIT. PIER DIAPH. LONGIT. ABUT. DIAPH. ENDS ABUT. DIAPH. LONGIT. B.F. PAVING NOTCH LONGIT. ABUT. DIAPH. WING EXT. LONGIT. ABUT. DIAPH. WING EXT. LONGIT. PIER DIAPH. HOOPS PIER DIAPH. TIES ENDS PIER DIAPH. TIES PIER DIAPH. HOOPS ENDS
12 108 36 12 12 16 8
12 108 36 12 12 16 8
12 108 36 12 12 16 8
12 108 36 12 12 16 8
12 108 36 12 12 16 8
12 108 36 12 12 16 8 24 24
3-8 6-1 5-2 8-11 5-0 25-4 25-0 10-10 10-9 11-2 2-11 3-3 10-10
12 108 36 12 12 16 8 24 24 48 4 48 4
3-8 6-1 5-2 8-11 5-0 25-4 25-0 10-10 10-9 11-2 2-11 3-3 10-10
12 108 36 12 12 16 8 24 24 48 4 48 4
3-8 6-1 5-2 8-11 5-0 25-4 25-0 10-10 10-9 11-2 2-11 3-3 10-10
12 108 36 12 12 16 8 24 24 48 4 48 4
3-8 6-1 5-2 8-11 5-0 25-4 25-0 10-10 10-9 11-2 2-11 3-3 10-10
48 4 48 4
446 12 163 36
48 4 48 4
446 12 163 36
48 4 48 4
509 12 163 41
48 4 48 4
509 12 163 41
48 4 48 4
509 12 163 41
48 4 48 4
ABUT. FOOTING LONGIT. ABUT. EXTENSION LONGIT. ABUT. EXTENSION LONGIT. ABUT. EXTENSION LONGIT.
36
26-7
2,555
36
26-7
2,555
36
26-7
2,555
36
26-7
2,555
36
26-7
2,555
36 16 8 8
36 16 8 8
36 16 8 8
36 16 8 8
ABUT. VERT. ABUT. DIAPH. VERT. B.F. ABUT. DIAPH. WING EXT. VERT.
158 74
6-8 15-3
2,812 3,013
158 74
6-8 15-3
2,812 3,013
158 74
7-3 15-3
3,058 3,013
158 74
7-3 15-3
3,058 3,013
158 74
7-3 15-3
3,058 3,013
154 74 40
154 74 40
154 74 40
154 74 40
ABUT. WING HORIZ. B.F. ABUT. TO WING ANCHOR ABUT. WING HORIZ. TRAFFIC FACE ABUT. TO WING ANCHOR TOP OF SLAB TRANSV. (AT RAIL) PAVING NOTCH PAVING NOTCH
28 56 28
28 56 28
28 56 28
28 56 28
28 56 28
36 12 36 12
36 12 36 12 516 78 78
36 12 36 12 546 78 78
36 12 36 12 586 78 78
336 78 78
366 78 78
396 78 78
426 78 78
456 78 78
486 78 78
ABUTMENT HOOPS (WOOD/STEEL) ABUTMENT HOOPS ABUT. BOTT. AT PILES ABUT. HOOPS AT ENDS
112/144 8
10-6 10-8
1227/1577 120/144 89 8
128/144 8
10-6 10-8
1402/1577 128/140 89 8
10-6 10-8
1402/1533 136/140 89 8
10-6 10-8
1489/1533 89
148 24 32 8
136 24 36 8
136 24 36 8
136 24 36 8
5s1
WING VERT.
64
5-10
389
64
5-10
389
64
6-2
412
64
6-2
412
64
6-2
412
64
6-11
462
64
6-11
462
64
6-11
462
64
6-11
462
4t1
14
4-7
43
14
4-7
43
14
4-7
43
14
4-7
43
14
4-7
43
14
4-10
45
14
4-10
45
14
4-10
45
14
4-10
45
#2
PILE SPIRAL (WOOD/STEEL)* SPIRAL SPACERS, L 7/8 x 7/8 x 1/8 x 0.70 (WOOD/STL.)* *EPOXY COATING NOT REQUIRED SUB TOTAL W/ WOOD PILES** SUB TOTAL W/ STEEL H-PILES** **RAIL REINFORCING NOT INCLUDED
30/14 90/42
38-6 1-10
193/90 116/54
32/14 96/42
38-6 1-10
206/90 123/54
34/14 102/42
38-6 1-10
219/90 131/54
34/16 102/48
38-6 1-10
219/103 131/62
36/16 108/48
38-6 1-10
231/103 139/62
20 60
38-6 1-10
129 77
22 66
38-6 1-10
141 85
22 66
38-6 1-10
141 85
22 66
38-6 1-10
141 85
58,500 58,685
62,663 62,741
66,944 66,913
71,621 71,567
8,788 9,409
1 5
9,347 10,115
9,879 10,823
10,478 11,352
11,445 13,289
12,003 13,756
12,576 14,526
13,312 15,308
5d1
D=2 1-10
C BM.
5h4
A , B
A,B D=3
5d6
2 -7 4 D=2 D=4
3 0
2 -7
1 1
1 4
6 THUS 5
6p3
4t1
4 1
1 1
0 3
2 -7
3 -6
1 6
D=2 1-10
6 THUS
0 1
D=2
2-9
2-1
2 -1 0
4 -0
1 5
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1-4 D=2
5d5
2 -6
2-2
C BM. 1 -0 1 -0
8f1
D=2
2-7 2-8
5p1
8f3
5p4
5k2
D=2
1 -0
5p1, 5p2,
D=3
5 1
D=2
5p2, 5p4
1 0
5k1
H44-16-07
8g3
5d4
5h3
1-0 1-0
9/29/2011
2:43:33 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
| BEAMS @ | PIER 3 SPA. @ 10 (TYP.) LOW STEP a BARS 5n1 5 TYP. 10 TYP.
BAR LENGTH SHAPE NO.
5m1
6-4
20
132
24
159
30
198
33
218
36
238
5m1
20 ----
5 ----
56 ---188
24 ----
5 ----
67 ---226
20 4 ---
5 8 ---
56 119 --373
16 -4 --
5 -8 --
45 -195 -458
8 --4
5 --8
22 --309 569
5m1 5m1
6-3
20
130
24
156
30
196
33
215
36
235
20 ----
5 ----
56 ---186
24 ----
5 ----
67 ---223
20 4 ---
5 8 ---
56 119 --371
16 -4 --
5 -8 --
45 -195 -455
8 --4
5 --8
22 --309 566
* 8n4
| BEAMS @ | PIER 5 3 SPA. 3 SPA. @ 10 (TYP.) LOW STEP a BARS @ 1-3 8n2 10 10 5 3 SPA. @ 1-3 5 TYP. 10 TYP.
5n1
D=2
5m1 5m1
5m1
TYPICAL SECTION
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D = PIN DIAMETER.
| BEAMS @ | PIER 5 3 SPA. 3 SPA. @ 10 (TYP.) LOW STEP a BARS @ 1-3 8n3 10 10 5 4 EQ. SPA. 5 10 10 5 3 SPA. @ 1-3 5 TYP. 10 TYP.
NOTES:
THE TABLE BELOW LISTS THE ADDITIONAL CONCRETE VOLUME REQUIRED IN EACH ABUTMENT FOOTING/PIER CAP BASED ON THE ROADWAY GRADE AT EACH ABUTMENT FOOTING/PIER CAP. ADDITIONAL CONCRETE SHOULD BE ADDED TO THE PLANS FOR EACH ABUTMENT FOOTING/PIER CAP THAT HAS 0.5 CU. YDS. OR MORE OF ADDITIONAL CONCRETE. VALUES SHOULD BE EXCLUDED FOR SCENARIOS THAT HAVE LESS THAN 0.5 CU. YDS. OF ADDITIONAL CONCRETE PER SUBSTRUCTURE UNIT. VALUES MAY BE INTERPOLATED FOR GRADES BETWEEN THE VALUES SHOWN IN THE TABLE.
5n1
5m1 5m1
| BEAMS @ | PIER 5 3 SPA. @ 10 (TYP.) 3 SPA. @ 1-3 LOW STEP a BARS 5 TYP. 5n1 8n4
EACH TEE PIER CAP - ALL BEAMS EACH PILE BENT PIER - ALL BEAMS
5 10 4 EQ. SPA.
5 10 10
5 4 EQ. SPA.
5 10 10
5 4 EQ. SPA.
5 10 10
5
A, B BEAMS
---
0.5 0.6
0.8 1.0
1.1 1.3
1.4 1.7
10
C BEAMS
---
0.5 0.5
0.8 0.8
1.1 1.1
1.4 1.4
5m1 5m1
APPROVED BY BRI DGE ENGI NEER
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
ADDITIONAL QUANTITIES
15 SKEW
H44-17-07
9/29/2011
2:43:34 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-17-07
11x17_pdf.pltcfg
47-2 CONSTANT 1-7 LEVEL 44-0 ROADWAY 1-7 LEVEL TOP OF SLAB 1 -1 1" CHAMFER DEPTH 3" PVC PIPE 5k1 8g3 8g1 TOP OF SLAB
-1 1
1 -3
1 -1
5d7
5d2
1 -3
5d6 5k2
1-3 5h2 4t1 COIL ROD S3 x 7.5 KEYWAY FORMED BY BEVELED 2 x 8 5p1
4t1
S3 x 7.5 8f1
TOP OF PI LE
STEEL H-PILE
2 -0
(2) BONDED URETHANE OR BONDED POLYFOAM WITH A MINIMUM DENSITY OF 5 LBS. PER CU. FT. AND SHALL BE AT RUG 1-6 1-6 PADDING LEAST IN. THICK, (MATERIAL LESS THAN IN. IN THICKNESS MAY BE USED, BUT WILL REQUIRE ADDITIONAL 3-0 WRAPS FOR A TOTAL OF AT LEAST ONE INCH).
CL. NOTE: THE SPIRAL AT THE TOP OF EACH PILE TO BE 7 TURNS OF NO. 2 BAR, 21" DIAMETER, 3" PITCH WITH 3 - L x x 3-0
TOP OF PI LE
CL.
5d5
1-7
6 5 B 0 E A 9 B M E T S W P E A E C N E S B E @ A M 7 S 1 0 =
6-10
3-1
1-6
1-7 3 -5 23-7
3" PVC PIPE. EACH WING DESI GN LOADS CHANGED TO LRFD. ABUT.WI NG SHAPE CHANGED. FIELD BEND KEYWAY FORMED BY BEVELED 2x8 GUTTER LINE TYP. 1-3 1-3 8g1 8g1
4 7 4
" A "
5p2
1 1 4
1-0
1 0
P I L E S P A C E S @ " B "
5p1
E QU S A P L A C E S " D "
S P A . @ 1 3
1 0 1 0
1 0
SPACING FOR: 43- 8g1 BACK FACE 36- 8g1 FRONT FACE
NOTE: SHIFT 8g1 BARS IN F.F. AS NECESSARY TO MISS BEAMS. PLACE 8g3 BARS PARALLEL TO LONGIT. STEEL.
5 p 1 D H O O 4 U O 8 B P f L 9 1 E S P M A I C N I . N L G A P
1 -6
1 -6
3 -0
8f1
8g3 2 @ 5d6-(MIN. LAP AT | 2-2) 5k1 & 5k2 0-8 3 5d7-(MIN. LAP AT | = 2-2)
37- 8g3 BACK FACE 38- 5k1 & 5k2 BACK FACE | ABUTMENT
3 0
" C "
PART SECTION A - A
ABUTMENT PILE SPACING
"A" PILE SPACES "B" (FT. - IN.) PI LES WOOD WI TH "C" (FT. - IN.) "D" EQUAL SPACES NO. OF PILES PER ABUT. 1 2 PILE BEARING (TONS) STRENGTH I DESIGN LOAD (KIPS) "A" PILE SPACES "B" (FT. - IN.) H-PI LES STEEL WI TH "C" (FT. - IN.) "D" EQUAL SPACES NO. OF PILES PER ABUT. PILE BEARING (TONS) STRENGTH I DESIGN LOAD (KIPS)
|-|
138-10 151-4 163-10 176-4 188-10
ABUT. BRG.
8g1 14 3-6 2-8 2 15 20 58 7 7-0 2-8 4 8 41 117 15 3-3 2-10 1 16 20 56 7 7-0 2-8 4 8 42 122 16 3-0 3-2 1 17 20 57 7 7-0 2-8 4 8 45 131 17 2-10 3-1 1 18 20 56 7 7-0 2-8 4 8 47 135 17 2-10 3-1 1 18 20 57 7 7-0 2-8 GUTTER LINE
T Y P . 3
FIELD BEND
ABUTMENT NOTES:
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR REINFORCING BAR IS TO BE 2" UNLESS OTHERWISE NOTED OR SHOWN.
OF ABUTMENT
5h2
IF NECESSARY TO PREVENT DAMAGE TO THE END OF THE BRIDGE DECK OR BACKWALL FROM CONSTRUCTION EQUIPMENT, AN APPROPRIATE METHOD OF PROTECTION APPROVED BY THE ENGINEER SHALL BE PROVIDED BY
APPROVED BY BRI DGE ENGI NEER
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
ABUTMENT PILES ARE TO BE DRIVEN TO THE DESIGN 1 1 -09 BEARING VALUE AS GIVEN IN THE ABUTMENT PILE SPACING TABLE.
PLACE 5h2 BAR AT 1:6 SLOPE TO MATCH TRAFFIC 4 8 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. BARRIER RAIL NOT SHOWN IN DETAILS. 48 139 1 FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD. SIDE OF ABUTMENT WING FACE. (BOTH SIDES TYPICAL)
1 2
ABUTMENT DETAILS
30 SKEW A & B BEAMS
H44-18-07
9/29/2011
2:43:36 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-18-07
11x17_pdf.pltcfg
3 -5
| ROADWAY
47-2 CONSTANT 1-7 LEVEL 44-0 ROADWAY 1-7 LEVEL 1 -1 TOP OF SLAB 5d8 (TRAFFIC FACE) 5d9 (BACK FACE) C
-1 1
1" CHAMFER
A 3" PVC 3" PVC PIPE 8g1 (FRONT FACE & BACK FACE)
5d8
1 -1
ABUTMENT NOTES:
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR 8g 1 MI N.EMBED. REINFORCING BAR IS TO BE 2" UNLESS OTHERWISE NOTED OR SHOWN. 5d7 5d2
PIPE 6g4
5d9
MI N.EMBEDMENT
6g 4 BARS
1 -3
1 -3
IF NECESSARY TO PREVENT DAMAGE TO THE END OF THE BRIDGE DECK OR BACKWALL FROM CONSTRUCTION EQUIPMENT, AN APPROPRIATE METHOD OF PROTECTION APPROVED BY THE ENGINEER SHALL BE PROVIDED BY THE BRIDGE CONTRACTOR AT NO EXTRA COST TO THE COUNTY OR STATE.
5d6
S3 x 7.5
5h4
1 -9
ABUTMENT PILES ARE TO BE DRIVEN TO THE DESIGN BEARING VALUE AS GIVEN IN THE ABUTMENT PILE SPACING TABLE.
5h2
8f3 & 8f5 5p2 2 CL. 2 CL. 5h2 (BACK FACE) 5h4 (TRAFFIC FACE) 3" CL. 6p3
NOTE: THE SPIRAL AT THE TOP OF EACH PILE TO BE 7 TURNS OF NO. 2 BAR, 21" DIAMETER, 3" PITCH WITH 3 - L x x SPACERS PUNCHED TO HOLD SPIRAL.
1-7 3 2 @ 0-8 8g1 5d5 FIELD " x1-3 COIL ROD BEND 4t1
S A M E S | ABUT. BRG. P A C I N G 2 7
CONSTR. JOINTS
8f4 5p2
5p1
2 CL. 3-0
2 CL.
PART SECTION B - B
23-8 | ABUT. BRG. & | PILES 8 TYP.
6 5 B 0 E A 9 B M E T S W P E A E C N E S B E @ A M 7 S 1 0
1-8
" C "
1-6
1-7 6p3
6 -6
5 -0
4 -9
6 -6
8g1
4 7 4
1 2 4
REVI SED 01 -1 2 - ADDED FI ELD BEND 5h4 BAR TO AVOI D PI LE I N ABUTMENT WI NG NOTE.
S P A . @ 1 2
2 -1 0
TYP.
1-3
1-3
1-8
1-4
8 f 1
1 1 1
1 0
4 9 M I N . L A P
1 6
PVC
" C "
1 0
SPACING FOR: 41- 8g1 BACK FACE 36- 8g1 FRONT FACE 1"
| ABUTMENT
3 0
GUTTER LINE
8g3 NOTE: SHIFT 8g1 BARS IN F.F. AS NECESSARY TO MISS BEAMS. PLACE 8g3 BARS PARALLEL TO LONGIT. STEEL. 5d7-(MIN. LAP AT | = 2-2) 5k1 & 5k2 5d6-(MIN. LAP AT | 2-2) 2 @ 0-8 3
37- 8g3 BACK FACE 38- 5k1 & 5k2 BACK FACE 22-0
5d5
*
5c3
| PILE
1-6
1-6
ABUT. BRG.
5d9
5d8
1 -6
|-|
201-4 213-10 226-4 243-0
T Y P . 3
9 5-5 5p2 2-11 8f5 3 12 46 GUTTER LINE 134 5d8 1-4 1-7 1" 5d9 6g4 01 -1 2 CL. 3" PVC PIPE 2
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
6g4
NO. OF PILES PER ABUT. PILE BEARING (TONS) STRENGTH I DESIGN LOAD (KIPS)
1 2 1 2
FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD. FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS.
ABUTMENT DETAILS
30 SKEW C BEAMS
H44-19-07
12/28/2011
1:15:47 PM
tsorens
W:\Highway\Bridge\NewStandards\Jan_2012_Release\H44-07.dgn
h44-19-07
11x17_pdf.pltcfg
1 -6
PART SECTION A - A
3 -5
5p2
NOTE: BRIDGE IS SYMMETRICAL ABOUT | 7-0 BARRIER RAIL END SECTION FACE TO FACE OF BARRIER RAIL END SECTIONS 5e4 BARS (SEE BARRIER RAIL LAYOUT SHEET) 4" MI N.CL. A D PARALLEL TO THE THEORETICAL | GRADE
6c4 BARS
~ 5c5-10
1 -6
~ 6c4 5b1 & b3 ELEV. A BEAM PRESTRESSING STEEL STRANDS 5d5 ~ 6c3 3 ~ 5c5-10 ELEV. B 1 x 8 x 0-8 INDENTATION SPACED @ 2-0
5e1 &
2 -3 MI N.
3 EQ.SPS.
5k1
6 -6 ( BBEAM
6 -2 ( ABEAM
5d2
5b1 5e1
5d2
5s1 2 CL.
5k2 5d3 8g3 5d6 4t1 " x 1-3 COIL ROD S3 x 7.5 | BEARINGS SEE DETAIL "A" 5e3
5h2
SECTION D-D
~ NOTE: SPS. SEE END SECTION DETAILS IN THESE PLANS FOR 5h2 DETAILS OF BARRIER RAIL END SECTION. REINFORCING BARS 6c3, 6c4, 5c5-10, 6d2 & 4t1 ARE INCLUDED IN THE SUPERSTRUCTURE QUANTITIES.
8g1
8g1
MIDWAY BETWEEN | ABUTMENT BEARING NOTE: PLUG 3" PVC PIPE WITH EXPANDING FOAM PRIOR TO BACKFILLING BEHIND ABUTMENTS. BEAM BEARINGS
8g1
SECTION A-A
MIDWAY BETWEEN BEARINGS 1" HOLE (TYP.)
| TO | BEAM BEARINGS
1-6
EXPANSION PIER
A | ABUTMENT BEARING TO | PIER | PIER | ABUTMENT BEARING TO | ABUTMENT BEARING (REQUIRED AT ONE PIER, ONLY IF TEE
ABUTMENT
FIXED PIER
FI XED PI ER
EXPANS.PI ER
" RADIUS
PIER
DETAIL "C"
5e2 1 -7
| PIER 6
3 1
5d4 6
5d4
STRANDS
1 -1 0
END OF BEAMS 2 4 6
| BEAM BEARINGS
9
1 3
44 -0 ROADWAY
1 6 1 6
3 1 8 1
DETAIL "A"
4-0 2-0 1-0
| BEAM BEARING
SECTION B-B
NOTE: SEE SHEET H44-37-07 FOR EXPANSION PIER
1" THICK STRIPS OF PREFORMED EXPANSION JOINT FILLER AROUND BEARINGS, FACE OF STEPS, SIDES AND ENDS OF KEYWAYS.
1 -1 0
5c10
PART PLAN
BEARING DETAILS
COIL ROD
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
~ 6c3
LATEST REVI SI ON DATE
1 1 -09
LONGITUDINAL SECTION
30 SKEW A & B BEAMS
PART PLAN
H44-20-07
9/29/2011
2:43:39 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
1-11 1-11
1 -1 1
| WEB
NOTE: BRIDGE IS SYMMETRICAL ABOUT | 7-0 BARRIER RAIL END SECTION FACE TO FACE OF BARRIER RAIL END SECTIONS 5e4 BARS SEE BARRIER RAIL DETAILS FOR BARS AND BAR SPACING A D (SEE BARRIER RAIL LAYOUT SHEET) 4" MI N.CL. PARALLEL TO THE THEORETICAL | GRADE
~ 5b1 & b3 5d8 (TRAFFIC FACE) 5d9 (BACK FACE) BEAM PRESTRESSING STEEL STRANDS ELEV. A 3" PVC PIPE ~ 6c3 5 EQ.SPACES:5d 3 ELEV. B ~ 5c5-10 ELEV. C 6c4 1 x 8 x 0-8 INDENTATION SPACED @ 2-0
SEE DETAIL "C" ELEV. C TOP OF SLAB 5k1 6 3" PVC PIPE 5d2 5d7 7 -3 5k2 8g3 5d6 5d3 5j1
5e1 &
2 CL. 3" PVC 5d9 PIPE 5d8 6g4 5h4 1 -9 MI N. FI XED PI ER EXPANS.PI ER | WEB 3 5 PIER 1" MIN. EMBED.
5b1 5e1
5d2 5d5
8g1
8g1 6g4 MIDWAY BETWEEN BEAM BEARINGS MIDWAY BETWEEN BEAM BEARINGS 1-6 9 9 " PREFORMED A 2-1 5h2 (BACK FACE) 5h1 (BACK FACE) EXPANSION JOINT FILLER
SPS. :5h
4t1
5s1
2 EQ. 4
5h2
| PIER 6
5d4 6
NOTE:
| ABUTMENT BEARING
| TO | BEAM BEARINGS
PLUG 3" PVC PIPE WITH EXPANDING FOAM PRIOR PRESTRESSED STRANDS TO BACKFILLING BEHIND ABUTMENTS. | ABUTMENT BEARING TO | ABUTMENT BEARING | ABUTMENT BEARING TO | PIER | PIER
EXPANSION PIER
(REQUIRED AT ONE PIER, ONLY IF TEE PIERS ARE USED)
SECTION A-A
MIDWAY BETWEEN BEARINGS
ABUTMENT
END OF BEAMS 2 4 6 7-0 BARRIER RAIL END SECTION 6-6 WING EXTENSION | BEAM BEARINGS
FIXED PIER
DETAIL "A"
1 -7 MIDWAY BETWEEN BEARINGS 5e4 7
DETAIL "C"
3 5 ABUTMENT )
1-11
5e2 1 -7
REVI SED 01 -1 2 - ADDED FI ELD BEND 5h4 BAR TO AVOI D PI LE I N ABUTMENT WI NG NOTE.
4-0 ~ 5c10
2-0
1-0
5d8 1 -7
| ABUT. BRG.
| PIER
2 -0
~ 6c4
5h1
5s1
6c3
3 EQ UA 4L 5e SP 1 AC & ES 45e 3
1 3 1 6
2@7
3 @ 6
5e3 1-11
1 6
1-11
3 1 8 1
2@7 ~ 6c4
5 SPA. @ 6
6 SPA. @ 5
| BEAM BEARING
SECTION B-B
NOTE: SEE SHEET H44-37-07 FOR EXPANSION PIER BEARING DETAILS
1" THICK STRIPS OF PREFORMED EXPANSION JOINT FILLER AROUND BEARINGS, FACE OF
2 -0
| BEAMS | PIER
2 8
6c4 BARS
PART PLAN
~ 5c5-10
APPROVED BY BRI DGE ENGI NEER
3-11
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 -6
5c5-1 0
2 -3 MI N.
~ NOTE: SEE END SECTION DETAILS IN THESE PLANS FOR DETAILS OF BARRIER RAIL END SECTION. 3" PVC PIPE REINFORCING BARS 6c3, 6c4, 5c5-10, 6d2 & 4t1
5s1 2 CL.
01 -1 2
1 -7
PART PLAN
LONGITUDINAL SECTION
30 SKEW C BEAMS
SECTION D-D
H44-21-07
12/28/2011
1:15:48 PM
tsorens
W:\Highway\Bridge\NewStandards\Jan_2012_Release\H44-07.dgn
h44-21-07
11x17_pdf.pltcfg
5 TYP.
1-11 1-11
ABUTMENT WING.
9 9
| - | ABUTMENT BRGS. | ABUT. BRG. - | PIER | PIER - | PIER "J" SPACES @ 10": 5j1 TOP SLAB 6 30 SPACES @ 10" 6a2 11 "X" "X" CONSTR. JOINT "X" "X" 10 "E" SPACES @ 10": 6a1 10 30 SPACES @ 10" 6a2 6 REINFORCING BARS | PIER - | ABUT. BRG.
TOP REINFORCING
b3 6a1
5j1
6a2 (1-11)
1 -7
6a2 (45-2)
5b2
5b1 6a1 PERMISSIBLE TRANSVERSE 6a1 CONSTRUCTION JOINT 1 6a3 (44-6) BOTTOM 6a3 (2-7) REINFORCING 4 2 5 3 6a3 (44-6) | ROADWAY
| ABUT. BRG. | ABUT. BRG. 11 29 SPACES @ 10" 6a3 10 | PIER "H" SPACES @ 10": 6a1 "S" OUT TO OUT OF SLAB | PIER
SLAB LAYOUT
REVI SED 1 0-1 1 - THE ESTI MATED QUANTI TI ES FOR THE STRUCTURAL STEEL WI TH DRAI NS WAS CHANGED. (LEFT AHEAD SKEW SHOWN, RIGHT AHEAD SKEW SIMILAR)
NOTE: CONCRETE DECK SLAB SHALL BE PLACED IN SECTIONS AND SEQUENCES INDICATED. ALTERNATE PROCEDURES FOR PLACING SLAB CONCRETE MAY BE SUBMITTED FOR APPROVAL TOGETHER WITH A STATEMENT OF THE PROPOSED METHOD AND EVIDENCE THAT THE CONTRACTOR POSSESSES THE NECESSARY EQUIPMENT AND FACILITIES TO ACCOMPLISH THE REQUIRED RESULTS.
ESTIMATED QUANTITIES
(SUPERSTRUCTURE PLUS INTEGRAL ABUTMENTS) STRUCTURAL CONCRETE SUPERSTRUCTURE (INCLUDES ABUTMENT WINGS)
151-4
163-10
176-4
188-10
201-4
213-10
226-4
243-0
GENERAL DATA
VERTICAL CURVE
151-4
163-10
176-4
1 -7
188-10
44 -0 ROADWAY
213-10
226-4
243-0
C.Y. C.Y. C.Y. C.Y. NO. NO. L.F. LB. LB. LB. LB. LB. LB. LB. LB. NO. NO. L.F. L.F.
247.1 249.6 43.1 44.8 7-A50 14-A42 312.6 5689 5009 6943 6263 67,844 68,509 67,393 68,058 30 16 300 160
262.3 265.0 42.9 44.8 7-A55 14-A46 337.6 5689 5009 6943 6263 71,967 72,588 72,022 72,643 32 16 320 160
289.3 292.3 42.8 44.8 7-B59 14-B50 362.6 5777 5009 7031 6263 76,807 77,575 76,753 77,521 34 16 340 160
304.5 307.7 42.7 44.8 7-B63 14-B55 387.6 5777 5009 7031 6263 82,123 83,067 81,962 82,906 36 16 360 160
364.4 368.1 ----52.6 7-C75 14-C67 481.7 5742 4894 7223 6375 ---------
380.3 384.2 ----52.6 7-C80 14-C71 506.7 5742 4894 7223 6375 ---------
401.3 405.5
TOP OF SLAB TO ABUT. CONSTR. JT. AT C.L. ABUT. BRG. TOP OF SLAB TO PIER TOP AT C.L. PIER* TOP OF SLAB TO ABUT. CONSTR. JT. AT C.L. ABUT. BRG. TOP OF SLAB TO PIER TOP AT C.L. PIER*
"U" "U" "U" "U" KIPS KIPS "E" "H" "J" "S" "X"
3-8 3-6 3-8 3-6 489.3 264.7 138 139 165 142-3 6-7
3-7 3-6 3-7 3-6 527.5 274.5 153 154 180 154-9 7-1
4-2 4-1 4-2 4-1 604.3 283.9 168 169 195 167-3 7-7
4-2 4-1 4-2 4-1 644.6 293.1 183 184 210 179-9 8-1
4-2 4-1 4-3 4-2 685.2 302.2 198 199 225 192-3 8-8
4-8 4-7 4-8 4-7 822.9 311.0 213 214 240 204-9 9-2
4-8 4-7 4-8 4-7 868.4 322.9 228 229 255 217-3 9-8
4-9 4-7 4-9 4-8 914.4 341.9 243 244 270 229-9 10-2
4-9 4-7 4-10 4-8 959.2 362.6 263 264 290 246-5 10-2
----52.6 7-C80 14-C80 D.L. PIER REACTION (D.L. + F.W.S.) 540.0 5742 4894 7223 NO. OF SPACES FOR 6a1 BARS (BOTTOM) 6375 --------NO. OF SPACES FOR 5j1 BARS (TOP) OUT TO OUT OF SLAB SLAB TRANSVERSE CONSTR. JT. DISTANCE FROM C.L. PIER L.L. PIER REACTION (HL93) NO IMPACT NO. OF SPACES FOR 6a1 BARS (TOP) STRAIGHT GRADE
PRETENSIONED PRESTRESSED CONCRETE BEAM, CENTER SPAN PRETENSIONED PRESTRESSED CONCRETE BEAM, END SPAN CONCRETE RAIL (BARRIER OR OPEN) STRUCTURAL STEEL (w/ PILE BENT PIERS & DRAINS) STRUCTURAL STEEL (w/ PILE BENT PIERS & NO DRAINS) STRUCTURAL STEEL (w/ TEE PIERS & DRAINS) STRUCTURAL STEEL (w/ TEE PIERS & NO DRAINS) EPOXY COATED REINF. STEEL (w/ WOOD PILES & BARRIER RAIL) EPOXY COATED REINF. STEEL (w/ WOOD PILES & OPEN RAIL) EPOXY COATED REINF. (w/ STEEL H PILES & BARRIER RAIL) EPOXY COATED REINF. (w/ STEEL H PILES & OPEN RAIL) NO. OF WOOD PILES, TREATED FOR TWO ABUTMENTS NO. OF STEEL H-PILES FOR TWO ABUTMENTS (HP 10 x 57) PREBORED HOLES (W/WOOD PILES) PREBORED HOLES (W/STEEL H-PILES)
14-B59 14-C63 412.6 5777 5009 7031 6263 86,642 87,516 86,481 87,355 36 16 360 160 456.7 5742 4894 7223 6375 --------94,534 96,378 ----22 ----220
100,147 104,673 110,469 101,900 106,623 112,465 ----22 ----220 ----22 ----220 ----24 ----240
138-10
151-4
163-10
176-4
188-10
201-4
213-10
226-4
243-0
VALUES SHOWN ARE FOR FIXED PIERS ONLY AND ALLOW FOR INCH DEFLECTION OF THE 1 INCH NEOPRENE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
BEARING PAD. AT EXPANSION PIER LOCATIONS ADD 3 INCHES TO "U" VALUES SHOWN. 1 0-1 1
LATEST REVI SI ON DATE
*** SEE SHEET H44-24-07 FOR ADDITIONAL CONCRETE REQUIRED IN ABUTMENT FOOTINGS.
SUPERSTRUCTURE DETAILS
30 SKEW
H44-22-07
9/29/2011
2:43:42 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-22-07
11x17_pdf.pltcfg
C BEAM LENGTH 46-10 VARIES VARIES WEIGHT 30,177 2,192 2,122 NO. 459 62 60
C BEAM LENGTH 46-10 VARIES VARIES WEIGHT 32,288 2,192 2,122 NO. 489 62 60
C BEAM LENGTH 46-10 VARIES VARIES WEIGHT 34,398 2,192 2,122 NO. 529 62 60
62 VARIES 60 VARIES
62 VARIES 60 VARIES
62 VARIES 60 VARIES
62 VARIES 60 VARIES
62 VARIES 60 VARIES
SLAB LONGITUDINAL, TOP & BOTT. SLAB LONGITUDINAL, TOP & BOTT., ENDS SLAB LONGITUDINAL, TOP @ PIERS SLAB LONGITUDINAL, TOP @ PIERS SLAB LONGITUDINAL, TOP @ PIERS
212 212 98
318 212 98
318 212 98
318 212
40-0 33-9
13,267 7,463
318 212
40-0 40-0
13,267 8,845
424 212
40-0 27-3
17,689 6,025
424 212
40-0 33-6
17,689 7,407
424 212
40-0 39-9
17,689 8,789
530 212
40-0 29-1
22,112 6,431
98
15-10
3,172
98
17-0
3,405
98
18-0
PIER DIAPH. ENDS PIER & ABUT. DIAPH. LONGIT. PIER & ABUT. DIAPH. LONGIT. PIER DIAPH. LONGIT. ABUT. DIAPH. ENDS ABUT. DIAPH. LONGIT. B.F. PAVING NOTCH LONGIT. ABUT. DIAPH. WING EXT. LONGIT. ABUT. DIAPH. WING EXT. LONGIT. PIER DIAPH. HOOPS PIER DIAPH. TIES ENDS PIER DIAPH. TIES PIER DIAPH. HOOPS ENDS
12 108 36 12 12 16 8
12 108 36 12 12 16 8
12 108 36 12 12 16 8
12 108 36 12 12 16 8
12 108 36 12 12 16 8
12 108 36 12 12 16 8 24 24
3-9 6-9 5-9 10-0 5-5 27-11 27-9 11-0 10-11 11-4 2-7 3-5 10-6
12 108 36 12 12 16 8 24 24 48 4 48 4
3-9 6-9 5-9 10-0 5-5 27-11 27-9 11-0 10-11 11-4 2-7 3-5 10-6
12 108 36 12 12 16 8 24 24 48 4 48 4
3-9 6-9 5-9 10-0 5-5 27-11 27-9 11-0 10-11 11-4 2-7 3-5 10-6
12 108 36 12 12 16 8 24 24 48 4 48 4
3-9 6-9 5-9 10-0 5-5 27-11 27-9 11-0 10-11 11-4 2-7 3-5 10-6
48 4 48 4
455 11 171 34
48 4 48 4
455 11 171 34
48 4 48 4
517 11 171 40
48 4 48 4
517 11 171 40
48 4 48 4
517 11 171 40
48 4 48 4
ABUT. FOOTING LONGIT. ABUT. EXTENSION LONGIT. ABUT. EXTENSION LONGIT. ABUT. EXTENSION LONGIT.
36
29-3
2,812
36
29-3
2,812
36
29-3
2,812
36
29-3
2,812
36
29-3
2,812
36 16 8 8
36 16 8 8
36 16 8 8
36 16 8 8
ABUT. VERT. ABUT. DIAPH. VERT. B.F. ABUT. DIAPH. WING EXT. VERT.
158 74
6-8 15-3
2,812 3,013
158 74
6-8 15-3
2,812 3,013
158 74
7-3 15-3
3,058 3,013
158 74
7-3 15-3
3,058 3,013
158 74
7-3 15-3
3,058 3,013
154 74 40
154 74 40
154 74 40
154 74 40
ABUT. WING HORIZ. B.F. ABUT. TO WING ANCHOR ABUT. WING HORIZ. TRAFFIC FACE ABUT. TO WING ANCHOR TOP OF SLAB TRANSV. (AT RAIL) PAVING NOTCH PAVING NOTCH
28 56 28
28 56 28
28 56 28
28 56 28
28 56 28
36 12 36 12
36 12 36 12 512 76 76
36 12 36 12 542 76 76
36 12 36 12 582 76 76
332 76 76
362 76 76
392 76 76
422 76 76
452 76 76
482 76 76
ABUTMENT HOOPS (WOOD/STEEL) ABUTMENT HOOPS ABUT. BOTT. AT PILES ABUT. HOOPS AT ENDS
168/140 8
10-6 11-5
1840/1533 120/140 95 8
10-6 11-5
1314/1533 128/140 95 8
10-6 11-5
1489/1533 95
168 24 36 8
168 24 36 8
168 24 36 8
152 24 40 8
5s1
WING VERT.
64
5-10
389
64
5-10
389
64
6-2
412
64
6-2
412
64
6-2
412
64
6-11
462
64
6-11
462
64
6-11
462
64
6-11
462
4t1
14
4-9
44
14
4-9
44
14
4-9
44
14
4-9
44
14
4-9
44
14
5-0
47
14
5-0
47
14
5-0
47
14
5-0
47
#2
PILE SPIRAL (WOOD/STEEL)* SPIRAL SPACERS, L 7/8 x 7/8 x 1/8 x 0.70 (WOOD/STL.)* *EPOXY COATING NOT REQUIRED SUB TOTAL W/ WOOD PILES** SUB TOTAL W/ STEEL H-PILES** **RAIL REINFORCING NOT INCLUDED
30/16 90/48
38-6 1-10
193/103 116/62
32/16 96/48
38-6 1-10
206/103 123/62
34/16 102/48
38-6 1-10
219/103 131/62
36/16 108/48
38-6 1-10
231/103 139/62
36/16 108/48
38-6 1-10
231/103 139/62
22 66
38-6 1-10
141 85
22 66
38-6 1-10
141 85
22 66
38-6 1-10
141 85
24 72
38-6 1-10
154 92
59,629 59,178
63,179 63,234
67,460 67,406
72,244 72,083
8,788 9,409 6 6 8
1 5
9,347 10,115
9,879 10,823
10,478 11,352
11,445 13,289
12,003 13,756
12,576 14,526
13,312 15,308
3 0
5d1
D=2 1-11
A , B
5d6
1 -0 D=2
2 -7
2 -7
1 1
1 4
6 THUS 5
5h4
D=3 A,B
3-9
6p3
4 1
4t1
1 1
0 3
3 -6
2 -1 0
4 -0
1 5
D=2
2 -1 1
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 6
D=2 1-6
6 THUS
1 1
D=2
2-9
2-1
1-2 D=2
26-6 6-8
5k1
3-10
5d5
2-4 1-6 1
10
2-0
2-4
2 -6
8f3, 8f4,
D=6
6
3 1 0
2 -2
5e2, 5e3
12-0
8f5
3 -1 1 D=2 7-10 5-3 1-10
8f1
1-3 C BM.
2 1 0
D=3
5k2
5 1
2 -2
5p2
D=2
1 0
D=3
5h3
5p1 5p4
D=2
5p1, 5p4
2-7 3-0 A, B BMS.3-0 C BM. 2-8
4-11
1-10
8g3
8f5
6-6
H44-23-07
5d4
9/29/2011
2:43:44 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-23-07
11x17_pdf.pltcfg
| BEAMS @ | PIER LOW STEP 3 SPA. @ 10 (TYP.) a BARS 5n1 5m1 6-8 20 5
139
30
209
33
229
37
257
49
341
5m1
20 -----
5 -----
56 ----195
20 4 ----
5 8 ----
56 133 ---398
16 -4 ---
5 -8 ---
45 -217 --491
8 --4 --
5 --8 --
22 --342 -621
20 ---4
5 ---8
56 ---426 823
* 8n5
G = GRADE (%) | BEAMS @ | PIER 5 3 SPA. LOW STEP 3 SPA. @ 10 (TYP.) a BARS @ 1-3 8n2 10 10 5 3 SPA. @ 1-3 5 TYP. 10 TYP. * 8n4 BARS VARY FROM 31-3 TO 32-10 8n5 BARS VARY FROM 39-2 TO 40-8
5n1
5m1 5m1 5m1 5n1 8n2 8n3 * 8n4 * 8n5 | BEAMS @ | PIER 5 3 SPA. LOW STEP 3 SPA. @ 10 (TYP.) a BARS @ 1-3 8n3 10 10 5 4 EQ. SPA. 5 10 10 5 3 SPA. @ 1-3 5 TYP. 10 TYP.
TOTAL (LB.)
6-7
20
137
30
206
33
227
37
254
49
336
20 -----
5 -----
56 ----193
20 4 ----
5 8 ----
56 133 ---395
16 -4 ---
5 -8 ---
45 -217 --489
8 --4 --
5 --8 --
22 --342 -618
20 ---4
5 ---8
56 ---426 818
G = GRADE (%) * 8n4 BARS VARY FROM 31-3 TO 32-10 8n5 BARS VARY FROM 39-2 TO 40-8
5n1
5m1 1 -1 0 5m1
2-11
D=2
5m1
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D = PIN DIAMETER.
| BEAMS @ | PIER 5 3 SPA. @ 10 (TYP.) LOW STEP a BARS 5 TYP. 5n1 3 SPA. @ 1-3 8n4 10 10 5 4 EQ. SPA. 5 10 10 5 4 EQ. SPA. 5 10 10 5 4 EQ. SPA. 5 10 10 6 5
NOTES:
THE TABLE BELOW LISTS THE ADDITIONAL CONCRETE VOLUME REQUIRED IN EACH ABUTMENT FOOTING/PIER CAP BASED ON THE ROADWAY GRADE AT EACH ABUTMENT FOOTING/PIER CAP. ADDITIONAL CONCRETE SHOULD BE ADDED TO THE PLANS FOR EACH ABUTMENT FOOTING/PIER CAP THAT HAS 0.5 CU. YDS. OR MORE OF ADDITIONAL CONCRETE. VALUES SHOULD BE EXCLUDED FOR SCENARIOS THAT HAVE LESS THAN 0.5 CU. YDS. OF ADDITIONAL CONCRETE PER SUBSTRUCTURE UNIT. VALUES MAY BE INTERPOLATED FOR GRADES BETWEEN THE VALUES SHOWN IN THE TABLE.
5m1 5m1
3 EQ. SPA.
5m1
0.5 0.6
1.2 1.4
1.9 2.3
2.7 3.1
3.4 4.0
3 SPA. @ 10 3 SPA. @ 10
TYPICAL SECTION
5n1 5n1 5n1
EACH TEE PIER CAP - ALL BEAMS EACH PILE BENT PIER - ALL BEAMS
0.5 0.5
1.3 1.3
2.1 2.0
2.9 2.8
3.7 3.6
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
6
LATEST REVI SI ON DATE
ADDITIONAL QUANTITIES
30 SKEW
H44-24-07
9/29/2011
2:43:45 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-24-07
11x17_pdf.pltcfg
A BEAM DATA
OVERALL BEAM TOTAL I NI TI AL 2 TOP DEFLECTED OR STRAIGHT STRANDS BEARI NG SPAN LENGTH LENGTH ( L) ARE TO BE CUT WITH 1-0 PROJECTIONS AND SHOP BENT UP OR DOWN AS SHOWN BEAM (BEND TOP AND BOTTOM ROWS). THE REMAINING TOP STRANDS ARE TO BE CUT WITH 0-3 PROJECTIONS. FOUR BOTTOM STRANDS ARE TO BE CUT STRAND SI ZE
NO. OF STRANDS
DEFLECTED
PRESTRESS
FORCE-KI PS
CAMBER (in.)
HOLD DOWN
DEFLECTION (in.) ~
D
PERMISSIBLE SPACING
STRAI GHT
KI PS
AT RELEASE
AFTER LOSSES
IMMEDIATE 1 (ELASTIC) ~
TIME (PLASTIC) ~
2
T
HL93 LOADING CONC. STEEL DIAPH. DIAPH. 7-6 7-6 7-6 7-6 7-6 7-6 7-6 7-6 7.1 7.7 8.4 9.1
| -|
CONC. STEEL
CONC. STEEL
4a2
4b2
WITH 1-0 PROJECTIONS AND SHOP BENT AS SHOWN. THE REMAINING BOTTOM A42 *A46 42-6 43-6 46-8 47-8 50-10 51-10 55-0 56-0 0.6" 0.6" 0.6" 0.6"
DIAPH.DIAPH. DIAPH. DIAPH. 383 426 510.9 553.4 9.3 8.5 11.7 10.8 0.70 0.76 1.02 1.29 1.24 1.35 1.82 2.30 0.38 0.50 0.69 0.94 0.35 0.47 0.65 0.88 0.09 0.13 0.17 0.23 0.09 0.12 0.16 0.22
7 8 9 10
2 2 3 3
( C.Y. )
(TONS)
CONCRETE
WEIGHT
A
4
*A50 *A55
4 2 -3 2 4 4 4 2
NOTES:
THESE BEAMS ARE DESIGNED FOR AASHTO LIVE LOADS AS INDICATED IN ABOVE TABLE WITH AN ALLOWANCE OF 20 lb. PER SQUARE FOOT OF ROADWAY FOR FUTURE WEARING SURFACE. HOLD DOWN POINTS FOR DEFLECTED STRANDS MAY BE MOVED TOWARD ENDS OF BEAM A DISTANCE OF 0.05 L MAXIMUM
THE DEFLECTIONS SHOWN ARE FOR A SLAB WEIGHT OF 757 #/FT. (8" SLAB AND 7-6 BEAM SPACING) AND ONE CONCRETE DIAPHRAGM (1912 #) OR ONE STEEL DIAPHRAGM (285 #) AT | OF SPAN. FOR DIFFERENT SLAB AND DIAPHRAGM WEIGHTS, DEFLECTIONS WILL BE DIRECTLY PROPORTIONAL.
2
AT PRODUCERS OPTION. ALL PRESTRESSING STRANDS SHALL CONFORM TO ASTM A416 GRADE 270 LOW RELAXATION STRANDS.
WEIGHT OF SLAB AND SHRINKAGE OF SLAB. TOTAL BEAM DEFLECTIONS AT | OF SPAN, ~ D , DUE TO
A55 ONLY)
TOPS OF BEAMS ARE TO BE STRUCK OFF LEVEL AND FINSHED AS PER MATERIALS IM570.
BEARINGS SHALL BE AS DETAILED ON OTHER DESIGN SHEETS. BEAMS TO BE USED IN BRIDGES MADE CONTINUOUS BY THE POURED IN PLACE FLOOR, ARE TO BE AT LEAST 28 DAYS OLD BEFORE THE FLOOR IS PLACED UNLESS A SHORTER CURING TIME IS APPROVED BY THE BRIDGE ENGINEER. THE PORTIONS OF THE PRESTRESS BEAMS THAT ARE TO BE EMBEDDED IN THE ABUTMENT AND PIER DIAPHRAGMS SHALL BE ROUGHENED FOR A DISTANCE OF 10" FROM THE BEAM END BY
3d
WEIGHT OF SLAB AND DIAPHRAGMS FOR DETAILING PURPOSE: (A) ~ D = ~ +~ FOR SIMPLE SPAN. T (B) ~ D = ~ +~ FOR T END SPANS OF CONTINUOUS BRIDGE. (C)
2" cl .
~ D
4b1 4b2
TOTAL INITIAL PRESTRESS IS BASED ON 72.6% fs, fs = 270 ksi AND As = 0.217 sq. in.
*
" COIL TIES (MINIMUM 9000 LBS. PULL OUT CAPACITY)
SANDBLASTING OR OTHER APPROVED METHODS TO PROVIDE SUITABLE BOND BETWEEN THE BEAM AND THE DIAPHRAGM IN ACCORDANCE WITH ARTICLE 2403.03, I, OF THE STANDARD
SPECIFICATIONS:
1-4
CONSTRUCTION: STANDARD SPECIFICATIONS OF THE IOWA DEPARTMENT OF TRANSPORTATION, CURRENT SERIES, WITH CURRENT APPLICABLE SPECIAL PROVISIONS AND SUPPLEMENTAL SPECIFICATIONS. DESIGN: A.A.S.H.T.O. LRFD, SERIES OF 2007, WITH MINOR MODIFICATIONS.
FOR ELASTIC SHORTENING, CREEP AND SHRINKAGE. IF THE STEEL DIAPHRAGM OPTION IS ALLOWED AND USED, HOLES MUST BE CAST IN THE WEB TO ACCOMMODATE THE STEEL DIAPHRAGM ATTACHMENTS AS DETAILED ON THE STEEL DIAPHRAGM DETAIL SHEET. IF SOLE PLATE IS REQUIRED FOR BEARING, SOLE PLATE IS TO
DESIGN STRESSES:
DESIGN STRESSES FOR THE FOLLOWING MATERIALS ARE TO BE IN ACCORDANCE WITH A.A.S.H.T.O. LRFD SPECIFICATIONS FOR HIGHWAY BRIDGES, SERIES OF 2007: REINFORCING STEEL IN ACCORDANCE WITH SECTION 5, GRADE 60. fc = 5000 psi CONCRETE IN ACCORDANCE WITH SECTION 5, (EXCEPT AS NOTED) PRESTRESSING STEEL IN ACCORDANCE WITH SECTION 5, fs = 270,000 psi.
BE SET IN FORMS WHEN BEAM IS CAST AND FORMED OUT BELOW TO EXCLUDE CONCRETE AS DETAILED ON THE BEARING SHEET. 0.6" DIAMETER STRANDS STRESSED TO NOT MORE THAN 5,000 LBS. EACH MAY BE USED IN LIEU OF THE a BARS WHICH RUN THE FULL LENGTH OF THE BEAM IN THE TOP FLANGE.
REVI SED 1 1 -09 - THE SPECI FI CATI ON REFERENCES WERE CHANGED. THE BEAM
D=2
NO. LENGTH NO. LENGTH NO. LENGTH NO. LENGTH 4 2 40 12 22-10 3-3 6-8 5-0 4 2 44 12 24-11 3-3 6-8 5-0 4 2 46 8 8 46 108 27-0 3-3 6-8 5-0 2-9 1-3 2-8 4 2 50 8 12 50 116 29-1
1 1
D=1 1-1
APPROVED BY BRI DGE ENGI NEER
3-3 4b2 6-8 5-0 2-9 1-3 D=1 2-8 10 3c1 2-6 4b5 2 3e 6 1-1
LATEST REVI SI ON DATE
D=2
2 -5
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
~~4b1
3d
1 1 -09
A BEAM DETAILS
H44-25-07
9/29/2011
2:43:46 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-25-07
11x17_pdf.pltcfg
STEEL-( l b)
REI NFORCI NG
-9 1 R=
| BRG. 4b1, 3c1, 3d 1* 4@9=3-0 11 3@1-0 4 @ 1-2 = 4-8 7 @ 1-4 = 9-4 8 ~ ~ * | 2 3 4 4a2
BAR 4a2
3 1 -4
A42
4 6 1 3@3 6 @ 4 3e 37 3 @ 9 4b2, 3d 2 5 4-3
3d
3e
22
22 4
2 1-5
BEAM A42
| BRG. ~ ~ * 2 3 4 4b1, 3c1, 3d 1* 5@9=3-9 2@10 1-1 5 @ 1-2 = 5-10 8 @ 1-4 = 10-8 8 | 4a2
BAR 4a2
2 DEFLECTED
2
2 BARS 5a1
STRANDS
A46
4 6 1 3@3 6 @ 4 3e 37 3 @ 9 4b2, 3d 2 2 4 4-8
3d
3e
BEAM A46
~~4b1 | BRG. ~~ ~ * DEFLECTED 2 2 3 4 4b1, 3c1, 3d 1* 5@9=3-9 BAR 4a2 2@1-1 5 @ 1-2 = 5-10 1-3 9 @ 1-4 = 12-0 2 BARS 5a1 8 | 4a2 4b2 3c1 2 2 STRANDS 5a1 STRAI GHT 22 2 6@2 2 STRANDS 4b5 3d 3e
4b5 @ 4
DETAI LS.
A50
6 6 1 8@4=3-0 3e 3 @ 9 4b2, 3d 2 7 5-1
22
BEAM A50
~~4b1 | BRG. ~~ ~ * 22 3 4 4b1, 3c1, 3d 1* 5@9=3-9 BAR 4a2 1-0 2@1-1 1-1 5 @ 1-2 = 5-10 10 @ 1-4 = 13-4 2 BARS 5a1 8 | 4a2 4b2 3c1 2
NOTE: BARS 3d ARE TO BE PLACED IN PAIRS.
DEFLECTED
4b5 @ 4
2@2
A55
6 6 1 8@4=3-0 3e 3 @ 9 4b2, 3d 4 6 5-6
3d
3e
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
22
222
1 1 -09
2 SYMMETRICAL ABOUT |
6@2
BEAM A55
NOTE: DIMENSIONS FOR THE LOCATION OF THE DEFLECTED STRANDS ARE AT | BEAM AND END OF BEAM.
A BEAM DETAILS
H44-26-07
9/29/2011
2:43:48 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-26-07
11x17_pdf.pltcfg
2 TOP DEFLECTED OR STRAIGHT STRANDS OVERALL BEAM DI A.( i nches) BEARI NG ARE TO BE CUT WITH 1-0 PROJECTIONS SPAN LENGTH AND SHOP BENT UP OR DOWN AS SHOWN (BEND TOP AND BOTTOM ROWS). THE REMAINING TOP STRANDS ARE TO BE CUT WITH 0-3 PROJECTIONS. FOUR BOTTOM STRANDS ARE TO BE CUT BEAM TOTAL I NI TI AL STRAND SI ZE
NO. OF STRANDS
B BEAM DATA
LENGTH ( L) PRESTRESS FORCE-KI PS CAMBER (in.) HOLD DOWN DEFLECTION (in.) ~
D
PERMISSIBLE SPACING
STRAI GHT
DEFLECTED
KI PS
AT RELEASE
AFTER LOSSES
IMMEDIATE 1 (ELASTIC) ~
TIME (PLASTIC) ~
2
T
HL93 LOADING CONC. STEEL DIAPH. DIAPH. 7-6 7-6 7-6 7-6 7-6 7-6 7-6 7-6 7-6 7-6 10.3 11.2 12.0 12.8 13.6
| -|
CONC. STEEL
CONC. STEEL
4a2
4b2
WITH 1-0 PROJECTIONS AND SHOP BENT AS SHOWN. THE REMAINING BOTTOM B50
DIAPH.DIAPH. DIAPH. DIAPH. 425 468 554 639 724 10.8 14.1 13.2 12.3 11.6 0.67 0.85 1.12 1.30 1.69 1.24 1.51 1.99 2.32 2.98 0.43 0.58 0.82 0.91 1.16 0.39 0.54 0.77 0.84 1.09 0.11 0.14 0.21 0.23 0.29 0.10 0.13 0.19 0.21 0.27
50-10 51-10 0.60 55-0 56-0 0.60 59-2 60-2 0.60 63-4 64-4 0.60 67-6 68-6 0.60
8 8 10 12 14
2 3 3 3 3
( C.Y. )
(TONS)
CONCRETE
WEIGHT
*B67
4 2 -1 0 2 4 4 4 2
6 3
DEFLECTIONS AT MID-SPAN DUE TO WEIGHT OF SLAB AND DIAPHRAGM. THE DEFLECTIONS SHOWN ARE FOR A SLAB WEIGHT OF 757 #/FT. (8" SLAB AND 7-6 BEAM SPACING) AND ONE CONCRETE DIAPHRAGM (2270 #) OR ONE
NOTES:
THESE BEAMS ARE DESIGNED FOR AASHTO LIVE LOADS AS INDICATED IN ABOVE TABLE WITH AN ALLOWANCE OF 20 lb. PER SQUARE FOOT OF ROADWAY FOR FUTURE WEARING SURFACE. HOLD DOWN POINTS FOR DEFLECTED STRANDS MAY BE MOVED TOWARD ENDS OF BEAM A DISTANCE OF 0.05 L MAXIMUM AT PRODUCERS OPTION. ALL PRESTRESSING STRANDS SHALL CONFORM TO ASTM A416 GRADE 270 LOW RELAXATION STRANDS.
STEEL DIAPHRAGM (285 #) AT | OF SPAN. FOR DIFFERENT SLAB AND DIAPHRAGM WEIGHTS, DEFLECTIONS WILL BE DIRECTLY PROPORTIONAL.
2
WEIGHT OF SLAB AND SHRINKAGE OF SLAB. TOTAL BEAM DEFLECTIONS AT | OF SPAN, ~ D , DUE TO WEIGHT OF SLAB AND DIAPHRAGMS FOR DETAILING PURPOSE:
2" cl . 4b1 4b2 6
TOPS OF BEAMS ARE TO BE STRUCK OFF LEVEL AND FINSHED AS PER MATERIALS IM570.
BEARINGS SHALL BE AS DETAILED ON OTHER DESIGN SHEETS. BEAMS TO BE USED IN BRIDGES MADE CONTINUOUS BY THE POURED IN PLACE FLOOR, ARE TO BE AT LEAST 28 DAYS OLD
(A) ~ D = ~ +~ FOR SIMPLE SPAN. T (B) ~ D = ~ +~ FOR T END SPANS OF CONTINUOUS BRIDGE. (C) ~ = ~ + ~ TFOR INTERIOR SPANS OF CONTINUOUS BRIDGE. D
IS BASED ON 72.6% fs, TOTAL INITIAL PRESTRESS AND As = 0.217 sq. in.
BEFORE THE FLOOR IS PLACED UNLESS A SHORTER CURING TIME IS APPROVED BY THE BRIDGE ENGINEER. THE PORTIONS OF THE PRESTRESS BEAMS THAT ARE TO BE
fs = 270 ksi
* 1-4
EMBEDDED IN THE ABUTMENT AND PIER DIAPHRAGMS SHALL BE ROUGHENED FOR A DISTANCE OF 10" FROM THE BEAM END BY SANDBLASTING OR OTHER APPROVED METHODS TO PROVIDE
SPECIFICATIONS:
CONSTRUCTION: STANDARD SPECIFICATIONS OF THE IOWA DEPARTMENT OF TRANSPORTATION, CURRENT SERIES, WITH CURRENT APPLICABLE SPECIAL PROVISIONS AND SUPPLEMENTAL SPECIFICATIONS. DESIGN: A.A.S.H.T.O. LRFD, SERIES OF 2007, WITH MINOR MODIFICATIONS.
SUITABLE BOND BETWEEN THE BEAM AND THE DIAPHRAGM IN ACCORDANCE WITH ARTICLE 2403.03, I, OF THE STANDARD SPECIFICATIONS. ALL BEAMS ARE TO BE INCREASED IN LENGTH TO COMPENSATE FOR ELASTIC SHORTENING, CREEP AND SHRINKAGE. IF THE STEEL DIAPHRAGM OPTION IS ALLOWED AND USED, HOLES MUST BE CAST IN THE WEB TO ACCOMMODATE THE STEEL DIAPHRAGM ATTACHMENTS AS DETAILED ON THE STEEL DIAPHRAGM DETAIL SHEET.
DESIGN STRESSES:
DESIGN STRESSES FOR THE FOLLOWING MATERIALS ARE TO BE IN ACCORDANCE WITH A.A.S.H.T.O. LRFD SPECIFICATIONS FOR HIGHWAY BRIDGES, SERIES OF 2007: ~~4b1 BARS TO BE EPOXY COATED. ** WHERE DEFLECTING STRANDS INTERFERE WITH PLACEMENT, SOME IN-PLACE BENDING MAY BE NECESSARY. PRESTRESSING STEEL IN ACCORDANCE WITH SECTION 5, fs = 270,000 psi. 3 REINFORCING STEEL IN ACCORDANCE WITH SECTION 5, GRADE 60. CONCRETE IN ACCORDANCE WITH SECTION 5, fc = 5000 psi (EXCEPT AS NOTED)
IF SOLE PLATE IS REQUIRED FOR BEARING, SOLE PLATE IS TO BE SET IN FORMS WHEN BEAM IS CAST AND FORMED OUT BELOW TO EXCLUDE CONCRETE AS DETAILED ON THE BEARING SHEET. 0.6" DIAMETER STRANDS STRESSED TO NOT MORE THAN 5,000 LBS. EACH MAY BE USED IN LIEU OF THE a BARS WHICH RUN THE FULL LENGTH OF THE BEAM IN THE TOP FLANGE.
REVI SED 1 1 -09 - THE SPECI FI CATI ON REFERENCES WERE CHANGED. THE BEAM
D=2
NO. LENGTH NO. LENGTH NO. LENGTH NO. LENGTH NO. LENGTH 4 2 44 12 27-3 4-2 7-10 6-2 4 2 46 12 29-4 4-2 7-10 6-2 4 2 50 12 31-5 4-2 7-10 6-2 4 2 52 12 12 52 128 24 33-6 4-2 7-10 6-2 3-3 1-5 2-10 1-8 4 2 56 12 12 56 136 24 35-7
1 1
4-2 7-10 6-2 6 3-3 1-5 D=1 2-10 10 1-8 3-1 ALL DIMENSIONS ARE OUT TO OUT. RADIUS TO | BAR. D = PIN DIAMETER. 4b5 3c1 3 1-1 3e 1 1 -09
LATEST REVI SI ON DATE
D=2
3 -0
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
~~4b1
3d
B BEAM DETAILS
H44-27-07
9/29/2011
2:43:49 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-27-07
11x17_pdf.pltcfg
STEEL-( l b)
REI NFORCI NG
-7 2 R=
| BRG. 4b1, 3c1, 3d 1* 4@9=3-0 11 4@1-1=4-4 7 @ 1-3 = 8-9 5 @ 1-7 = 7-11 9 | 24 * 4a2 ~ ~ 2 3
~~4b1 4b2
BAR 4a2
1-1
DEFLECTED STRANDS
6a1
1 "
2 BARS 6a1
3c1
B50
STRAI GHT
3 -3
4 6 1
37
2 @ 9
10
4b2, 3d
3d
3e
STRANDS
1 -8
222
22
| BRG. 4b1, 3c1, 3d 1* 4@9=3-0 4 @ 1-1 = 4-4 1-1 6 @ 1-3 = 7-6 7 @ 1-7 = 11-1 9 | 2 4 2 2 4 2
BAR 4a2
3c1 6a1
1-5
BEAM B50
2@2
2 BARS 6a1
"B" BEAM
STRAI GHT STRANDS
B55
CROSS SECTION
A = 382.5 in. 17.06 in. 62,000 in. Y b = =
3d
3e
4 6 1
37
2 @ 9
11
4b2, 3d
3@3
6 @ 4
2@6
3e
6@2
| BRG. 4b1, 3c1, 3d 1* 5@9=3-9 10 4 @ 1-1 = 4-4 6 @ 1-3 = 7-6 8 @ 1-7 = 12-8 9
2 2 2 2 DEFLECTED STRANDS |
3c1 6a1
BEAM B55
BAR 4a2
2@2
3d
3e
B59
STRANDS
GHT 2 2 2 STRAI
2 BARS 6a1
2 4
~~4b1 4b2
4 6 1
37
3 @ 9
4b2, 3d
5-11
59-2 |-| BEARINGS SYMMETRICAL ABOUT | 3@3 8@4=3-0 3e 2 6@2 2 60-2 END TO END OF BEAM
DETAI LS.
2 | BRG. 4b1, 3c1, 3d 1* 5 @ 9 = 3-9 4 @ 1-1 = 4-4 6 @ 1-3 = 7-6 1-4 9 @ 1-7 = 14-3 9 |
3c1 6a1
BEAM B59
BAR 4a2
2 2 2 DEFLECTED STRANDS
3d
3e
3d
3e
4b5 @ 4
2@2
2 BARS 6a1 1
NOTE: BARS 3d ARE TO BE PLACED IN PAIRS.
B63
DEFLECTED STRANDS
4 6 1 3@3 8@4=3-0 3e 37 3 @ 9 4b2, 3d 2 4 6 6-4
6@2
6@2
KEEP
BEAM B63
BEAM B67
| BRG. 4b1, 3c1, 3d 1* 5 @ 9 = 3-9 5 @ 1-0 = 5-0 1-2 6 @ 1-3 = 7-6 10 @ 1-7 = 15-10 9
BAR 4a2 |
APPROVED BY BRI DGE ENGI NEER
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
4b5 @ 4
2@2
2 BARS 6a1
LATEST REVI SI ON DATE
1 1 -09
B67
4 6 1
37
3 @ 9
6-9
SYMMETRICAL ABOUT | 3@3 8@4=3-0 3e 68-6 END TO END OF BEAM NOTE: DIMENSIONS FOR THE LOCATION OF THE DEFLECTED STRANDS ARE AT | BEAM AND END OF BEAM.
B BEAM DETAILS
H44-28-07
9/29/2011
2:43:50 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-28-07
11x17_pdf.pltcfg
C BEAM DATA
OVERALL BEAM TOTAL I NI TI AL THE TOP STRAIGHT STRANDS OF BEAMS DI A.( i nches) SPAN LENGTH BEARI NG LENGTH ( L) C63 AND C67 ARE TO BE CUT WITH 1-0 PROJECTIONS AND SHOP BENT BEAM UP. THE TOP AND BOTTOM DEFLECTED STRANDS OF BEAMS C71 THROUGH C80 ARE TO BE CUT WITH 1-0 PROJECTIONS AND SHOP BENT UP OR STRAND SI ZE
NO. OF STRANDS
REI NFORCI NG
PRESTRESS
FORCE-KI PS
CAMBER (in.)
HOLD DOWN
DEFLECTION (in.) ~
D
PERMISSIBLE SPACING
CONCRETE
WEIGHT (TONS)
STRAI GHT
DEFLECTED
KI PS
AT RELEASE
AFTER LOSSES
IMMEDIATE 1 (ELASTIC) ~
TIME (PLASTIC) ~
2
T
HL93 LOADING CONC. STEEL DIAPH. DIAPH. 7-6 7-6 7-6 7-6 7-6 7-6 7-6 7-6 7-6 7-6 18.9 20.1 21.4 22.6 23.8
| -|
CONC. STEEL
CONC. STEEL
4a2
4b2
DOWN AS SHOWN. THE REMAINING TOP STRANDS ARE TO BE CUT WITH 0-3 C63 63-4 64-4 67-6 68-6 71-8 72-8 0.60 0.60 0.60
DIAPH.DIAPH. DIAPH. DIAPH. 681 766 0.70 0.92 16 22 21 1.21 1.33 1.64 1.24 1.62 2.13 2.34 2.90 0.59 0.76 0.88 1.07 1.31 0.54 0.71 0.82 0.99 1.24 0.15 0.19 0.22 0.27 0.33 0.14 0.18 0.20 0.25 0.31
16 18 14 14 16 4 6 6
1-4
1-6
FOUR BOTTOM STRANDS ARE TO BE CUT WITH 1-0 PROJECTIONS AND SHOP BENT AS SHOWN. THE REMAINING BOTTOM STRANDS SHALL BE CUT OFF REASONABLY FLUSH WITH THE CONCRETE.
3 3 -4 4 6 4 3
4
1
DEFLECTIONS AT MID-SPAN DUE TO WEIGHT OF SLAB AND DIAPHRAGM. THE DEFLECTIONS SHOWN ARE FOR A SLAB WEIGHT OF 757 #/FT. (8" SLAB AND 7-6 BEAM SPACING) AND ONE CONCRETE DIAPHRAGM (2635 #) OR ONE STEEL DIAPHRAGM (285 #) AT | OF SPAN. FOR DIFFERENT SLAB AND DIAPHRAGM WEIGHTS, DEFLECTIONS WILL BE DIRECTLY PROPORTIONAL.
2
NOTES:
THESE BEAMS ARE DESIGNED FOR AASHTO LIVE LOADS AS INDICATED IN ABOVE TABLE WITH AN ALLOWANCE OF 20 lb. PER SQUARE FOOT OF ROADWAY FOR FUTURE WEARING SURFACE. HOLD DOWN POINTS FOR DEFLECTED STRANDS MAY BE MOVED TOWARD ENDS OF BEAM A DISTANCE OF 0.05 L MAXIMUM AT PRODUCERS OPTION. ALL PRESTRESSING STRANDS SHALL CONFORM TO ASTM A416 GRADE 270 LOW RELAXATION STRANDS.
6 3
WEIGHT OF SLAB AND SHRINKAGE OF SLAB. TOTAL BEAM DEFLECTIONS AT | OF SPAN, ~ D , DUE TO WEIGHT OF SLAB AND DIAPHRAGMS FOR DETAILING PURPOSE: (A) ~ D = ~ +~ FOR SIMPLE SPAN. T
3d
DETAI LS.
TOPS OF BEAMS ARE TO BE STRUCK OFF LEVEL AND FINISHED AS PER MATERIALS IM570.
BEARINGS SHALL BE AS DETAILED ON OTHER DESIGN SHEETS. BEAMS TO BE USED IN BRIDGES MADE CONTINUOUS BY THE POURED IN PLACE FLOOR, ARE TO BE AT LEAST 28 DAYS OLD
IS BASED ON 72.6% fs, TOTAL INITIAL PRESTRESS AND As = 0.217 sq. in.
BEFORE THE FLOOR IS PLACED UNLESS A SHORTER CURING TIME IS APPROVED BY THE BRIDGE ENGINEER. THE PORTIONS OF THE PRESTRESS BEAMS THAT ARE TO BE
2 " cl .
fs = 270 ksi
9
4b1
8
4b2
EMBEDDED IN THE ABUTMENT AND PIER DIAPHRAGMS SHALL BE ROUGHENED FOR A DISTANCE OF 10" FROM THE BEAM END BY SANDBLASTING OR OTHER APPROVED METHODS TO PROVIDE SUITABLE BOND BETWEEN THE BEAM AND THE DIAPHRAGM
SPECIFICATIONS:
" COIL TIES (MINIMUM 9000 LBS. PULL OUT CAPACITY)
CONSTRUCTION: STANDARD SPECIFICATIONS OF THE IOWA DEPARTMENT OF TRANSPORTATION, CURRENT SERIES, WITH
ALL BEAMS ARE TO BE INCREASED IN LENGTH TO COMPENSATE FOR ELASTIC SHORTENING, CREEP AND SHRINKAGE. IF THE STEEL DIAPHRAGM OPTION IS ALLOWED AND USED, HOLES MUST BE CAST IN THE WEB TO ACCOMMODATE THE STEEL DIAPHRAGM ATTACHMENTS AS DETAILED ON THE STEEL DIAPHRAGM DETAIL SHEET.
DESIGN STRESSES:
DESIGN STRESSES FOR THE FOLLOWING MATERIALS ARE TO BE IN ACCORDANCE WITH A.A.S.H.T.O. LRFD SPECIFICATIONS FOR HIGHWAY BRIDGES, SERIES OF 2007: REINFORCING STEEL IN ACCORDANCE WITH SECTION 5, GRADE 60. CONCRETE IN ACCORDANCE WITH SECTION 5, fc = 5000 psi (EXCEPT AS NOTED) PRESTRESSING STEEL IN ACCORDANCE WITH ** WHERE DEFLECTING STRANDS INTERFERE WITH PLACEMENT, SOME IN-PLACE BENDING MAY BE NECESSARY. ~~ 4b1 BARS TO BE EPOXY COATED. SECTION 5, fs = 270,000 psi.
IF SOLE PLATE IS REQUIRED FOR BEARING, SOLE PLATE IS TO BE SET IN FORMS WHEN BEAM IS CAST AND FORMED OUT BELOW TO EXCLUDE CONCRETE AS DETAILED ON THE BEARING SHEET. 0.6" DIAMETER STRANDS STRESSED TO NOT MORE THAN 5,000 LBS. EACH MAY BE USED IN LIEU OF THE a BARS WHICH RUN THE FULL LENGTH OF THE BEAM IN THE TOP FLANGE.
REVI SED 1 1 -09 - THE SPECI FI CATI ON REFERENCES WERE CHANGED. THE BEAM
D=2
3 -1 1
D=2
4 2
37-8 5-0
4 2
39-9 5-0
4 2 2 60 12 16 60 144 26
D=2
3 -6
NO. LENGTH NO. LENGTH NO. LENGTH NO. LENGTH NO. LENGTH
3-7 6b5
4b2 8-10 ~~4b1 7-2 9 3-9 1-8 3-0 1-10 5 ALL DIMENSIONS ARE OUT TO OUT. RADIUS TO | OF BAR. D = PIN DIAMETER. D=1 1-1 3 1-3 3e 1 1 -09 4
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
3c1
1 1
D=1 1-1 3d
C BEAM DETAILS
H44-29-07
9/29/2011
2:43:51 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-29-07
11x17_pdf.pltcfg
STEEL-( l b)
3 ( C.Y. )
-5 3 R=
~~4b1 4 * 4b1, 3c1, 3d 1* 5 @ 9 = 3-9 3@1-0=3-0 BAR 4a2 6b5 2 2 2 3c1 STRAIGHT STRANDS 6b5 4 * 4a2 ~~4b1 4b2 3 -9 2 -1 1-7 13 @ 1-9 = 22-9 10 | 1-4 4a2 4b2
1 "
C63
GHT 2 2 STRAI
6 6 1
4@9=3-0
10
4b2, 3d
6 3d SYMMETRICAL ABOUT | 3e
STRANDS
10@4=3-9 | BRG.
2@6
3e
4b1, 3c1, 3d 1*
5 @ 9 = 3-9
1-8
14 @ 1-9 = 24-6
10 | 3 2 2 6 2 2
6b5 @ 4 2
3 3d 3e STRANDS 1-8
6 6 1
4@9=3-0
11
4b2, 3d
6 2
SYMMETRICAL ABOUT |
3 2 3c1
2 2
2 2
10@4=3-9 | BRG.
2@6
3e
BEAM C67
4 * 6a1 6b5 4a2 22 3 ~~ ~ 17 @ 1-7 = 26-11 9 |
~~4b1 4b2
4b1, 3c1, 3d 1*
2 @ 1-1
1-3
1-4
GHT 2 2 STRAI
6b5 @ 4
2 BARS 6a1
3d
3e
STRANDS
3c1
DEFLECTED STRANDS
6a1 6b5
C71
GHT 2 2 STRAI 3 2
6 6 DETAI LS. 1
4@9=3-0
11
4b2, 3d
7-2
3d
3e
7 @ 2
71-8 |-| BEARINGS 10 @ 4 = 3-9 | BRG. 2@6 3e 72-8 END TO END OF BEAM
2 @ 4
SYMMETRICAL ABOUT |
BEAM C71
9 |
4b1, 3c1, 3d 1*
6a1 6b5 3 7 @ 2
3c1
22
6b5 @ 4
2@2
2 BARS 6a1
BEAM C75
GHT 2 2 STRAI 3d 3e STRANDS
C75
2 @ 4
6 1 10 @ 4 = 3-9 | BRG. 4b1, 3c1, 3d 1* 5 @ 9 = 3-9 BAR 4a2 3@1-0=3-0 1-4 1-5 2@6 3e
4@9=3-0
10
4b2, 3d
7-7
KEEP
SYMMETRICAL ABOUT |
7 @ 2
BEAM C80
19 @ 1-7 = 30-1 2 BARS 6a1 9 |
APPROVED BY BRI DGE ENGI NEER
2@4
6b5 @ 4
2 BARS 8a3
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
C80
1 1 -09
6 6 1
4@9=3-0
10
4b2, 3d
8-0
SYMMETRICAL ABOUT | NOTE: DIMENSIONS FOR THE LOCATION OF THE DEFLECTED STRANDS ARE AT | BEAM AND END OF BEAM.
C BEAM DETAILS
H44-30-07
9/29/2011
2:43:54 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-30-07
11x17_pdf.pltcfg
STRANDS
NOTES:
ALL DIAPHRAGM MATERIALS, INCLUDING BOLTS, NUTS AND WASHERS SHALL BE GALVANIZED.
SHOP DRAWINGS OF THE STEEL DIAPHRAGMS SHOWING LAYOUT AND DETAILS OF THE DIAPHRAGMS SHALL BE SUBMITTED FOR APPROVAL.
SEE DETAIL D
ALL COSTS FOR FURNISHING AND INSTALLING STEEL INTERMEDIATE DIAPHRAGMS SHALL BE INCLUDED IN THE PRICE BID FOR STRUCTURAL STEEL.
THE 1" HOLES FOR THE " H.S. BOLTS SHALL BE CAST INTO 6-10 TYPICAL BEAM SPACING 6 BEAM SPACES @ 6-10 = 41-0 SEE DETAIL E FOR 0 SKEW BRIDGE SEE DETAIL D FOR 15 AND 30 SKEW BRIDGES THE " H.S. BOLTS THROUGH THE WEB SHALL HAVE A THREAD LENGTH OF 3" MIN. AND 4" MAX. AND SHALL MEET THE REQUIREMENTS OF ASTM A449. THE WEB. DRILLING IS NOT ALLOWED.
CONCRETE DIAPHRAGM DETAILS SHALL BE PROVIDED IN THE BRIDGE PLANS FOR OVERHEAD BRIDGES. DESIGNER SHALL ADJUST THE CONCRETE, REINFORCING AND STRUCTURAL STEEL QUANTITIES ACCORDINGLY.
DETAIL D DETAIL D 1" HOLE IN WEB DETAIL D | BOLT DETAIL E | BOLT D/2 D/2 A & B BEAMS C BEAMS D 6 9
6 " H.S. BOLT WITH HEAVY HEX NUT AND 2 HARDENED WASHERS 9
" H.S. BOLT WITH HEAVY HEX NUT AND 2 HARDENED WASHERS 2
L6x4xx1-3
D/2
DETAIL D
C15 x 33.9
L6x4xx1-3 A/2
SECTION A-A
FOR 0 SKEW BRIDGES
SECTION A-A
FOR 15 AND 30 SKEW BRIDGES L6x4xx1-3
2 4 x x 1-3 {
A/2
2 - " x LENGTH H.S. BOLTS WITH NUTS AND WASHERS A + 1 -3 BRIDGE SKEW LENGTH OF H.S. BOLTS (IN.) REVI SED 1 1 -09 - MI NOR CHANGES WERE MADE TO AGREE WI TH OFFI CE STANDARD. 6 9 9 12 WEIGHT PER 0 DETAIL "E" (LB.) 15 & 30 BRIDGE SKEW
1 -3
30 WEIGHT A + 1 -3
1 -3
15 15 15
0 0 0
5.34
2 - L6x4xx1-3 = 41.2 LB
4.30
1 -3
(LB.)
1 -0
C15 x 33.9
1" HOLE IN 4-1" x 2" SLOTTED HOLES IN 6" LEG OF L. 4-" H.S. 1" HOLE IN 4" LEG OF L AND IN 4 x x 1-3 { BOLTS WITH HEAVY HEX NUT, 1-1" I.D. BY 2" O.D. PLAIN WASHER AND 2 4" LEG OF L
C15 x 33.9
4.30
36
1 - L6x4xx1-3 = 20.6 LB
HARDENED WASHERS
DETAIL E
DETAIL D
VARIES
APPROVED BY BRI DGE ENGI NEER
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
B C
* THE LENGTH OF THE C15 x 33.9 IS BASED ON A VARIABLE CLEARANCE OF 1 TO 2 BETWEEN THE FACE OF BEAM WEB AND END OF C15 x 33.9.
TOTAL WEIGHT
WEB THICKNESS (IN.) 0 4749 4619 BRIDGE SKEW 15 & 30 5009 4894 4-1" HOLES IN C15 x 33.9
INTERMEDIATE DIAPHR. STRUCT. STEEL - TOTAL (LB) = INTERMEDIATE DIAPHR. STRUCT. STEEL - TOTAL (LB) =
6 9
SECTION B-B
H44-31-07
9/29/2011
2:43:55 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-31-07
11x17_pdf.pltcfg
A/2
1 -3
15 &
1 -0
" MIN. (TYP.) |-| ABUT. BRG " " TYP. 1-7 2 9 2 5 ROADWAY WIDTH
15
180-10 180-11 166-10 166-11 166-10 166-11 158 158-0 159 0 3-11 0 158 158-0 159 0 3-11 0
5c1
COATING
5d2
I NTERSECTI ON
BREAKING
2 -0
BOND
" 0 1 = R
POI NT OF
1 = R
"
MI N.
15
30
5c3
5c14
205-10 205-11 206-3 191-10 191-10 183 183-0 184 0 3-11 0 191-11 191-11 183 183-0 184 0 3-11 0 192-3 192-3 183 183-0 184 0 4-1 0
" TYP.
1-7 2 9 2 5
ROADWAY WIDTH
"L" END TO END OF BARRIER RAIL (BID LENGTH) 7-0 END SECTION SEE BARRIER RAIL END SECTION DETAILS "F" ** ABUT. DIAPH. EXT. 6 CONSTRUCTION JOINT 4 EQUAL SP. a-5c1; a-5c3; a-5c14 6 6 "W" 5 EQ. SPA. TYPICAL PERMISSIBLE CONSTRUCTION JOINT A 5c1 5d2 (EACH END) 6} MIN. LAP 5d1
LINES OF INTERSECTION
** ABUT. DIAPH. EXT. "C" SPACES AT 1-0 = "D" ; "E" - 5c1 & 5c2 "W" 5 EQ. SPA. 6 6 4 EQUAL SP. a-5c1; a-5c3; a-5c14 B 2-2 6
SPACI NG
"F"
5c1
JOINT 2 -9
5d1
I NTERSECTI ON
CONSTRUCTION
2 -0
188-10
201-4
213-10
226-4
243-0
*1 0
" 0 1 = R
POI NT OF
3
REVI SED 1 1 -09 - THE SPECI FI CATI ON REFERENCES WERE CHANGED. 5 3 1 "
1 = R
"
5c2 B
5c2
THE PERMISSIBLE CONSTRUCTION JOINTS ARE TO BE PLACED BETWEEN VERTICAL BARS AT A MINIMUM SPACING OF 20 FEET. CONSTRUCTION JOINT
THE JOINT SEALER SHALL BE LIGHT GRAY NONSAG LATEX CAULKING SEALER MARKETED FOR OUTDOOR USE. NO TESTING OR CERTIFICATION IS REQUIRED.
CONTACT SURFACES ARE TO BE COATED WITH AN APPROVED BOND BREAKER. TOP OF THE BARRIER RAIL IS TO BE PARALLEL TO THE THEORETICAL |
APPROVED BY BRI DGE ENGI NEER
COST OF THE JOINT SEALER AND BOND BREAKER SHALL BE CONSIDERED INCIDENTAL TO OTHER CONSTRUCTION.
GRADE.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
CROSS SECTIONAL AREA OF THE STANDARD SECTION OF THE BARRIER THE CONCRETE BARRIER RAIL IS TO BE BID ON A LINEAL FOOT BASIS. THE NUMBER OF LINEAL FEET OF BARRIER RAIL INSTALLED WILL BE PAID 1 1 -09 FOR AT THE CONTRACT PRICE PER LINEAL FOOT BASED ON PLAN QUANTITIES. PRICE BID FOR CONCRETE BARRIER RAILING SHALL BE FULL COMPENSATION FOR FURNISHING ALL MATERIAL, EXCLUDING REINFORCING STEEL, AND ALL OF THE EQUIPMENT AND LABOR REQUIRED TO ERECT THE RAIL IN ACCORDANCE WITH THESE PLANS AND CURRENT SPECIFICATIONS. CONCRETE BARRIER RAILS PLACED USING THE SLIPFORM METHOD WILL REQUIRE THE USE OF A CLASS BR CONCRETE IN ACCORDANCE WITH ARTICLE 2513.03, A, 2, OF THE STANDARD SPECIFICATIONS. CAST-IN-PLACE BARRIER RAILS SHALL USE CLASS C MIX. CLASS D CONCRETE IS NOT PERMITTED FOR CONCRETE BARRIER RAILS (CAST-IN-PLACE OR SLIPFORMED METHOD). IF CONDUIT IS REQUIRED IN THIS PLAN THE RIGID STEEL CONDUIT, JUNCTION BOXES AND FITTINGS INCLUDING LABOR AND ANY ADDITIONAL WORK TO DO THE INSTALLATION IS CONSIDERED INCIDENTAL TO THE COST OF THE RAILING. RAIL = 2.84 SQUARE FEET.
LATEST REVI SI ON DATE
H44-32-07
9/29/2011
2:43:57 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-32-07
11x17_pdf.pltcfg
*1 0
2 -1 0
2 -1 0
SHAPE
NO. 12 4 4 12 6
WEIGHT 99 17 25 144 23
6 @ 5= 2-7
5 @ 6 = 2-6
2 @ 7 = 1-3
| 1" HOLES
JOINT
6d1
1 -7
1 -7
5c5-10
6d1 7 5
6 8 1
60 81 4
A
GUTTER LINE
6d2
B
1"
5d3
6d2 5d3
C
3 @ 6=1-6
D
2 @ 7 = 1-3 3
1-0
2-0
4-0
F
5c5-5c10 SPACING (INCLUDE WITH BARRIER RAIL REINFORCING) TOTAL WEIGHT (LBS.) 458 4t1 ABUTMENT WING TIE BARS 4 VARIES 5
HOLES
1-8
SLOPE FACE
OF WALL
2 TO 24
2 -0
2 -1 0
LINES OF
INTERSECTION
1 -1 0
SLOPE 5 TO 7 VERTICAL
5-10 2 -6 3 -9 D=4
10
D=4
1 1
ABUT.
WI NG
1-0
2-0
4t1
" X "
3 = D
9 1
10 8 2 10 7
| 1" HOLES 2
NOTE: CONSTRUCTION JOINT BETWEEN TOP OF WING AND BARRIER RAIL IS ROUGHENED CONCRETE.
6d1
6d2 2 -0
6d1
6d2 2 -0
5c5-5c10
NOTE: THE 10" RADIUS AND 1" RADIUS ARE TYPICAL AND SHALL BE USED WHEN CONSTRUCTING THE CORNERS FOR VIEW A-A, SECTION B-B, SECTION C-C AND SECTION D-D.
6c1 2 -9
6c2
6c1
6c1
4t1
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D = PIN DIAMETER.
2 -1 0
2 -9
5d3 8 1 -6
1 -6
" 0 1 = R
2 -1 0
THE 6c4, 6c3, 5c5-10, 2-6d2 AND 4t1 BARS ARE TO BE PLACED WITH THE ABUTMENT WING. THE 3 DETAILS FOR PLACEMENT ARE SHOWN ON THE WING ABUTMENT
WING
CONSTR. 2 -3 MI N.( TYP) 2 -3 MI N.( TYP) 1 -1 1 MI N. 6c3 6c4 6c4 5c5-10 JOINT (TYP.) 6c4
6d2 6d2
SHEET.
NOTE: 1 -1 1 MI N.
APPROVED BY BRI DGE ENGI NEER
4t1 5c5-10
DASHED LINES BELOW THE TOP OF WING ARE THE ABUTMENT WING
LATEST REVI SI ON DATE
2 -3 MI N.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
H44-33-07
VIEW A-A
SECTION B-B
SECTION C-C
SECTION D-D
9/29/2011
2:43:58 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-33-07
11x17_pdf.pltcfg
2 -2
3 1
5d1 5d2
36 36
40-0 34-8
1,502 1,302
54 36
40-0 22-0
2,253 826
54 36
40-0 28-3
2,253 1,061
54 36
40-0 34-6
2,253 1,295
72 36
40-0 21-10
3,004 820
72 36
40-0 32-5
3,004 1,217
72 36
40-0 38-8
3,004 1,452
90 36
40-0 26-0
3,755 976
90 36
40-0 34-4
3,755 1,289
1,832
1,832
1,832
1,832
1,832
1,832
1,832
1,832
1,832
8,215
8,788
9,347
9,879
10,478
11,445
12,003
12,576
13,312
D=3 5
D=4
2 -7
2 -4
2 -0
2 -0
5c14 5c1
1-0
5c2
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D = PIN DIAMETER.
REVI SED 1 1 -09 - THE REI NFORCI NG STEEL WAS CHANGED TO AGREE WI TH H44-33-07.
29.9 2.6
32.6 2.6
35.2 2.6
2 -0 37.8 2.6
D=3 5
5c3
1 -2
7
6
D=3
0 -1 1
TOTAL C.Y.
* SEE SHEET H44-32-07 FOR DIMENSION "B". CONCRETE QUANTITIES SHOWN ARE BASED ON 30 SKEW BID LENGTHS.
1 1 -09
=3 D
40.5 2.6
45.1 2.6
47.7 2.6
50.4 2.6
53.9 2.6
32.5
35.2
37.8
40.4
43.1
47.7
50.3
53.0
56.5
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
H44-34-07
9/29/2011
2:44:00 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-34-07
11x17_pdf.pltcfg
10
1" HOLES SKEW DI MENSI ON OR NUMBER L (FT.-IN.) S (FT.-IN.) B C (FT.-IN.) D (FT.-IN.) E F (FT.-IN.) 0 15 30 156-3 142-3 18 7-8 138-3 17 0 0 168-4 154-4 19 7-11 150-4 18 0 15 168-5 154-5 19 7-11 150-5 18 0 30 168-9 154-9 19 7-11 150-9 18 0 0 180-10 166-10 21 7-9 162-10 20 0 15 180-11 166-11 21 7-9 162-11 20 0 30 181-3 167-3 21 7-9 163-3 20 0 0 193-4 179-4 23 7-7 175-4 22 0 15 193-5 179-5 23 7-7 175-5 22 0 30 193-9 179-9 23 7-7 175-9 22 0 0 15 30 206-3 192-3 24 7-10 188-3 23 0 SKEW DI MENSI ON OR NUMBER L (FT.-IN.) S (FT.-IN.) B C (FT.-IN.) D (FT.-IN.) E F (FT.-IN.) 6c2 6d2 2 -1 0 1 -6 6c1 TOP OF 2 ABUT. WING 2 -3 MI N.( TYP) 6d1 6d2 4c4 6d1
137-10 137-11 17 0 17 0
2 -3 MI N.
6d2
15
6c3
VIEW A-A
SECTION B-B
7-0 END SECTION PERMISSIBLE CONSTRUCTION JOINT 3 6 @ 5 = 2-7 6 6 3@6 =1-6 2@7 =1-3 4
"B" POST SPACES @ "C" = "D": 2 - END POSTS; "E" - INTERIOR POSTS
2-0
PERMISSIBLE CONSTRUCTION CONSTRUCTION JOINT 6 2-2 8 EQ. SPA. 9-6c1 EA. FACE & 9-4c5 4 EQ. SPA.: 10-4t2 4j3 TIES (TYP. BETWEEN 4j3 TIES (TYP. BETWEEN INTERIOR POSTS) 4j3 TIES 6h1 (TYP.) 6h2 (AT EACH END) 2 3-6 MIN. SPLICE | 1" HOLES " GAP 6 1-6 1-6 11 EQ. SPA. @ 6"(}) 1-0 1-0 12 EQ. SPA. @ 6"(}) 1-0 | END POST | INTERIOR POST (TYP.) | END POST CONSTRUCTION JOINT 1-0 8 1-8 1-0 JOINT
6d1 BACK FACE 6d2 TRAFFIC FACE A 6c2 " GAP BETWEEN RAI L AND ABUT.DI APH.EXT. B 4c4
MIN. LAP
END POSTS)
1 -8
4j2 TIES
3 SPACES @ 3"
2-4j3 TIES EACH END OF RAIL PANEL (TYP.) 6d2 4t1 A B CONSTRUCTION JOINT BETWEEN TOP OF WING AND RAIL IS ROUGHENED CONCRETE. 4t2
PROVIDE 5 HOLES FORMED WITH 1" PLASTIC 6j1 (TYP.) CONDUIT. COST TO BE INCLUDED IN PRICE BID FOR CONCRETE OPEN RAILING.
COST OF THE JOINT SEALER AND BOND BREAKER SHALL BE CONSIDERED INCIDENTAL TO OTHER CONSTRUCTION.
HATCHED AREA
APPROVED BY BRI DGE ENGI NEER
1 -0
THE CONCRETE OPEN RAIL IS TO BE BID ON A LINEAL FOOT BASIS MEASURED FROM END TO END OF RAIL. THE NUMBER OF LINEAL FEET OF OPEN RAIL INSTALLED WILL BE PAID FOR AT THE CONTRACT PRICE PER LINEAL FOOT. PRICE BID FOR "CONCRETE OPEN
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
RAILING, TL-4" SHALL BE FULL COMPENSATION FOR FURNISHING ALL MATERIAL, EXCLUDING REINFORCING STEEL, AND ALL OF THE EQUIPMENT AND LABOR REQUIRED TO CONSTRUCT THE RAIL IN ACCORDANCE WITH THESE PLANS AND CURRENT SPECIFICATIONS. 07-1 0
ALL OPEN RAIL REINFORCING STEEL IS TO BE INCLUDED WITH THE SUPERSTRUCTURE REINFORCING STEEL.
BOND BREAKING COATING
THE CAST-IN-PLACE OPEN RAIL SHALL USE CLASS C MIX. CLASS D CONCRETE IS NOT PERMITTED.
H44-35-07
IF CONDUIT IS REQUIRED IN THIS PLAN THE RIGID STEEL CONDUIT, JUNCTION BOXES AND FITTINGS INCLUDING LABOR AND ANY ADDITIONAL WORK TO DO THE INSTALLATION IS CONSIDERED INCIDENTAL TO THE COST OF THE RAILING.
9/29/2011
2:44:01 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-35-07
11x17_pdf.pltcfg
6c1
1 -1 0
2 -1 0
2 -8
1-1
VAR.
4c5 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 709 68 98 38 33 NO. 96 16 16 20 16 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 709 68 98 38 33 NO. 96 16 16 20 16 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 709 68 98 38 33 NO. 96 16 16 20 16 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 709 68 98 38 33 NO. 96 16 16 20 16 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 709 68 98 38 33 NO. 168 16 16 20 52 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 1,241 68 98 38 107 NO. 168 16 16 20 52 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 1241 68 98 38 107 NO. 168 16 16 20 52 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 1241 68 98 38 107 NO. 168 16 16 20 52 LENGTH WEIGHT 4-11 2-10 4-1 2-10 3-1 1241 68 98 38 7 107 2 -1 0 3 3
6d2
6d1 6d2
24 32
6-8 6-9
240 324
24 32
6-8 6-9
240 324
24 32
6-8 6-9
240 324
24 32
6-8 6-9
240 324
24 32
6-8 6-9
240 324
24 32 48
24 32 48
24 32 48
24 32 48
( TYP. )
JOINT
6d2
6h1 6h2
24 24
40-0 36-8
1,442 1,322
36 24
40-0 24-8
2,163 889
36 24
40-0 30-11
2,163 1,114
36 24
40-0 37-2
2,163 1,340
48 24
40-0 25-2
2,884 907
48 24
40-0 31-5
2,884 1,133
48 24
40-0 37-8
2,884 1,358
60 24
40-0 25-8
3,605 925
60 24
40-0 34-0
3,605 1,226
4t1
VERTICAL DOWELS, OPEN RAIL HOOP, INTERIOR POST HOOP, OPEN RAIL HOOP, END POST
SECTION C-C
1 1-1 4
4t1 4t2
16
VARIES
19
16
VARIES
19
16
VARIES
19
16
VARIES
19
16
VARIES
19
16 40
VARIES 1-11
19 51 13,289 7-0
16 40
VARIES 1-11
19 51 13,756
16 40
VARIES 1-11
19 51 14,526
16 VARIES 40 1-11
19 51 15,308 2 -8
4 EQ.SPA. :1 0-5d3
4c5
8,880
9,409
10,115
10,823
11,352
* TRAFFIC FACE 5d3 BARS MAY REQUIRE FIELD CUTTING OR BENDING FOR HIGHER SKEW BRIDGES.
5d3
END SECTION 2 2 1
ROUGHENED 3 JOINT
1 -1
2 -6
3 -9
D=2 1 -2
D=4
0 -1 1 & 1 -2
1 -0
2 8
" GAP BETWEEN RAI L AND ABUT.DI APH.EXT. CHANGED 6j1 BAR LENGTH.
END POST
INTERIOR POST
5d3
4t2
6c1
4 4 4
SECTION D-D
1-3 6h1 1 -8 1-0 2 6j1 1 -0 ROUGHENED JOINT 4j3 1" CL.
2 -2
1 -3
1 -4
3-0
D=2
4t1
4t2
1 -0 1 -0
1 -0
4j2
4j3
4j4
9 1-0 9
6j1
6j1
6j1
4c5
6d1
6d2
5d3
6c1
END POST
INTERIOR POST
NOTE:
6d2
21.9 2.7
23.8 2.7
25.8 2.7
27.7 2.7
29.6 2.7
TOTAL (C.Y.)
27.4
29.4
31.7
33.9
35.9
40.1
42.2
44.4
47.3
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
CONCRETE QUANTITIES SHOWN ARE BASED ON 30 SKEW. FOR "E" SEE SHEET H44-35-07.
LATEST REVI SI ON DATE
07-1 0
H44-36-07
9/29/2011
2:44:03 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
h44-36-07
11x17_pdf.pltcfg
2 -8
D=4
1 7
4j4
4j2
P I E R D I A P H R A G M
( N O R M A LT O G R A D E )
P I E R D I A P H R A G M ( N O R M A LT O G R A D E )
3
TYP. SOLE { 7 x 1 x "C"
6
(TYP.)
PINTLE { 12x1x"E" PINTLE { 12 x 1 x "E" DETAIL C PINTLE DETAIL 10 x 2 x "F" LAMINATED NEOPRENE PADS (SEE DETAILS) BAR BAR x x x "H" " STEEL {, ASTM-A1011 {S REQUIRED, 9 x "F"-" x 0-9
PART ELEVATION
B NOTCH BEAM END TO SOLE { THICKNESS MAXIMUM 1"
PART ELEVATION
A
1 "- " D" | PINTLES
"A" MATERIAL FOR NEOPRENE 9 "A"
B BEAMS.
"B"
"A"
"B"
SLOPE SLOPE
"B"
"G"
"G"
"B"
PINTLE DETAIL
DETAIL C
SOLE { 7 x 1 x "C"
PINTLE {
4.2% "F" + 9
CORRECTI ON 06-1 1 - THE REFERENCE TO BAR DI MENSI ON " A" WAS CHANGED TO " H" I N SECTI ON B-B FOR A &
A
FLAT & TRUE
BAR x x "H" "E"
SECTION A-A
P/G ELEV. @ NEAR ABUT. - P/G ELEV. @ PIER 1 = 100% SPAN 1 LENGTH
EXTENSI ON
x KEEPER BAR
TAPERED. REFER TO TABLE FOR DIMENSIONS OF TAPERED PADS. COST OF NEOPRENE PADS SHALL BE INCLUDED
BAR
x 0-9
PINTLE {
TYP.
1 "
" B"
R= 1
" A"
" H"
PAD
MI N.
LAMINATED
DETAIL C
BAR
PINTLE DETAIL
EXPANSION PIER BEARING NOTES:
SURFACES MARKED "V" SHALL BE FINISHED ANSI 250. PINTLE PLATES ARE A PART OF THE SUPERSTRUCTURE "STRUCTURAL STEEL QUANTITY". COSTS OF ANCHORED CURVED SOLE PLATES AND NEOPRENE PADS ARE TO BE INCLUDED IN THE PRICE BID FOR "PRETENSIONED PRESTRESSED CONCRETE BEAMS". THE SOLE PLATES AND PINTLE PLATES SHALL BE GALVANIZED. ALL WELDING SHALL BE COMPLETED PRIOR TO GALVANIZING. THE SURFACE OF THE PINTLE PLATE IN CONTACT WITH THE LAMINATED NEOPRENE PADS SHALL BE FREE OF PROJECTIONS DUE TO THE GALVANIZING. SOLE PLATES ARE TO BE SET IN FORMS WHEN BEAMS ARE CAST AND THE BOTTOM OF BEAMS FORMED OUT AS SHOWN TO EXCLUDE CONCRETE. SOLE PLATES SHALL COMPLY WITH ONE OF THE FOLLOWING : ASTM A 852 ASTM A 514 GRADE B ASTM A 709 GRADE HPS 70W
" B"
" E"
FIXED PIER
4 1 9
4 1
| PINTLES
VARIABLE DIMENSIONS
BEAM BOTTOM FLANGE WIDTH
APPROVED BY BRI DGE ENGI NEER
1-0
C BEAMS 1-8
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
EXPANSION PIER
"H"
0-11
1-2
H44-37-07
9/29/2011
2:44:04 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-37-07
11x17_pdf.pltcfg
SYMMETRICAL ABOUT | ROADWAY 3-3 6-10 KEYED NOTCH (SEE DETAIL) | PIER 6-10 TYP. 10 5 5n1 5m1 | BEARINGS 1 -6 1 -6 1" PREFORMED EXPANSION JOINT MATERIAL 3 -0 1" 9 " PREFORMED EXPANSION JOINT MATERIAL (TYP.) 2 5n1 3 3 EQ. SP. 3 5-7 1-3 4-4 2-6 4-4 2-6 4-4 3-3
A
2-0
" 1
5m1
5n1 2-0 6-10 6-10 6-10 6-10 6-10 6-10 2-0 | BEAMS 8
45-0
TYPICAL PLAN
NOTE: SEE SHEET H44-09-07 FOR "U" DIMENSION. " U" SYMMETRICAL ABOUT | ROADWAY GRADE ELEV. @ | PIER
5c1
5m1
5c1
8e1
a2
a1
5n1
a1
a2
8e1
TOP OF PI LES
3 3 1 12 3 EQ. SPA. 1-6 1-0 1-0 3 EQ. SPA. 3 -0 1-6 b1 1-0 TYP. TYP. 1-0 b1 1 12 8 a1 8e1 1 -0
3 3
2" CL.
3 -0
1 -6
10 PILE BENT
1 1 1 8e1 a2 1 5c1 a1 5n1 5m1
11 PILE BENT
1 a1 1 a2 5c1 8e1
2" CL.
b1
b1
5c1 3 4 3-0
5c1 3 4 3-0
VIEW A-A
FOR 10 PILE BENT 1 12 3 EQ. SPA. 1-6 1-0 1-0 3 EQ. SPA. 12 PILE SPACES @ 3-6 = 42-0 1-6 3 b1 1-0 TYP. TYP. 1-0 b1 1 12
VIEW A-A
FOR 11, 12, 13, 14, 15 & 16 PILE BENTS
2" CL.
11
11
12 PILE BENT
1 1 1 8e1 REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS. a2 1 5c1 a1 5n1 5m1
13 PILE BENT
1 5c1 a2 1 8 a1 2" CL. a1 8e1 3 -0 8e1 1 -0
b1
5c1 3 4 3-0
1 12
b1
TYP. 1-0
TYP. 1-0
b1
1 12
1-6
1-6
VIEW A-A
FOR 17 PILE BENT
14 PILE BENT
1 1 8e1 a2 1 5c1 a1 5n1 5m1
15 PILE BENT
1 1 5c1 a2 1 a1 8e1
APPROVED BY BRI DGE ENGI NEER
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
1 12
b1
TYP. 1-0
1-0 7
TYP. 1-0
b1
1 12
1-6
1-6
H44-38-07
16 PILE BENT
17 PILE BENT
9/29/2011
2:44:07 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-38-07
11x17_pdf.pltcfg
2" CL.
1 -6
a2
TOP OF PI LES
2" CL.
1 -6
a2
1 -0
a2
TOP OF PI LES
3 EQ. SPA.
2 EQ. SPA.
BAR a1 a2 b1
SHAPE
NO. SIZE 8 4 4 38 4 12 12 9 8 9 5 8 5 5
5c1 8e1
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR REINFORCING BAR SHALL BE 2 INCHES UNLESS OTHERWISE NOTED OR SHOWN.
5m1 5n1
2951
2696
2745
2793
2842
2590
2627
2165
STRUCTURAL
----16.1
----16.1
15.5 16.1
15.5 16.1
15.5 16.1
15.4 16.1
15.4 16.1
15.3 -----
CONCRETE (CY)
2 -8
2 -6
1 -6
D=2
D=6
D=2
2-8
8e1
5m1
5c1
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D=PIN DIAMETER.
PILE SIZE
17
16
37
108 14 14
-----
--
--
-15 14
243-0
-----
--
--
-16
NOTE: FRICTION BEARING INCLUDES SIDE FRICTION AND END BEARING IN SOIL. POINT BEARING INCLUDES SIDE FRICTION AND POINT BEARING IN ROCK.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
H44-39-07
9/29/2011
2:44:08 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-39-07
11x17_pdf.pltcfg
SYMMETRICAL ABOUT | ROADWAY 3-3 6-10 KEYED NOTCH (SEE DETAIL) | PIER 6-10 TYP. 10 5 5n1 5m1 | BEARINGS 1 -6 1 -6 5-7 1-3 4-4 2-6 4-4 2-6 4-4 3-3
5n1 2-0 6-10 6-10 6-10 6-10 6-10 6-10 2-0 | BEAMS
45-0
TYPICAL PLAN
NOTE: SEE SHEET H44-09-07 FOR "U" DIMENSION. " U" SYMMETRICAL ABOUT | ROADWAY GRADE ELEV. @ | PIER
a2
5c1
5m1
5c1
8e1
a1
5n1
a1
a2
8e1
3 -0
2-0
1" PREFORMED EXPANSION JOINT MATERIAL 1 12 1-0 1-6 6 PILE SPACES @ 7-0 = 42-0 1-0 7 PILE SPACES @ 6-0 = 42-0 1-6 8 b1 TYP. 5 EQ. SPA. 1-0 TYP. 4 EQ. SPA. 1-0 12 b1 1 1" " PREFORMED EXPANSION JOINT MATERIAL (TYP.) 2 5n1 3 3 EQ. SP. 3
" 1
5m1
7 PILE BENT
8 PILE BENT
a2 5c1 8e1
5c1
5m1
8e1
a2
a1
5n1
a1
3 EQ. SPA. b1 1-0 12 1-0 1-6 8 PILE SPACES @ 5-3 = 42-0 1-0 4 EQ. SPA. 1 1 1-6 3 -6 a1 8e1 4 EQ. SPA. TYP. TYP. 1-0 12 3 1 3 7
2 EQ. SPA. 3 3 7
b1
1 1
2" CL.
1 -0
3 -6
a2 b1
1 -0
a2 b1
1 -6
9 PILE BENT
10 PILE BENT
1 1
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR THE 1 4" PI LE OPTI ON &
8e1
a2
5c1
a1
5m1
5c1
8e1
5c1 3 4 3-0
5n1
a1
a2
2" CL.
1 1
5c1 3 4 3-0
VIEW A-A
FOR 7, 8, 9 & 10 PILE BENTS 1 12 3 EQ. SPA. 1-6 1-0 1-0 3 EQ. SPA. 11 PILE SPACES @ 3-9 = 41-11 1-6
APPROVED BY BRI DGE ENGI NEER
VIEW A-A
FOR 11 & 12 PILE BENTS
1 12
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
11 PILE BENT
12 PILE BENT
LATEST REVI SI ON DATE
1 1 -09
H44-40-07
9/29/2011
2:44:11 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-40-07
11x17_pdf.pltcfg
18.6
18.6
18.6
18.6
18.6
18.6
3 -2
2 -6
1 -6
D=2
D=6
D=2
2-8
8e1
5m1
5c1
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D=PIN DIAMETER.
7 138-10 7 8 151-4 7 8 163-10 7 9 176-4 7 CAP DEPTH I S 3 -6. 9 188-10 8 10 201-4 8 10 213-10 9 11 226-4 9 12 243-0 REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR THE 1 4" PI LE OPTI ON & 10
HP14x73 HP14x89 HP14x73 HP14x89 HP14x73 HP14x89 HP14x73 HP14x89 HP14x73 HP14x89 HP14x73 HP14x89 HP14x73 HP14x89 HP14x73 HP14x89 HP14x73 HP14x89
NOTE: FRICTION BEARING INCLUDES SIDE FRICTION AND END BEARING IN SOIL. POINT BEARING INCLUDES SIDE FRICTION AND POINT BEARING IN ROCK.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
H44-41-07
9/29/2011
2:41:33 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-41-07
11x17_pdf.pltcfg
6-10
6-10
6-10
6-10
6-10
6-10
A
3 1
6-10
6-10
5-7
3 1
4-4
6 2
4-4
6 2
4-4 | BEARINGS
2-6
| PIER
| ROADWAY 8 1 -6
1" PREFORMED EXPANSION JOINT MATERIAL " PREFORMED EXPANSION JOINT MATERIAL 1" (TYP.)
1 -6
3 -1
SYMMETRICAL ABOUT THIS POINT THROUGH 180 ROTATION EXCEPT STEP ELEVATIONS 2-3
NOTE: THE HEIGHT OF THE STEPS ON THE BRIDGE SEAT IS EQUAL TO THE DIFFERENCE IN
TYPICAL PLAN
SYMMETRICAL ABOUT | PIER EXCEPT STEPS GRADE ELEV. @ | PIER " U"
ELEVATIONS OF THE TOP OF SLAB AT ADJACENT BEAMS ALONG | PIER. SEE SHEET H44-15-07 FOR "U" DIMENSION.
8e1
a2
a1
5c1
a1
5c1
a2
8e1 TOP OF PI LES TOP OF PI LES 1 -6 2" CL. TOP OF PI LES 1 -6 2" CL. 2" CL. 3 EQ. SPA. 3 3 7 3 EQ. SPA. 2" CL. 3 2 EQ. SPA. 3 3 7 2 EQ. SPA. 3 2" CL.
3 -0
3 -0
1 12
b1
1 12
a1 8e1
2" CL.
a1 8e1
1 -0
1-6
2" CL.
10 PILE BENT
8e1 a2 5c1 a1 a1
11 PILE BENT
5c1 a2 8e1
5c1 3 4 3-1
b1
1 -6
a2
1 -0
9 9
" 1
VIEW A-A
FOR 10 PILE BENT
VIEW A-A
FOR 11, 12, 13, 14, 15 & 16 PILE BENTS
1 12
b1
1 12 3 3 11 7 11 3
1-6
3 -0
1 -0
12 PILE BENT
8e1 REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS. a2 5c1 a1 a1
13 PILE BENT
5c1 a2 8e1
a2 b1
5c1 3 4 3-1
1 12
b1
TYP. 1-0
TYP. 1-0
b1
1 12
VIEW A-A
FOR 17 PILE BENT
1-6
1-7
14 PILE BENT
8e1 a2 5c1 a1 a1
15 PILE BENT
5c1 a2 8e1
APPROVED BY BRI DGE ENGI NEER
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
1 12
b1
TYP. 1-0
TYP. 1-0
b1 1 12
1-7
1-6
H44-42-07
16 PILE BENT
17 PILE BENT
9/29/2011
2:41:38 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-42-07
11x17_pdf.pltcfg
BAR a1 a2 b1
SHAPE
NO. SIZE 8 4 4 38 4 9 8 9 5 8
5c1 8e1
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR REINFORCING BAR SHALL BE 2 INCHES UNLESS OTHERWISE NOTED OR SHOWN.
2958
2690
2740
2789
2838
2888
2615
2335
STRUCTURAL
----17.4
----17.4
16.8 17.4
16.8 17.4
16.7 17.4
16.7 17.4
16.6 17.4
16.6 -----
CONCRETE (CY)
2 -8
D=2
2 -7
D=6
2-9
8e1
5c1
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D=PIN DIAMETER.
PILE SIZE
17
16
38
109 14 14
-----
--
--
-15 15
243-0
-----
--
--
-16
NOTE: FRICTION BEARING INCLUDES SIDE FRICTION AND END BEARING IN SOIL. POINT BEARING INCLUDES SIDE FRICTION AND POINT BEARING IN ROCK.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
H44-43-07
9/29/2011
2:41:39 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-43-07
11x17_pdf.pltcfg
6-10
6-10
6-10
6-10
6-10
6-10
A
3 1
6-10
6-10
5-7
3 1
4-4
6 2
4-4
6 2
4-4 | BEARINGS
| PIER
| ROADWAY 8 1 -6
SYMMETRICAL ABOUT THIS POINT THROUGH 180 ROTATION EXCEPT STEP ELEVATIONS 2-3
TYPICAL PLAN
SYMMETRICAL ABOUT | PIER EXCEPT STEPS GRADE ELEV. @ | PIER " U"
1 -6
NOTE: THE HEIGHT OF THE STEPS ON THE BRIDGE SEAT IS EQUAL TO THE DIFFERENCE IN ELEVATIONS OF THE TOP OF SLAB AT ADJACENT BEAMS ALONG | PIER. SEE SHEET H44-15-07 FOR "U" DIMENSION.
8e1
a2
a1
5c1
a1
5c1
a2
8e1
3 -1
1 12
1-0
1-0
1-0
1-0
b1
b1
6 EQ. SPA. FOR 7-7 PILE SPACING 7-7 7-7 3-3 6-6
1 12
8 5-9 1-6
7 PILE BENT
8e1
a2
5c1
a1
a1
5c1
a2
8e1
2 EQ. SPA. 3 3 7
1 1
1 12
b1
1 3 -6 12
a1 8e1
1 1
2" CL.
a1 8e1
1 -0
3 -6
a2 b1
1 -0
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR THE 1 4" PI LE OPTI ON &
9 PILE BENT
10 PILE BENT
1 1
1-6
1 -6
9 9
2-6
1" PREFORMED EXPANSION JOINT MATERIAL " PREFORMED EXPANSION JOINT MATERIAL 1" (TYP.)
" 1
b1
5c1 3 4 3-1
5c1 3 4 3-1
8e1
a2
5c1
a1
a1
5c1
a2
8e1
VIEW A-A
FOR 7, 8, 9 & 10 PILE BENTS
VIEW A-A
FOR 11 & 12 PILE BENTS
1 12
b1
1 12
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1-6
1 1 -09
11 PILE BENT
12 PILE BENT
H44-44-07
9/29/2011
2:41:41 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-44-07
11x17_pdf.pltcfg
20.0
20.0
20.0
20.0
20.0
20.0
3 -2
D=2
2 -7
D=6
2-9
8e1
5c1
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D=PIN DIAMETER.
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR THE 1 4" PI LE OPTI ON &
SEE SHEET H44-17-07 FOR STEP REINFORCING STEEL QUANTITIES AND DETAILS.
NOTE: FRICTION BEARING INCLUDES SIDE FRICTION AND END BEARING IN SOIL. POINT BEARING INCLUDES SIDE FRICTION AND POINT BEARING IN ROCK.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
H44-45-07
9/29/2011
2:41:44 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-45-07
11x17_pdf.pltcfg
6-10
6-10
6-10
6-10
6-10
6-10
A
6-10
3 1
6-10
5-7
3 1
4-4
6 2
4-4
6 2
4-4
| PIER
| ROADWAY
| BEARINGS 7
9
1 -7
SYMMETRICAL ABOUT THIS POINT THROUGH 180 ROTATION EXCEPT STEP ELEVATIONS 2-4(-)
TYPICAL PLAN
NOTE: THE HEIGHT OF THE STEPS ON THE BRIDGE SEAT IS EQUAL TO THE DIFFERENCE IN ELEVATIONS OF THE TOP OF SLAB AT ADJACENT BEAMS ALONG | PIER. SEE SHEET H44-22-07 FOR "U" DIMENSION. SYMMETRICAL ABOUT | PIER EXCEPT STEPS GRADE ELEV. @ | PIER " U" " PREFORMED 1" PREFORMED EXPANSION JOINT MATERIAL 1" 2 8 EXPANSION JOINT MATERIAL (TYP.) 2-8
1 -7
3 -3
" 1
a1 5c1 a2 8e1
8e1
a1
a2
5c1
1 12
b1 1-0 4 EQ. SPA. TYP. 1-0 TYP. 1-0 1-0 3 EQ. SPA.
b1
1 12
1-6
1-7
10 PILE BENT
8e1 a1 a2 5c1 a1
12 PILE BENT
TOP OF PI LES 5c1 a2 3 8e1 3 7 3 3 3 7 3 TOP OF PI LES 1 -6 2" CL. 3 EQ. SPA. 3 EQ. SPA. 2" CL. 2 EQ. SPA. 2 EQ. SPA. 2" CL.
3 -0
3 -0
1 -0
1 REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS. 12
b1 1-0 4 EQ. SPA. TYP. 1-0 TYP. 1-0 1-0 3 EQ. SPA. 15 PILE SPACES @ 3-3 = 48-9
b1
1 12
2" CL.
b1
1 -6
a2
1 -0
a2 b1
5c1 3 4 3-3
5c1 3 4 3-3
1-7
1-7
14 PILE BENT
16 PILE BENT
VIEW A-A
FOR 10, 12 & 14 PILE BENTS 8e1 a2 a1 5c1 a1 5c1 a2 8e1
VIEW A-A
FOR 16, 18 & 19 PILE BENTS
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 12
b1
TYP. 1-0
TYP. 1-0
b1
1
LATEST REVI SI ON DATE
12 1 1 -09
1-6
1-7
18 PILE BENT
19 PILE BENT
H44-46-07
9/29/2011
2:41:46 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-46-07
11x17_pdf.pltcfg
BAR a1 a2 b1
SHAPE
NO. SIZE 8 4 4 47 4 9 8 9 5 8
5c1 8e1
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR REINFORCING BAR SHALL BE 2 INCHES UNLESS OTHERWISE NOTED OR SHOWN.
3345
3333
3599
3185
2920
2958
----20.4
19.8 20.4
19.7 20.4
19.7 20.4
19.6 -----
19.5 -----
2 -8
D=2
2 -9
D=6
2-11
8e1
5c1
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D=PIN DIAMETER.
PILE SIZE
REVI SED 1 0-1 1 - BAR LI ST HAD LENGTH I N THE NUMBER COLUMNS. CHANGED LENGTH TO SI ZE.
243-0
19
16
38
109 16
NOTE: FRICTION BEARING INCLUDES SIDE FRICTION AND END BEARING IN SOIL. POINT BEARING INCLUDES SIDE FRICTION AND POINT BEARING IN ROCK.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 0-1 1
H44-47-07
9/29/2011
2:41:48 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-47-07
11x17_pdf.pltcfg
6-10
6-10
6-10
6-10
6-10
6-10
A
6-10
3 1
6-10
5-7
3 1
4-4
6 2
4-4
6 2
4-4
| PIER
| ROADWAY
| BEARINGS 7
9
1 -7
SYMMETRICAL ABOUT THIS POINT THROUGH 180 ROTATION EXCEPT STEP ELEVATIONS 2-4(-)
TYPICAL PLAN
1 -7
NOTE: THE HEIGHT OF THE STEPS ON THE BRIDGE SEAT IS EQUAL TO THE DIFFERENCE IN ELEVATIONS OF THE TOP OF SLAB AT ADJACENT BEAMS ALONG | PIER. SEE SHEET H44-22-07 FOR "U" DIMENSION.
SYMMETRICAL ABOUT | PIER EXCEPT STEPS 2-8 GRADE ELEV. @ | PIER " U" " PREFORMED 1" PREFORMED a1 5c1 a2 EXPANSION 8e1 JOINT MATERIAL 1" 2 8 1 12 1-0 1-0 1-0 1-0 b1 b1 1-0 1-0 5 EQ. SPA. FOR 6-4 PILE SPACING 7-4 3-8 6-4 6-4 6-4 1-0 1-0 4 EQ. SPA. FOR 5-6 PILE SPACING 5-6 1-6 1 12 4 EQ. SPA. FOR 6-0 PILE SPACING 1-6 6-0 6 EQ. SPA. FOR 7-4 PILE SPACING 7-4 EXPANSION JOINT MATERIAL (TYP.)
8e1
a1
a2
5c1
3 -3
" 1
8 PILE BENT
CAP DEPTH I S 3 -6.
9 PILE BENT
3 EQ. SPA. 3 3 7 3 EQ. SPA. 2" CL. TOP OF PI LES 3 2 EQ. SPA. 3 3 7 2 EQ. SPA. TOP OF PI LES 1 -6 2" CL. 3 2" CL.
8e1
a1
a2
5c1
a1
5c1
a2
8e1
1 1
a1 8e1
1 1
2" CL.
3 -6
1 -0
3 -6
a2
1 -0
a2
1 1
1 12
b1 1-0 4 EQ. SPA. TYP. 1-0 TYP. 1-0 1-0 3 EQ. SPA.
b1
1 12
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR THE 1 4" PI LE OPTI ON &
2" CL.
5c1 3 4 3-3
1 1
b1
1 -6
b1
5c1 3 4 3-3
1-6
1-6
10 PILE BENT
VIEW A-A
FOR 12 PILE BENT
8e1
a1
a2
5c1
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 12
b1
LATEST REVI SI ON DATE
12 PILE BENT
H44-48-07
9/29/2011
2:41:50 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-48-07
11x17_pdf.pltcfg
23.5
23.5
23.5
23.5
23.5
3 -2
D=2
2 -9
D=6
2-11
8e1
5c1
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D=PIN DIAMETER.
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR THE 1 4" PI LE OPTI ON &
SEE SHEET H44-24-07 FOR STEP REINFORCING STEEL QUANTITIES AND DETAILS.
NOTE: FRICTION BEARING INCLUDES SIDE FRICTION AND END BEARING IN SOIL. POINT BEARING INCLUDES SIDE FRICTION AND POINT BEARING IN ROCK.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
H44-49-07
9/29/2011
2:41:52 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-49-07
11x17_pdf.pltcfg
SYMMETRICAL ABOUT | ROADWAY | BEAMS 2-0 6-10 6-10 6-10 TYP. 1-3 | PIER 1 -6 1 -6 6-10 5 5c4 5m1 5n1 a1 LOW STEP @ 3 @ 3 3 a2 1-3 TYP. 2x8 BEVELED KEY 5c1 5c4 45-0 9 6a3 9 @ 10 3 SP. 5c2 a1 5c3 2" CL. 9 4 a1 6-10 6-10 2-0 3 3-0
3 SP. 6
3 SP.
3 -0
| BEARINGS
3 5n1
3 EQ. SP.
CAP PLAN
- 138-10, 151-4, 163-10, 176-4, 188-10 5c2 - 6 SP. @ 9 = 4-6 - 201-4, 213-10
5c3
5c1
B
" U" 11 5c1 - 4 SPA. @ 1-10 7 7
6a4
BAR LAYOUT
1 1 1
a1 6a3
3-0
SECTION B-B
8b1 3
2 -6
H = HEI GHT OF PI ER
d1
6a4
H = 1 6TO 24
4e BARS @ 1 -0 CTRS.
4e BARS @ 1 -0 CTRS.
A
13-3 9-0
H = 25TO 40
4 -8 MI N.
| PIER
LAP
2 SP.
CONSTRUCTION JOINT
@ 9
D = DEPTH
PIER NOTES:
SEE "TEE PIER NOTES" ON H44-02-07 FOR NOTES REGARDING APPLICATION OF THESE PIER STANDARDS.
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR 1 -0 REINFORCING BAR SHALL BE 2 INCHES UNLESS OTHERWISE NOTED OR SHOWN. 1-6 TOP OF PILES DETAILS SEE FOOTING DETAILS 1-6 1-6 SEE FOOTING 1-6 ELIMINATE 2x8 BEVELED KEYWAY ON TOP OF CAP FOR EXPANSION PIERS.
FRONT ELEVATION
3 18 SPACES @ 10 = 15-0 19 d1 & d2 BARS EA. FACE d2 BARS d1
END ELEVATION
4e1
2" CL.
2 -6
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
4e2
5 EQUAL SPACES
LATEST REVI SI ON DATE
1 0
CLEAR d1 COLUMN
1 0
1 0
6 -6
1 0
SECTION A-A
H44-50-07
9/29/2011
2:41:55 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-50-07
11x17_pdf.pltcfg
| - | ABUT. BEARINGS 4 REI NFORCI NG STEEL BAR a1 a2 6a3 LENGTH 44-8 44-8 44-8 SHAPE
138-10
151-4
163-10
176-4
188-10
201-4
213-10
226-4
243-0
NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT 8 8 8 4 8 24 24 36 18 12 12 9 8 6 6 8 5 5 5 5 5 5 4958 29.9 1215 954 537 199 504 421 397 502 125 71 33 8 8 8 4 8 24 24 36 18 12 12 9 8 6 6 8 5 5 5 5 5 5 4958 29.9 1215 954 537 199 504 421 397 502 125 71 33 8 8 8 4 8 24 24 36 18 12 12 9 9 6 6 8 5 5 5 5 5 5 5219 29.9 1215 1215 537 199 504 421 397 502 125 71 33 8 8 8 4 8 24 24 36 18 12 12 9 9 6 6 8 5 5 5 5 5 5 5219 29.9 1215 1215 537 199 504 421 397 502 125 71 33 8 8 8 4 8 24 24 36 18 12 12 10 9 6 6 8 5 5 5 5 5 5 5542 29.9 1538 1215 537 199 504 421 397 502 125 71 33 8 8 8 4 8 24 28 36 18 12 12 10 10 6 6 8 5 5 5 5 5 5 5932 29.9 1538 1538 537 199 504 421 464 502 125 71 33 8 8 8 4 8 24 28 36 18 12 12 10 10 6 6 8 5 5 5 5 5 5 5932 29.9 1538 1538 537 199 504 421 464 502 125 71 33 8 8 8 4 8 24 40 36 18 12 12 11 10 6 6 8 5 5 5 5 5 5 6491 29.9 1899 1538 537 199 504 421 662 502 125 71 33 8 8 8 4 8 24 40 36 18 12 12 11 10 6 6 8 5 5 5 5 5 5 6491 29.9 1899 1538 537 199 504 421 662 502 125 71 33
2 -5
1 -8
D=6
D=2
2 -2
3 -4
D=2
10-3
13-1
5c1 16-10 5c2 VARIES 5c3 VARIES 5c4 5m1 6-8 5-8 2-8 TOTAL (LB.)
5c1 5c2
2-10
8b1
2-8
4e1
2 -2
3-9 TO 5-2
5c3 4
5n1
1 -6
D=2
5m1
COLUMN
REINFORCING STEEL H IN FEET 16 COLUMN HEIGHT STRUCTURAL CONCRETE (CY) NO. SIZE LENGTH WEIGHT NO. SIZE LENGTH WEIGHT NO. SIZE LENGTH WEIGHT 6-0 7-0 8-0 9-0 10-0 11-0 12-0 13-0 14-0 14-6 15-6 16-6 17-6 18-6 19-6 20-6 21-6 22-6 23-6 24-6 25-6 26-6 27-6 28-6 29-6 9.7 11.3 12.9 14.6 16.2 17.8 19.4 21.0 22.6 23.4 25.1 26.7 28.3 29.9 31.5 33.1 34.8 36.4 38.0 39.6 41.2 42.9 44.5 46.1 47.7 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 8-9 9-9 10-9 11-9 12-9 13-9 14-9 15-9 16-9 17-3 18-3 19-3 20-3 21-3 22-3 23-3 24-3 25-3 26-3 27-3 28-3 29-3 30-3 31-3 32-3 1369 1525 1681 1838 1994 2151 2307 2463 2620 2698 2854 3011 3167 3324 3480 3636 3793 3949 4106 4262 4418 4575 4731 4888 5044 14 16 18 20 22 24 26 28 30 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 11-11 111 127 143 159 175 191 207 223 239 239 255 271 287 302 318 334 350 366 382 398 414 430 446 462 478 28 32 36 40 44 48 52 56 60 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 13-10 259 296 333 370 407 444 481 517 554 554 591 628 665 702 739 776 813 850 887 924 961 998 1035 1072 1109 d1 BAR 4e1 BAR 4e2 BAR TOTAL WEIGHT (LB.) 1739 1948 2157 2367 2576 2786 2995 3203 3413 3491 3700 3910 4119 4328 4537 4746 4956 5165 5375 5584 5793 6003 6212 6422 6631
D=2
4e2
5c4
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D = PIN DIAMETER.
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
H44-51-07
9/29/2011
2:41:56 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-51-07
11x17_pdf.pltcfg
| PIER
1 1 SP.@ 1 0 = 9 -2
REINF.
d2 2" CL.
9 SP.@ 1 -0 = 9 -0
4 -8 MI N.
1 -6
1 0 - 5f2
# 9 BAR
f1 f2 g1
6
SYMM. ABOUT | PIER 6 23 SP. @ 1-0 = 23-0 24 - 5f1 24-0 SYMM. ABOUT | PIER
1 -6
3 -6
45 TYP.
TOP OF
g2 PI LE
CL. 1 -1
1 -0
3-6 x 10-0 x 24-0 FOR 21A, 22A & 23A TYPICAL SECTION
5
7 -0
8g2 D=9
9 SP.@ 1 -0 = 9 -0 1 1 SP.@ 1 0 = 9 -2
BOTT. FTG.
1 2 - 8g 2
3 -6
8g1
REINF.
1 -6
1 0 - 5f2
1-7
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
SYMM. ABOUT | PIER 6 23 SP. @ 1-0 = 23-0 24 - 5f1 24-0 SYMM. ABOUT | PIER
1 -6
REINF.
3 -6
45 TYP.
FOOTING NOTES:
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP d2 BARS BATTER PILES IN EXTERIOR ROWS 1:4 IN THE DIRECTION SHOWN. AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-50-07.
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING d1 5 EQUAL SPACES | PIER 4e1 4 - d1 & d2 BARS ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER OF ADJACENT PILING SHALL NOT EXCEED 8-0.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1342 242 247 800 758 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. 3389 31.1 1 FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD. CONCRETE (CY) WEIGHT (LB.) SYMMETRICAL ABOUT | ROADWAY 1 1 -09 TOTAL
d2 f1 3-6 x 10 x 24 f2 g1 g2
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-50-07.)
H44-52-07
9/29/2011
2:41:59 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-52-07
11x17_pdf.pltcfg
1 0 -0
1 0 -0
1 -6
| PIER
1 1 SP.@ 1 0 = 9 -2
9g1
9 SP.@ 1 -0 = 9 -0
4 -8 MI N.
d2 2" CL.
1 0 SP.@ 1 -0 = 1 0 -0
1 0 -0
1 -6
1 0 - 5f2
# 9 BAR
24B, 25B 1 -6
f1 f2 g1
6
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 25-0 SYMM. ABOUT | PIER
45
6
CL. 1 -1
1 -0
TYP.
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
1 -6
5f2
4 -0
1 1 - 5f2
3 -6
45 TYP.
TOP OF
g2 PI LE
4-0 x 10-0 x 25-0 FOR 22B, 23B, 24B, 25B & 26A TYPICAL SECTION
7 27 SP. @ 11 = 24-9 28 - 9g1
5
1 -6
9g2
1 1 SP.@ 1 0 = 9 -2
9g2 BOTT. FTG. 3 -6 REINF. OMIT ON 22C, 24C, 26B OMIT ON 22C, 23C
1 1 SP.@ 1 1 = 1 0 -1
H IN FT. 37 TO 40 34 TO 36 31 TO 33 28 TO 30 25 TO 27
| - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 22B 22B 24B 25B 22B 23B 24B 26A 22C 23C 24C 26B 22D 23D 24D 26C 22D 23D 25C 26C
1 0 -0
BRG. (TONS) 49 50 50 50 49 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50
1 0 SP.@ 1 -0 = 1 0 -0
FOOTING SIZE
9 SP.@ 1 -0 = 9 -0
1 DES.
2 LRFD
1 2 - 9g 2
PILING (HP10x57)
9g1
1 -6
1 0 - 5f2
1 -6
143 143 144 4 x 10 x 26 145 143 144 144 4 x 11 x 26 145 143 146 147 4 x 11 x 26 143
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
45
6
TYP.
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
1 -6
5f2
REINF.
4 -0
4 x 10 x 25
1 1 - 5f2
3 -6
45 TYP.
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
4-0 x 11-0 x 26-0 FOR 24D, 25C & 26C FOOTING NOTES:
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP
145
REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1421 252 257 920 790 1421 262 3640 37.0 TOTAL WEIGHT (LB.) | PIER CONCRETE (CY)
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE d1 5 EQUAL SPACES 4 - d1 & d2 BARS 4e1 4e2 OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER OF ADJACENT PILING SHALL NOT EXCEED 8-0.
d2 f1 4 x 10 x 25 f2 g1 g2 d2 f1 4 x 10 x 26 f2 g1 g2 d2 f1 4 x 11 x 26 f2 g1 g2
46 - #9 AS SHOWN 25 - #5 @ 1-0 10 - #5 @ 1-0 28 - #9 @ 0-10 12 - #8 @ 0-10 46 - #9 AS SHOWN 26 - #5 @ 1-0 10 - #5 @ 1-0 28 - #9 @ 0-11 12 - #9 @ 0-10 46 - #9 AS SHOWN 26 - #5 @ 1-0 11 - #5 @ 1-0 31 - #9 @ 0-10 12 - #9 @ 0-11
9-1 9-8 24-8 9-8 24-8 9-1 9-8 25-8 9-8 25-8 9-1 10-8 25-8 10-8 25-8
7 -6
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
D=9
LATEST REVI SI ON DATE
1-7
1 1 -09
268
3918
38.5
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-50-07.)
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
H44-53-07
9/29/2011
2:42:01 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-53-07
11x17_pdf.pltcfg
1 1 -0
1 1 -0
1 1 SP.@ 8 = 7 -4
| PIER
7 SP.@ 1 -0 = 7 -0
7g2 7g1
1 2 - 7g 2
8 - 5f2
2 -6
1 -6
4 -8 MI N.
d2 2" CL.
5f1 5f2
# 9 BAR
f1 f2 g1
SYMM. ABOUT | PIER 6 21 SP. @ 1-0 = 21-0 22 - 5f1 SYMM. ABOUT | PIER
2 -6
45 TYP.
TOP OF
g2 PI LE
CL. 1 -1
1 -0
22-0
TYPICAL SECTION
1 1 SP.@ 8 = 7 -4
7g2 7g1
1 2 - 7g 2
7 SP.@ 1 -0 = 7 -0
7 -0
8 - 5f2
2 -6
1 -6
D=9
5f1 5f2
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
SYMM. ABOUT | PIER 6 21 SP. @ 1-0 = 21-0 22 - 5f1 22-0 SYMM. ABOUT | PIER
1 -6
1-7
2 -6
45 TYP.
FOOTING NOTES:
PILING (HP10x57) H IN FT. 22 TO 24 1 9 TO 21 1 6 TO 1 8 | - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 14A 15A 16A 16A 15A 15A 16A 17A 15A 16A 16A 17A 1 DES. BRG. (TONS) 75 74 73 75 73 75 74 75 74 72 75 75 2 LRFD DES. BRG. (KIPS) 220 2" CL. 214 3-6 x 8 x 22 210 219 210 218 3-6 x 8 x 22 214 215 213 208 3-6 x 8 x 22 217 218 4e2
APPROVED BY BRI DGE ENGI NEER
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-50-07.
d2 BARS
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER OF ADJACENT PILING SHALL NOT EXCEED 8-0. d1 5 EQUAL SPACES
| PIER 4e1
4 - d1 & d2 BARS
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1342 176 181 470 531 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. 2700 22.8 1 FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD. CONCRETE (CY) WEIGHT (LB.) SYMMETRICAL ABOUT | ROADWAY 1 1 -09 TOTAL
d2 f1 3-6 x 8 x 22 f2 g1 g2
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-50-07.)
H44-54-07
9/29/2011
2:42:04 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-54-07
11x17_pdf.pltcfg
8 -0
8 -0
5 | PIER
4 -8 MI N.
1 -6
d2
1 1 SP.@ 8 = 7 -4
2" CL.
1 2 - 8g 2
2 -6
7g1
1 1 SP.@ 9 = 8 -3
8g2
BOTT. FTG.
8g2 8g1
1 2 - 8g 2
7 SP.@ 1 -0 = 7 -0
8 SP.@ 1 -0 = 8 -0
8 - 5f2
8 -0
1 -6
# 9 BAR
f2
g1
1 -6
OMIT ON 15C
CL. 1 -1
1 -0
SYMM. ABOUT | PIER 6 22 SP. @ 1-0 = 22-0 23 - 5f1 23-0 SYMM. ABOUT | PIER
45
6
TOP OF
TYP.
g2 PI LE
SYMM. ABOUT | PIER 6 22 SP. @ 1-0 = 22-0 23 - 5f1 23-0 SYMM. ABOUT | PIER
1 -6
3 -0
f1
9 - 5f2
2 -6
45 TYP.
TYPICAL SECTION
4-0 x 8-0 x 23-0 FOR 15B, 16B & 17B 4-0 x 9-0 x 23-0 FOR 15C, 16C, 17C & 18A
6 25 SP. @ 11 = 23-11 26 - 8g1
4
2-3
4-4
4-4
1-6
1 1 SP.@ 9 = 8 -3
9g2
1 2 - 9g 2
8g1
8 SP.@ 1 -0 = 8 -0
1 -6
IN FT. 37 TO 40 34 TO 36 31 TO 33 28 TO 30 25 TO 27
ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0
NO. & LAYOUT 15B 16B 16B 17B 15C 16C 16C 17C 15C 16C 16C 18A 15D 16D 16D 18B 15D 16D 17D 18B
FOOTING SIZE 7 -6
OMIT ON 15D
4 x 8 x 23 218 219 213 207 4 x 9 x 23 217 218 216 210 4 x 9 x 23 219 212 214 208 4 x 9 x 25 217 209 218 212 4 x 9 x 25 213 1-7
D=9
6
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 SYMM. ABOUT | PIER
1 -6
3 -0
PILING (HP10x57) | - |
9 - 5f2
45 TYP.
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
25-0
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR A 75 TON STEEL PI LLI NG OPTI ON.
FOOTING NOTES:
18 SP. @ 10 = 15-0 19 - d1 & d2 BARS EA. FACE THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-50-07. d2 2" CL. BARS BATTER PILES IN EXTERIOR ROWS 1:4 IN THE DIRECTION SHOWN.
213
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER d1 5 EQUAL SPACES OF ADJACENT PILING SHALL NOT EXCEED 8-0.
REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1421 184 189 376 726 1421 2896 27.3 TOTAL WEIGHT (LB.) | PIER CONCRETE (CY)
d2 f1 4 x 8 x 23 f2 g1 g2 d2 f1 4 x 9 x 23 f2 g1 g2 d2 f1 4 x 9 x 25 f2 g1 g2
46 - #9 AS SHOWN 23 - #5 @ 1-0 8 - #5 @ 1-0 24 - #7 @ 0-11 12 - #8 @ 0-8 46 - #9 AS SHOWN 23 - #5 @ 1-0 9 - #5 @ 1-0 26 - #8 @ 0-10 12 - #8 @ 0-9 46 - #9 AS SHOWN 25 - #5 @ 1-0 9 - #5 @ 1-0 26 - #8 @ 0-11 12 - #9 @ 0-9
9-1 7-8 22-8 7-8 22-8 9-1 8-8 22-8 8-8 22-8 9-1 8-8 24-8 8-8 24-8
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
208 1 1 -09 213 602 726 1421 226 232 602 1006 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. 3487 33.3 1 FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD. 3170 30.7 SYMMETRICAL ABOUT | ROADWAY
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-50-07.)
H44-55-07
9/29/2011
2:42:06 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-55-07
11x17_pdf.pltcfg
9 -0
9 -0
7 | PIER
3
4 -8 MI N.
4 -6
8 -6;1 3 - 7g 2
8 SP.@ 1 -0 =
8 SP.@ 1 -0 =
8 -0;9 - 5f2
1 2 SP.@ 8
1 3 SP.@ 7
8 -0;9 - 5f2
REINFORCING
6g1
8 -1 ;1 4 - 9g 2
7g2
7g1
9g2
REINFORCING
2" CL.
9 -0
4 -6 6 3 5 -0 6 4 -6
d2
BOTT. FOOTING
BOTT. FOOTING
# 9 BAR
5f1
4 -6
5f1
f1 f2
1 -0
3" CL.
g1
g2
H IN FT.
| - | ABUT. BRG.
8 -2;1 5 - 8g 2 8 -0;9 - 5f2
FOOTING SIZE 4 -6
= 9 -6
BOTT. FOOTING
8 SP.@ 1 -0 = 1 4 SP.@ 7 =
138-10 151-4 1 6 TO 1 8 163-10 176-4 3-6 x 9 x 27 188-10 201-4 3-6 x 9 x 29 213-10 226-4 243-0 138-10 151-4 1 9 TO 21 163-10 176-4 188-10 201-4 213-10 226-4 3-6 x 10 x 29 243-0 138-10 151-4 22 TO 24 163-10 176-4 188-10 201-4 213-10 226-4 3-6 x 10 x 29 243-0 3-6 x 9 x 29 3-6 x 9 x 27 1-7 3-6 x 9 x 25 3-6 x 9 x 29 3-6 x 9 x 27 3-6 x 9 x 25 3-6 x 10 x 29 3-6 x 9 x 25
7g1
8g2
BOTT. FOOTING
10g2
9 SP.@ 1 -0 =
9 -0;1 0 - 5f2
REINFORCING
8g1
1 3 - 1 0g 2
REINFORCING
9 -0
5f1
REINFORCING
5f2
5f1
6
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
REINFORCING STEEL (ONE FOOTING) STRUCTURAL REVI SED 04-1 2 - EXCAVATI ON LI MI T WAS CHANGED TO 3 -0. FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1473 2" CL. 226 232 404 655 1473 244 250 496 1068 1473 4e2 3531 31.5 | PIER 4e1 d1 5 EQUAL SPACES 4 - d1 & d2 BARS 2990 29.2 TOTAL WEIGHT (LB.) d2 BARS CONCRETE (CY) 18 SP. @ 10 = 15-0 19 - d1 & d2 BARS EA. FACE
FOOTING NOTES:
THESE SPREAD FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-50-07.
46 - #9 AS SHOWN 25 - #5 @ 1-0 9 - #5 @ 1-0 31 - #6 @ 0-9 13 - #7 @ 0-8 46 - #9 AS SHOWN 27 - #5 @ 1-0 9 - #5 @ 1-0 28 - #7 @ 0-11 15 - #8 @ 0-7 46 - #9 AS SHOWN 29 - #5 @ 1-0 9 - #5 @ 1-0 31 - #7 @ 0-11 14 - #9 @ 0-7 46 - #9 AS SHOWN 29 - #5 @ 1-0 10 - #5 @ 1-0 32 - #8 @ 0-11 13 - #10 @ 0-9
9-5 8-8 24-8 8-8 24-8 9-5 8-8 26-8 8-8 26-8 9-5 8-8 28-8 8-8 28-8 9-5 9-8 28-8 9-8 28-8
THESE SPREAD FOOTINGS SHALL EXTEND AT LEAST 6 INCHES INTO SUITABLE FOUNDATION ROCK AND THE LAST 6 INCHES OF ROCK EXCAVATION SHALL BE TO NEAT LINES OF MASONRY. THE FOUNDATION ROCK SHALL HAVE A MINIMUM LRFD NOMINAL BEARING RESISTANCE OF 30 kips PER SQUARE FOOT (ALLOWABLE BEARING VALUE OF AT LEAST 5 TONS PER SQUARE FOOT).
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
262 269 549 1365 1473 292 299 826 1604 4494 37.6 SYMMETRICAL ABOUT | ROADWAY 3918 33.8 04-1 2
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-50-07.)
H44-56-07
3/28/2012
8:42:16 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-56-07
11x17_pdf.pltcfg
5 -0
TOP FOOTING
1 2 SP.@ 9
4 -6
1 0 -0
9 -0
H IN FT.
4 -6
8 -2;1 5 - 6g 2
8 SP.@ 1 -0 =
8 SP.@ 1 -0 =
25 TO 27
8 -0;9 - 5f2
8 -0;9 - 5f2
163-10
6g1
8 -2;1 5 - 9g 2
1 4 SP.@ 7 =
1 4 SP.@ 7 =
6g2
9g2
REINFORCING
9 -0
4 -6 6 6 4 -6 6 6 5 -0 6 4 -6 4 -6
151-4
BOTT. FOOTING
5f1
4 -6
5f1
4 x 9 x 25
28 TO 30
4 x 9 x 27
4 x 9 x 29
4 x 9 x 31
4 x 10 x 31 4 x 9 x 25 4 x 9 x 27
3
31 TO 33
163-10 176-4 4 x 9 x 29
8 -1 ;1 6 - 9g 2
8 -6;1 3 - 8g 2
8 SP.@ 1 -0 =
8 SP.@ 1 -0 =
8 -0;9 - 5f2
213-10 226-4 4 x 10 x 31 4 -8 MI N. 243-0 138-10 151-4 34 TO 36 163-10 176-4 4 x 9 x 29 188-10 201-4 4 x 9 x 31 213-10 226-4 4 x 10 x 31 243-0 138-10 4 x 9 x 27 151-4 37 TO 40 163-10 3" CL. 176-4 188-10 201-4 213-10 226-4 243-0 4 x 10 x 31 4 x 9 x 31 4 x 9 x 29 # 9 BAR 4 x 9 x 27 d2 2" CL.
1 2 SP.@ 8
1 5 SP.@ 6
4 x 9 x 31
8 -0;9 - 5f2
201-4
| PIER
6g1
REINFORCING
8g2
4 -6
188-10
BOTT. FOOTING
9g2
9 -0
5f1
4 -6
5f1
f1 f2
1 -0
g1
g2
1 4 SP.@ 8 = 9 -4
BOTT. FOOTING
1 5 - 1 0g 2
10g2
8g1
REINFORCING
THESE SPREAD FOOTINGS SHALL EXTEND AT LEAST 6 INCHES INTO SUITABLE REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1551 226 232 364 556 2929 33.3 TOTAL WEIGHT (LB.) CONCRETE (CY) FOUNDATION ROCK AND THE LAST 6 INCHES OF ROCK EXCAVATION SHALL BE TO NEAT LINES OF MASONRY. THE FOUNDATION ROCK SHALL HAVE A MINIMUM LRFD NOMINAL BEARING RESISTANCE OF 30 kips PER SQUARE FOOT (ALLOWABLE BEARING VALUE OF AT LEAST 5 TONS PER SQUARE FOOT).
1 0 - 5f2
46 - #9 AS SHOWN 25 - #5 @ 1-0 9 - #5 @ 1-0 28 - #6 @ 0-10 15 - #6 @ 0-7 46 - #9 AS SHOWN 27 - #5 @ 1-0 9 - #5 @ 1-0 31 - #6 @ 0-10 13 - #8 @ 0-8 46 - #9 AS SHOWN 29 - #5 @ 1-0 9 - #5 @ 1-0 34 - #6 @ 0-10 15 - #9 @ 0-7 46 - #9 AS SHOWN 31 - #5 @ 1-0 9 - #5 @ 1-0 37 - #6 @ 0-10 16 - #9 @ 0-6 46 - #9 AS SHOWN 31 - #5 @ 1-0 10 - #5 @ 1-0 31 - #8 @ 1-0 15 - #10 @ 0-8
9-11 8-8 24-8 8-8 24-8 9-11 8-8 26-8 8-8 26-8 9-11 8-8 28-8 8-8 28-8 9-11 8-8 30-8 8-8 30-8 9-11 9-8 30-8 9-8 30-8
6 1551 244 250 404 926 1551 262 269 443 1462 1551 280 288 482 1668 1551 313 320 800 1979 4963 45.9 SYMMETRICAL ABOUT | ROADWAY 1-7 4269 41.3 4e2 3987 38.7 | PIER 4e1 8 -4 d1 5 EQUAL SPACES 4 - d1 & d2 BARS
APPROVED BY BRI DGE ENGI NEER
3375
36.0
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
D=9 04-1 2
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-50-07.)
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
H44-57-07
3/28/2012
8:41:49 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-57-07
11x17_pdf.pltcfg
5 -0
1 0 -0
9 -0
9 -0
| BEAMS 2-3 2x8 BEVELED KEY 1 -7 8 | PIER | ROADWAY 7-0 7-0 7-0 7-0 | PIER 5c4 a1 7-0 7-0 2-3
3 -2
1 -7
3-2
3 8
. P Y 3 T 1 3 31 1 . P Y T
3 SP. @4
3 SP. @4
| BEARINGS
15 5c4 47-0
SYMMETRICAL ABOUT THIS POINT THROUGH 180 ROTATION EXCEPT STEP ELEVATIONS
CAP PLAN
a2 5c1 9 9 6a3
5c2 - 4 SP. @ 1-0 = 4-0 - 138-10, 151-4, 163-10, 176-4, 188-10 5c2 - 6 SP. @ 8 = 4-0 - 201-4, 213-10, 226-4, 243-0 GRADE ELEV. AT PIER 9
a1
B
SHIFT 5c1 BARS TO CLEAR d1 COLUMN BARS ALL SPANS 11 5c4 - 3 SP. @ 1-10 6a3 a1 a2 3 5c1 4 -0 5c4 5c3 2" CL. 5c3 d1 2 -9 2 -9 2-1 8b1 LAP 4 5c2 3 3 8b1 1 -1 3-2 6a4 " U" 5c1 - 4 SP. @ 1-10 10 8 8 8 SP. @ 1-0 = 8-0 6 1 -0 9 NOTE: 2 SP. @ 8 2" CL.
H = HEI GHT OF PI ER
4e BARS @ 1 -0 CTRS.
SECTION B-B
CONSTRUCTION 4 2-6 4 JOINT
A B
13-9 9-6
4 -8 MI N.
4e BARS @ 1 -0 CTRS.
6a4
8b1
H = 1 6TO 24
| PIER
@ 1 0
4e2 4e3
2 SP.
LAP
SYMMETRICAL ABOUT
4e1
CONSTRUCTION JOINT
D = DEPTH
PIER NOTES:
SEE "TEE PIER NOTES" ON H44-02-07 FOR NOTES REGARDING APPLICATION OF THESE PIER STANDARDS.
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE TO NEAR 1 -0 REINFORCING BAR SHALL BE 2 INCHES UNLESS OTHERWISE NOTED OR SHOWN. 1-6 TOP OF PILES DETAILS SEE FOOTING DETAILS 1-6 1-6 SEE FOOTING 1-6 ELIMINATE 2x8 BEVELED KEYWAY ON TOP OF CAP FOR EXPANSION PIERS.
2" CL.
d2 BARS
4e1
d1
APPROVED BY BRI DGE ENGI NEER
2 -6
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
| PIER 1-3
1 1 -09
4e3
6 -9
SECTION A-A
H44-58-07
9/29/2011
2:42:13 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-58-07
11x17_pdf.pltcfg
| - | ABUT. BEARINGS 4 REI NFORCI NG STEEL BAR a1 a2 6a3 LENGTH 46-8 46-8 46-8 SHAPE
138-10
151-4
163-10
176-4
188-10
201-4
213-10
226-4
243-0
NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT 8 8 8 4 8 30 20 36 16 9 8 6 6 8 5 5 5 5 1269 997 561 220 527 548 343 517 115 8 8 8 4 8 30 20 36 16 9 8 6 6 8 5 5 5 5 1269 997 561 220 527 548 343 517 115 8 8 8 4 8 30 20 36 16 9 9 6 6 8 5 5 5 5 1269 1269 561 220 527 548 343 517 115 8 8 8 4 8 30 20 36 16 9 9 6 6 8 5 5 5 5 1269 1269 561 220 527 548 343 517 115 8 8 8 4 8 30 20 36 16 10 9 6 6 8 5 5 5 5 1606 1269 561 220 527 548 343 517 115 8 8 8 4 8 30 28 36 16 10 9 6 6 8 5 5 5 5 1606 1269 561 220 527 548 481 517 115 8 8 8 4 8 30 28 36 16 10 10 6 6 8 5 5 5 5 1606 1606 561 220 527 548 481 517 115 8 8 8 4 8 30 28 36 16 10 10 6 6 8 5 5 5 5 1606 1606 561 220 527 548 481 517 115 8 8 8 4 8 30 28 36 16 11 10 6 6 8 5 5 5 5 1984 1606 561 220 527 548 481 517 115
2 -8
1 -1 0
D=6
D=2
2 -2
3 -4
D=2
10-9
13-7
5c1 5c2 4
2-9
8b1
4e1
2 -2
3-9 TO 5-4
5c3 1 4 TOTAL (LB.) 5097 34.1 5097 34.1 5369 34.1 5369 34.1 5706 34.1 5844 34.1 6181 34.1 6181 34.1 6559 34.1
COLUMN
4e2 H 4e3 IN FEET COLUMN HEIGHT STRUCTURAL CONCRETE (CY) NO. SIZE LENGTH WEIGHT NO. SIZE LENGTH WEIGHT NO. SIZE LENGTH WEIGHT NO. SIZE LENGTH WEIGHT 9.8 11.5 13.2 15.0 16.7 18.4 20.1 21.8 23.5 24.4 26.1 27.8 29.5 31.2 32.9 34.6 36.3 38.0 39.7 41.5 43.2 44.9 46.6 48.3 50.0 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 8-6 9-6 10-6 11-6 12-6 13-6 14-6 15-6 16-6 17-0 18-0 19-0 20-0 21-0 22-0 23-0 24-0 25-0 26-0 27-0 28-0 29-0 30-0 31-0 32-0 1387 1550 1714 1877 2040 2203 2366 2530 2693 2774 2938 3101 3264 3427 3590 3754 3917 4080 4243 4406 4570 4733 4896 5059 5222 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 11-10 95 111 126 142 158 174 190 206 221 237 253 269 285 300 316 332 348 364 379 395 411 427 443 458 474 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 15-9 126 147 168 189 210 231 253 274 295 316 337 358 379 400 421 442 463 484 505 526 547 568 589 610 631 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 14-0 112 131 150 168 187 206 224 243 262 281 299 318 337 355 374 393 411 430 449 468 486 505 524 542 561 d1 BAR 4e1 BAR 4e2 BAR 4e3 BAR TOTAL WEIGHT (LB.) 1720 1939 2158 2376 2595 2814 3033 3253 3471 3608 3827 4046 4265 4482 4701 4921 5139 5358 5576 5795 6014 6233 6452 6669 6888 REINFORCING STEEL
5c4
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D = PIN DIAMETER.
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
5-9 6-9 7-9 8-9 9-9 10-9 11-9 12-9 13-9 14-3 15-3 16-3 17-3 18-3 19-3 20-3 21-3 22-3 23-3 24-3 25-3 26-3 27-3 28-3 29-3
1 SEE SHEET H44-17-07 FOR STEP REINFORCING STEEL QUANTITIES AND DETAILS.
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
H44-59-07
9/29/2011
2:42:15 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-59-07
11x17_pdf.pltcfg
10
| PIER
4
1 -6
4 -8 MI N.
d2
1 1 SP.@ 9 = 8 -3
9g2 3 -0 REINF.
1 0 SP.@ 1 1 = 9 -2
2" CL.
8 SP.@ 1 -0 = 8 -0
REINF.
9 SP.@ 1 -0 = 9 -0
9 - 5f2
9 -0
1 -6
# 9 BAR
f2
g1
5f1 5f2
OMIT ON 22A
1 -6
5f1 5f2
CL. 1 -1
1 -0
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 25-0 SYMM. ABOUT | PIER
45
6
TOP OF
TYP.
g2 PI LE
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
3 -6
f1
1 0 - 5f2
3 -0
45 TYP.
TYPICAL SECTION
3-6 x 9-0 x 25-0 FOR 22A, 24A & 25A 3-6 x 10-0 x 26-0 FOR 22B & 23A
7 27 SP. @ 11 = 24-9 28 - 9g1
5
2-10
2-10
2-10
2-10
1-6
9g2 7 -0
1 0 SP.@ 1 1 = 9 -2
REINF.
D=9
9 SP.@ 1 -0 = 9 -0
1 -6
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
5f1 5f2
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 SYMM. ABOUT | PIER
1 -6
3 -6
1-7
1 0 - 5f2
45 TYP.
PILING (HP10x57) H IN FT. 22 TO 24 1 9 TO 21 1 6 TO 1 8 REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS. | - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 22A 22A 24A 25A 22B 22B 24B 25B 22B 23A 24B 26A 1 DES. BRG. (TONS) 49 50 50 50 49 50 49 50 50 50 50 50 2 LRFD DES. BRG. (KIPS) 140 146 3-6 x 9 x 25 143 145 140 146 3-6 x 10 x 26 2" CL. 142 145 143 144 3-6 x 10 x 26 145 143 | PIER REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1401 SYMMETRICAL 3389 29.2 1 1 -09 ABOUT | PIER
LATEST REVI SI ON DATE
26-0
FOOTING SIZE
3-6 x 10-0 x 26-0 FOR 24B, 25B & 26A FOOTING NOTES:
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-58-07. d2 BARS
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER d1 5 EQUAL SPACES 4 - d1 & d2 BARS 4e1 OF ADJACENT PILING SHALL NOT EXCEED 8-0.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
d2 f1 3-6 x 9 x 25 f2 g1 g2 d2 f1 3-6 x 10 x 26 f2 g1 g2
48 - #9 AS SHOWN 25 - #5 @ 1-0 9 - #5 @ 1-0 32 - #8 @ 0-9 12 - #8 @ 0-9 48 - #9 AS SHOWN 26 - #5 @ 1-0 10 - #5 @ 1-0 28 - #9 @ 0-11 11 - #9 @ 0-11
8-7 8-8 24-8 8-8 24-8 8-7 9-8 25-8 9-8 25-8
226 232 740 790 1401 262 268 920 960 2 3811 33.7 1
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-58-07.)
H44-60-07
9/29/2011
2:42:17 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-60-07
11x17_pdf.pltcfg
1 0 -0
1 0 -0
10
| PIER
3
1 -6
4 -8 MI N.
d2
1 2 SP.@ 1 0 = 1 0 -0
8g2
= 1 0 -0
2 -6
2" CL.
8g1
1 3 - 8g 2
REINF.
1 0 SP.@ 1 -0 = 1 0 -0
1 0 SP.@ 1 -0 = 1 0 -0
1 -3 1 -3
1 6 SP.@ 7
1 -3 1 -3
1 0 -6
2 -6
1 -6
# 9 BAR
f1 f2 g1
1 1 - 5f2
2 -6
1 1 - 5f2
5f1
CL. 1 -1
1 -0
1 -6
TOP OF
PI LE
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 SYMM. ABOUT | PIER
g2
45 TYP.
SYMM. ABOUT | PIER 6 26 SP. @ 1-0 = 26-0 27 - 5f1 SYMM. ABOUT | PIER
1 -6
2 -6
45 TYP.
TYPICAL SECTION
25-0
27-0
1-7
3-1
3-1
3-1
1-6
1-9
3-5
3-5
3-5
1-6
9 1 -6 1 -6
8g2 1-7
1 2 SP.@ 1 0 = 1 0 -0
8g2
= 1 0 -0
BOTT. FTG.
1 7 - 8g 2
8g1
REINF.
1 0 SP.@ 1 -0 = 1 0 -0
1 0 SP.@ 1 -0 = 1 0 -0
1 6 SP.@ 7
1 -3 1 -3
1 -3 1 -3
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
1 0 -6
2 -6
1 1 - 5f2
2 -6
H IN FT. 37 TO 40 34 TO 36 31 TO 33 28 TO 30 25 TO 27
| - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 22C 23B 24C 25C 22D 23C 24D 25D 22D 23C 24D 25D 22D 24D 24D 26B 23C 24D 25D 26B
FOOTING SIZE
5f1
1 -6
142 144 142 143 4 x 10-6 x 27 142 143 144 145 4 x 10-6 x 27 144 145 146 140 4 x 10-6 x 27 142 145 142 4 x 10-6 x 27 144 145 6
SYMM. ABOUT | PIER 24 SP. @ 1-0 = 24-0 25 - 5f1 25-0 SYMM. ABOUT | PIER
4 x 10-6 x 25
45 TYP.
SYMM. ABOUT | PIER 6 26 SP. @ 1-0 = 26-0 27 - 5f1 27-0 SYMM. ABOUT | PIER
1 -6
2 -6
PILING (HP10x57)
1 1 - 5f2
45 TYP.
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
4-0 x 10-6 x 27-0 FOR 24D, 25D & 26B 4-0 x 10-6 x 25-0 FOR 24C & 25C FOOTING NOTES:
19 SPA. @ 10 = 16-2 THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP 20 - d1 & d2 BARS EA. FACE AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-58-07.
2" CL.
145
d2 BARS
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER d1 5 EQUAL SPACES 4 - d1 & d2 BARS 4e1 OF ADJACENT PILING SHALL NOT EXCEED 8-0.
| PIER REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1482 SYMMETRICAL TOTAL WEIGHT (LB.) CONCRETE (CY) 4e3 4e2
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
d2 f1 4 x 10-6 x 25 f2 g1 g2 d2 f1 4 x 10-6 x 27 f2 g1 g2
48 - #9 AS SHOWN 25 - #5 @ 1-0 11 - #5 @ 1-0 33 - #8 @ 0-9 13 - #8 @ 0-10 48 - #9 AS SHOWN 27 - #5 @ 1-0 11 - #5 @ 1-0 33 - #8 @ 0-9 17 - #8 @ 0-7
9-1 10-2 24-8 10-2 24-8 9-1 10-2 26-8 10-2 26-8
265 283 896 856 1482 286 306 896 1210 2 4180 42.0 1 3782 38.9
1 1 -09
ABOUT | PIER
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-58-07.)
H44-61-07
9/29/2011
2:42:19 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-61-07
11x17_pdf.pltcfg
1 0 -6
1 0 -6
| PIER
4
4 -8 MI N.
7 SP.@ 1 -0 = 7 -0
1 1 SP.@ 8 = 7 -4
d2 2" CL.
8g2 7g1
1 2 - 8g 2
8 - 5f2
2 -6
1 -6
# 9 BAR
f1 f2 g1
5f1 5f2
CL. 1 -1
1 -0
SYMM. ABOUT | PIER 6 23 SP. @ 1-0 = 23-0 24 - 5f1 24-0 SYMM. ABOUT | PIER
1 -6
2 -6
45 TYP.
TOP OF
g2 PI LE
TYPICAL SECTION
6
2-2
4-2
4-2
1-6
7 SP.@ 1 -0 = 7 -0
1 1 SP.@ 8 = 7 -4
8g2 7g1
1 2 - 8g 2
8 - 5f2
2 -6
1 -6
7 -0
D=9
5f1 5f2
1-7
6
SYMM. ABOUT | PIER 6 23 SP. @ 1-0 = 23-0 24 - 5f1 SYMM. ABOUT | PIER
2 -6
45 TYP.
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
24-0
FOOTING NOTES:
PILING (HP10x57) H IN FT. 22 TO 24 1 9 TO 21 1 6 TO 1 8 | - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 15A 15A 16A 16A 15A 15A 16A 17A 15A 16A 16A 18A 1 DES. BRG. (TONS) 72 75 73 75 73 75 75 75 75 73 75 74 2 LRFD DES. BRG. (KIPS) 207 3-6 x 8 x 24 211 220 212 220 3-6 x 8 x 24 215 216 216 210 3-6 x 8 x 24 4e3 4e2
APPROVED BY BRI DGE ENGI NEER
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP FOOTING SIZE 19 SPA. @ 10 = 16-2 20 - d1 & d2 BARS EA. FACE BATTER PILES IN EXTERIOR ROWS 1:4 IN THE DIRECTION SHOWN. 2" CL. d2 BARS AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-58-07.
215
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER OF ADJACENT PILING SHALL NOT EXCEED 8-0.
219 212
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1401 192 197 470 758 2 3018 24.9 1 TOTAL WEIGHT (LB.) CONCRETE (CY)
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-58-07.)
d2 f1 3-6 x 8 x 24 f2 g1 g2
H44-62-07
9/29/2011
2:42:22 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-62-07
11x17_pdf.pltcfg
8 -0
8 -0
| PIER
4
1 -6
4 -8 MI N.
1 1 SP.@ 9 = 8 -3
1 1 SP.@ 9 = 8 -3
d2 2" CL.
8g2 8g1
1 2 - 8g 2
9g2 8g1
1 2 - 9g 2
8 SP.@ 1 -0 = 8 -0
8 SP.@ 1 -0 = 8 -0
9 -0
1 -6
9 - 5f2
# 9 BAR
3 -0
9 - 5f2
f1 f2 g1
OMIT ON 15B
OMIT ON 15C
1 -6
CL. 1 -1
1 -0
SYMM. ABOUT | PIER 6 23 SP. @ 1-0 = 23-0 24 - 5f1 24-0 SYMM. ABOUT | PIER
45 TYP.
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
1 -6
3 -0
45 TYP.
TOP OF
g2 PI LE
TYPICAL SECTION
2-4
4-7
4-7
1-6
9g2
= 9 -6
BOTT. FTG.
1 3 - 9g 2
9 SP.@ 1 -0 = 9 -0
1 2 SP.@ 9
3 -6
8g1
REINF.
1 -6
H IN FT. 37 TO 40 34 TO 36 31 TO 33 28 TO 30 25 TO 27
PILING (HP10x57) | - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 15B 16B 16B 18B 15C 16C 16C 18C 15C 16C 17B 18C 15D 16D 17C 18D 16D 16D 17C 18D 1 DES. BRG. (TONS) 75 73 75 74 74 72 75 73 75 73 74 74 75 74 74 74 72 75 75 75 2 LRFD DES. BRG. (KIPS) 217 210 4 x 9 x 24 220 213 215 209 4 x 9 x 26 218 210 218 212 4 x 9 x 26 213 213 219 212 4 x 10 x 26 213 213 209 216 4 x 10 x 26 217 2" CL. 217 d2 BARS 19 SPA. @ 10 = 16-2 20 - d1 & d2 BARS EA. FACE FOOTING SIZE
1 0 - 5f2
OMIT ON 15D
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
1 -6
3 -6
45 TYP.
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR A 75 TON STEEL PI LI NG OPTI ON.
4-0 x 10-0 x 26-0 FOR 15D, 16D, 17C & 18D FOOTING NOTES:
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-58-07.
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER OF ADJACENT PILING SHALL NOT EXCEED 8-0.
REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1482 | PIER 217 222 602 758 1482 3281 32.0 TOTAL WEIGHT (LB.) CONCRETE (CY)
d2 f1 4 x 9 x 24 f2 g1 g2 d2 f1 4 x 9 x 26 f2 g1 g2 d2 f1 4 x 10 x 26 f2 g1 g2
48 - #9 AS SHOWN 24 - #5 @ 1-0 9 - #5 @ 1-0 26 - #8 @ 0-11 12 - #8 @ 0-9 48 - #9 AS SHOWN 26 - #5 @ 1-0 9 - #5 @ 1-0 26 - #8 @ 1-0 12 - #9 @ 0-9 48 - #9 AS SHOWN 26 - #5 @ 1-0 10 - #5 @ 1-0 34 - #8 @ 0-9 13 - #9 @ 0-9
9-1 8-8 23-8 8-8 23-8 9-1 8-8 25-8 8-8 25-8 9-1 9-8 25-8 9-8 25-8
4e3
4e2
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
602 1047 1482 262 268 878 1134 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. 4024 38.5 1 FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD. NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
1 1 -09
241
d2
9
7 -6
235
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-58-07.) 1-7
H44-63-07
9/29/2011
2:42:24 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-63-07
11x17_pdf.pltcfg
1 0 -0
9 -0
8 | PIER
3
4 -8 MI N.
4 -6
8 SP.@ 1 -0 =
8 -1 ;1 4 - 9g 2
8 -6;1 3 - 7g 2
8 -0;9 - 5f2
1 2 SP.@ 8
1 3 SP.@ 7
8 -0;9 - 5f2
REINFORCING
8 SP.@ 1 -0 =
6g1
7g2
9g2
7g1
REINFORCING
2" CL.
9 -0
4 -6 6 4 5 -0 6 4 -6
d2
BOTT. FOOTING
BOTT. FOOTING
# 9 BAR
5f1
4 -6
5f1
f1 f2
1 -0
3" CL.
g1
g2
H IN FT.
| - | ABUT. BRG.
8 -2;1 5 - 8g 2 8 SP.@ 1 -0 = 1 4 SP.@ 7 = 8 -0;9 - 5f2
FOOTING SIZE 4 -6
= 9 -6
9 SP.@ 1 -0 = 9 -0
8g2
BOTT. FOOTING
8g1
1 3 - 1 0g 2
10g2
138-10 151-4 3-6 x 9 x 26 1 6 TO 1 8 163-10 176-4 188-10 201-4 213-10 226-4 243-0 3-6 x 10 x 30 138-10 151-4 1 9 TO 21 163-10 176-4 3-6 x 9 x 28 188-10 201-4 3-6 x 9 x 30 226-4 3-6 x 10 x 30 243-0 138-10 3-6 x 9 x 26 151-4 22 TO 24 163-10 176-4 188-10 201-4 3-6 x 9 x 30 213-10 226-4 3-6 x 10 x 30 243-0 NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT. 3-6 x 9 x 28 1-7 D=9 7 -1 0 213-10 3-6 x 9 x 26 3-6 x 9 x 30 3-6 x 9 x 28
REINFORCING
1 0 - 5f2
9 -0
5f1
REINFORCING
5f2
5f1
d2
REINFORCING STEEL (ONE FOOTING) STRUCTURAL REVI SED 04-1 2 - EXCAVATI ON LI MI T WAS CHANGED TO 3 -0. FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1537 2" CL. 235 241 417 682 1537 253 260 456 1108 4e3 d2 f1 3-6 x 9 x 30 f2 g1 g2 d2 f1 3-6 x 10 x 30 f2 g1 g2 48 - #9 AS SHOWN 30 - #5 @ 1-0 9 - #5 @ 1-0 33 - #7 @ 0-11 14 - #9 @ 0-7 48 - #9 AS SHOWN 30 - #5 @ 1-0 10 - #5 @ 1-0 33 - #8 @ 0-11 13 - #10 @ 0-9 9-5 8-8 29-8 8-8 29-8 9-5 9-8 29-8 9-8 29-8 1537 271 278 585 1412 1537 302 309 852 1660 4660 38.9 4083 35.0 SYMMETRICAL ABOUT | PIER 04-1 2 4e2 3614 32.7 | PIER 4e1 d1 5 EQUAL SPACES 4 - d1 & d2 BARS 3112 30.3 d2 BARS TOTAL WEIGHT (LB.) CONCRETE (CY) 20 - d1 & d2 BARS EA. FACE 19 SPA. @ 10 = 16-2
FOOTING NOTES:
THESE SPREAD FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-58-07.
d2 f1 3-6 x 9 x 26 f2 g1 g2 d2 f1 3-6 x 9 x 28 f2 g1 g2
48 - #9 AS SHOWN 26 - #5 @ 1-0 9 - #5 @ 1-0 32 - #6 @ 0-9 13 - #7 @ 0-8 48 - #9 AS SHOWN 28 - #5 @ 1-0 9 - #5 @ 1-0 35 - #6 @ 0-9 15 - #8 @ 0-7
9-5 8-8 25-8 8-8 25-8 9-5 8-8 27-8 8-8 27-8
THESE SPREAD FOOTINGS SHALL EXTEND AT LEAST 6 INCHES INTO SUITABLE FOUNDATION ROCK AND THE LAST 6 INCHES OF ROCK EXCAVATION SHALL BE TO NEAT LINES OF MASONRY. THE FOUNDATION ROCK SHALL HAVE A MINIMUM LRFD NOMINAL BEARING RESISTANCE OF 30 kips PER SQUARE FOOT (ALLOWABLE BEARING VALUE OF AT LEAST 5 TONS PER SQUARE FOOT).
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-58-07.)
H44-64-07
3/28/2012
8:41:52 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-64-07
11x17_pdf.pltcfg
5 -0
TOP FOOTING
1 2 SP.@ 9
4 -6
1 0 -0
9 -0
H IN FT.
8 FOOTING SIZE
4
4 x 9 x 25 4 -6
8 -4;1 1 - 6g 2
4 x 9 x 27
8 SP.@ 1 -0 =
25 TO 27
8 -0;9 - 5f2
8 -0;9 - 5f2
REINFORCING
8 SP.@ 1 -0 =
6g1
8 -6;1 3 - 9g 2
6g2
9g2
6g1
REINFORCING
1 2 SP.@ 8
9 -0
4 -6 6 6 4 -6 6 6 5 -0 6 4 -6 4 -6
BOTT. FOOTING
BOTT. FOOTING
5f1
TOP FOOTING
REINFORCING
4 -6
5f1
TOP FOOTING
5f2
REINFORCING
5f2
28 TO 30
31 TO 33
4 x 9 x 29
8 -3;1 2 - 1 0g 2
8 SP.@ 1 -0 =
213-10 226-4 243-0 138-10 4 x 9 x 27 151-4 34 TO 36 163-10 4 x 9 x 29 176-4 188-10 201-4 213-10 226-4 243-0 138-10 151-4 37 TO 40 163-10 176-4 188-10 201-4 213-10 4 x 10 x 31 226-4 243-0 4 x 9 x 31 4 x 9 x 27 4 x 9 x 29 3" CL. 4 x 10 x 31 # 9 BAR 4 x 9 x 31 4 x 10 x 31 4 -8 MI N. d2 2" CL.
8 -0;9 - 5f2
201-4
4 x 9 x 31
6g1
REINFORCING
1 1 SP.@ 9 =
| PIER
8 -4;1 1 - 8g 2
8g2
4 -6
BOTT. FOOTING
10g2
9 -0
4 -6
5f1
5f1
f1 f2
1 -0
g1
g2
= 9 -2
BOTT. FOOTING
1 4 - 1 0g 2
10g2
8g1
REINFORCING
THESE SPREAD FOOTINGS SHALL EXTEND AT LEAST 6 INCHES INTO SUITABLE REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 1618 226 232 364 408 2848 33.3 TOTAL WEIGHT (LB.) CONCRETE (CY) FOUNDATION ROCK AND THE LAST 6 INCHES OF ROCK EXCAVATION SHALL BE TO NEAT LINES OF MASONRY. THE FOUNDATION ROCK SHALL HAVE A MINIMUM LRFD NOMINAL BEARING RESISTANCE OF 30 kips PER SQUARE FOOT (ALLOWABLE BEARING VALUE OF AT LEAST 5 TONS PER SQUARE FOOT).
1 0 - 5f2
1 3 SP.@ 8
5f1
48 - #9 AS SHOWN 25 - #5 @ 1-0 9 - #5 @ 1-0 28 - #6 @ 0-10 11 - #6 @ 0-10 48 - #9 AS SHOWN 27 - #5 @ 1-0 9 - #5 @ 1-0 31 - #6 @ 0-10 11 - #8 @ 0-10 48 - #9 AS SHOWN 29 - #5 @ 1-0 9 - #5 @ 1-0 34 - #6 @ 0-10 13 - #9 @ 0-8 48 - #9 AS SHOWN 31 - #5 @ 1-0 9 - #5 @ 1-0 37 - #6 @ 0-10 12 - #10 @ 0-9 48 - #9 AS SHOWN 31 - #5 @ 1-0 10 - #5 @ 1-0 31 - #8 @ 1-0 14 - #10 @ 0-8
9-11 8-8 24-8 8-8 24-8 9-11 8-8 26-8 8-8 26-8 9-11 8-8 28-8 8-8 28-8 9-11 8-8 30-8 8-8 30-8 9-11 9-8 30-8 9-8 30-8
6 1618 244 250 404 783 1618 262 269 443 1267 4e3 1618 280 288 482 1584 1618 313 320 800 NOTE: D = PIN DIAMETER. 1847 DIMENSIONS ARE OUT TO OUT. 4898 45.9 4252 41.3 SYMMETRICAL ABOUT | PIER 1-7 4e2 8 -4 3859 38.7 | PIER 4e1
APPROVED BY BRI DGE ENGI NEER
3299
36.0
2" CL.
d2 BARS
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
D=9 04-1 2
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-58-07.)
d2
H44-65-07
3/28/2012
8:41:54 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-65-07
11x17_pdf.pltcfg
5 -0
1 0 -0
9 -0
9 -0
| PIER | BEAMS 3-4 2-3 7-10 2x8 BEVELED KEY 7 1 -8 | PIER 7-10 7-10 7-10 5c4 5c1 a1 LOW STEP 7-10 7-10 2-3 3 3 SP. @ 4(+) 7 3 SP. @ 4(+) 3 a2
. P Y T
| ROADWAY
3 -4
1 -8
5c1
3 3 1 1 . P Y T
5c3 9 6a3 9 9
| BEARINGS
3 1
SYMMETRICAL ABOUT THIS POINT THROUGH 180 ROTATION EXCEPT STEP ELEVATIONS
CAP PLAN
9 2" CL. 7 -0
5c2 - 5 SP. @ 1-0 = 5-0 - 138-10, 151-4, 163-10, 176-4, 188-10 9 6a4 9 8b1 11(-) 5c4 - 4 SP. @ 1-11(+) 6a3 9 9 SP. @ 0-11(-) = 8-6 a1 a2 6 3-4 2" CL. 3 d1 5c3 MARCH, 2007 5c3 5c2 - 6 SP. @ 10 = 5-0 - 201-4, 213-10 5c2 - 7 SP. @ 8(-) = 5-0 GRADE ELEV. AT PIER - 226-4, 243-0
B
" U" NOTE: SHIFT 5c1 BARS TO CLEAR d1 COLUMN BARS ALL SPANS 5c1 - 5 SP. @ 1-11(+) 9 9 1 0 3
5c1 4 -0 5c4
SECTION B-B
3 -6
3 -0
5c2 3 3
H = HEI GHT OF PI ER
BEVELED KEY
H = 25TO 40
8b1
H = 1 6TO 24
4e BARS @ 1 -0 CTRS.
2x8x18-0
d1 BARS
6a4
4e BARS @ 1 -0 CTRS.
A B
15-3 10-6
| PIER
5 -1 0 MI N.
LAP
2 SP.
4e1
CONSTRUCTION JOINT
@ 9
D = DEPTH
PIER NOTES:
SEE "TEE PIER NOTES" ON H44-02-07 FOR NOTES REGARDING APPLICATION OF THESE PIER STANDARDS.
d2 BARS
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
MINIMUM CLEAR DISTANCE FROM FACE OF CONCRETE 1 -0 TO NEAR REINFORCING BAR SHALL BE 2 INCHES UNLESS OTEHRWISE NOTED OR SHOWN. 1-6 TOP OF PILES DETAILS SEE FOOTING DETAILS 1-6 1-6 SEE FOOTING 1-6 ELIMINATE 2x8 BEVELED KEYWAY ON TOP OF CAP FOR EXPANSION PIERS.
2" CL.
d2 BARS
4e1
d1
3 -0
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
PRETENSIONED PRESTRESSED CONCRETE BEAM BRIDGES TEE PIER CAP AND COLUMN
30 SKEW
SECTION A-A
H44-66-07
9/29/2011
2:42:31 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-66-07
11x17_pdf.pltcfg
a1
9
| - | ABUT. BEARINGS 4 REI NFORCI NG STEEL BAR a1 a2 6a3 LENGTH 51-8 51-8 51-8 SHAPE
138-10
151-4
163-10
176-4
188-10
201-4
213-10
226-4
243-0
NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT NO. SIZE WEIGHT 8 8 8 6 8 26 24 40 20 9 8 6 6 8 5 5 5 5 5713 40.9 1405 1104 621 350 580 493 425 586 149 8 8 8 6 8 26 24 40 20 9 9 6 6 8 5 5 5 5 6014 40.9 1405 1405 621 350 580 493 425 586 149 8 8 8 6 8 26 24 40 20 10 9 6 6 8 5 5 5 5 6388 40.9 1779 1405 621 350 580 493 425 586 149 8 8 8 6 8 26 24 40 20 10 9 6 6 8 5 5 5 5 6388 40.9 1779 1405 621 350 580 493 425 586 149 8 8 8 6 8 26 24 40 20 10 9 6 6 8 5 5 5 5 6388 40.9 1779 1405 621 350 580 493 425 586 149 8 8 8 6 8 26 28 40 20 10 10 6 6 8 5 5 5 5 6833 40.9 1779 1779 621 350 580 493 496 586 149 8 8 8 6 8 26 28 40 20 11 10 6 6 8 5 5 5 5 7250 40.9 2196 1779 621 350 580 493 496 586 149 8 8 8 6 8 26 32 40 20 11 10 6 6 8 5 5 5 5 7321 40.9 2196 1779 621 350 580 493 567 586 149 8 8 8 6 8 26 32 40 20 11 11 6 6 8 5 5 5 5 7738 40.9 2196 2196 621 350 580 493 567 586 149
1 -1 1
2 -1 1
D=6
D=2
2 -8
4 -2
D=2
11-9
15-1
5c1 5c2 4
2-10
8b1
4e1
1 2 -8
5c4
3-9 TO 5-5
5c3 4
COLUMN
REINFORCING STEEL H IN FEET COLUMN HEIGHT STRUCTURAL CONCRETE (CY) NO. SIZE LENGTH WEIGHT NO. SIZE LENGTH WEIGHT NO. SIZE LENGTH WEIGHT 16 17 18 5-6 6-6 7-6 8-6 9-6 10-6 11-6 12-6 13-6 14-0 15-0 16-0 17-0 18-0 19-0 20-0 21-0 22-0 23-0 24-0 25-0 26-0 27-0 28-0 29-0 12.4 14.7 17.0 19.2 21.5 23.7 26.0 28.3 30.5 31.7 33.9 36.2 38.5 40.7 43.0 45.2 47.5 49.8 52.0 54.3 56.5 58.8 61.1 63.3 65.6 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 9-0 10-0 11-0 12-0 13-0 14-0 15-0 16-0 17-0 17-6 18-6 19-6 20-6 21-6 22-6 23-6 24-6 25-6 26-6 27-6 28-6 29-6 30-6 31-6 32-6 1936 2152 2367 2582 2797 3012 3227 3442 3658 3765 3980 4195 4411 4626 4841 5056 5271 5486 5701 5917 6132 6347 6562 6777 6992 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 13-3 106 124 142 159 177 195 212 230 248 266 283 301 319 336 354 372 389 407 425 443 460 478 496 513 531 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 17-3 277 323 369 415 461 507 553 599 645 691 737 784 830 876 922 968 1014 1060 1106 1152 1198 1244 1291 1337 1383 d1 BAR 4e1 BAR 4e2 BAR TOTAL WEIGHT (LB.) 2319 2599 2878 3156 3435 3714 3992 4271 4551 4722 5000 5280 5560 5838 6117 6396 6674 6953 7232 7512 7790 8069 8349 8627 8906
4e2
5c4
NOTE: ALL DIMENSIONS ARE OUT TO OUT. D = PIN DIAMETER.
19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
1 SEE SHEET H44-24-07 FOR STEP REINFORCING STEEL QUANTITIES AND DETAILS.
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
H44-67-07
9/29/2011
2:42:33 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-67-07
11x17_pdf.pltcfg
10
| PIER 1 -6 7g2 5 -1 0 MI N.
= 9 -7
d2
1 0 SP.@ 1 -0 = 1 0 -0
8g1
1 2 - 7g 2
2" CL.
1 1 SP.@ 1 0
#1 0 BAR
1 1 - 5f2
f1 f2 g1
5f1 5f2
CL. 1 -1
1 -0
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 25-0 SYMM. ABOUT | PIER
1 -6
2 -6
TOP OF
45 TYP.
g2 PI LE
1-7
3-1
3-1
3-1
1-6
D=10 7g2
= 9 -7
8g1
1 2 - 7g 2
1-10
1 0 SP.@ 1 -0 = 1 0 -0
1 1 SP.@ 1 0
1 -3 1 -3
1 -6
1 1 - 5f2
d2
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-66-07.
3
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 SYMM. ABOUT | PIER
1 -6
FOOTING NOTES:
2 -6
45 TYP.
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS. OF ADJACENT PILING SHALL NOT EXCEED 8-0. PILING (HP10x57) H IN FT. 22 TO 24 1 9 TO 21 1 6 TO 1 8 | - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 22A 23A 24A 25A 22A 24A 24A 26A 23A 24A 25A 27A 1 DES. BRG. (TONS) 50 50 50 50 50 49 50 50 50 50 50 50 2 LRFD DES. BRG. (KIPS) 143 145 3-6 x 10-6 x 25 146 147 140 3-6 x 10-6 x 25 146 144 146 143 3-6 x 10-6 x 25 146 144 4e2 REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 2152 265 283 869 605 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. 4174 34.0 1 g1 g2 32 - #8 @ 0-9 12 - #7 @ 0-10 10-2 24-8 FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD. CONCRETE (CY) WEIGHT (LB.) 1 1 -09 TOTAL SYMMETRICAL ABOUT | PIER
LATEST REVI SI ON DATE
25-0
2" CL.
143
d2 BARS
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
d2 f1 3-6 x 10-6 x 25 f2
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-66-07.)
H44-68-07
9/29/2011
2:42:35 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-68-07
11x17_pdf.pltcfg
1 0 -6
1 0 -6
10
1 -6
7g2
1 0 SP.@ 1 -0 = 1 0 -0 = 1 0 -3
2 -8
5 -1 0 MI N.
d2
1 0 SP.@ 1 -0 = 1 0 -0
9g1
1 1 - 7g 2
REINF.
REINF.
1 0 SP.@ 1 -0 = 1 0 -0
2" CL.
1 -4 1 -4
1 3 SP.@ 9
1 -4 1 -4
1 1 -0
2 -8
BOTT. FTG.
1 -6
| PIER
1 1 - 5f2
#1 0 BAR
2 -8
1 1 - 5f2
f1 f2 g1
5f1 5f2
1 -6
CL. 1 -1
1 -0
TOP OF
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 25-0 SYMM. ABOUT | PIER
45 TYP.
SYMM. ABOUT | PIER 6 26 SP. @ 1-0 = 26-0 27 - 5f1 27-0 SYMM. ABOUT | PIER
1 -6
2 -8
45 TYP.
g2 PI LE
TYPICAL SECTION 4-0 x 11-0 x 25-0 FOR 24B, 25B, 26B & 27B
6 25 SP. @ 11 = 23-11 26 - 9g1
6
1-7
3-1
3-1
3-1
1-6
1-9
3-5
3-5
3-5
1-6
1 -6
7g2
1 0 SP.@ 1 -0 = 1 0 -0 = 1 0 -3
2 -8
9g1
1 1 - 7g 2
REINF.
REINF.
1 0 SP.@ 1 -0 = 1 0 -0
1 0 SP.@ 1 -0 = 1 0 -0
1 -4 1 -4
1 3 SP.@ 9
1 -4 1 -4
1 1 -0
2 -8
BOTT. FTG.
1 -6
1 1 - 5f2
H IN FT. 37 TO 40 34 TO 36 31 TO 33 28 TO 30 25 TO 27
PILING (HP10x57) | - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 24B 24B 26B 27B 24B 25B 26B 28A 24C 25C 26C 28B 24C 25C 27C 28B 25C 26C 28B 29A 1 DES. BRG. (TONS) 49 50 50 50 50 50 50 50 50 50 50 49 50 50 50 50 50 50 49 50 2 LRFD DES. BRG. (KIPS) 141 146 4 x 11 x 25 144 146 143 FOOTING SIZE
2 -8
1 1 - 5f2
5f1 5f2
5f1 5f2
1 -6
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 25-0 SYMM. ABOUT | PIER
45 TYP.
SYMM. ABOUT | PIER 6 26 SP. @ 1-0 = 26-0 27 - 5f1 27-0 SYMM. ABOUT | PIER
1 -6
2 -8
45 TYP.
145 4 x 11 x 25 146 144 143 144 4 x 11 x 27 145 143 145 146 4 x 11 x 27 144 2" CL. 145 145 145 4 x 11 x 27 142 144 d1 5 EQUAL SPACES 4 - d1 & d2 BARS REINFORCING STEEL (ONE FOOTING) STRUCTURAL | PIER 4e1 8 -8
APPROVED BY BRI DGE ENGI NEER
REVI SED 1 1 -09 - SHEET WAS REVI SED TO MEET LRFD SPECI FI CATI ONS.
4-0 x 11-0 x 27-0 FOR 28B & 29A 4-0 x 11-0 x 25-0 FOR 28A
20 SPA. @ 10 = 17-11 21 - d1 & d2 BARS EA. FACE
FOOTING NOTES:
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-66-07. d2 BARS BATTER PILES IN EXTERIOR ROWS 1:4 IN THE DIRECTION SHOWN.
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER OF ADJACENT PILING SHALL NOT EXCEED 8-0.
CONCRETE (CY)
4e2 D=10
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
d2 f1 4 x 11 x 25 f2 g1 g2 d2 f1 4 x 11 x 27 f2 g1 g2
50 - #10 AS SHOWN 25 - #5 @ 1-0 11 - #5 @ 1-0 26 - #9 @ 0-11 11 - #7 @ 1-0 50 - #10 AS SHOWN 27 - #5 @ 1-0 11 - #5 @ 1-0 33 - #8 @ 0-9 14 - #8 @ 0-9
10-6 10-8 24-8 10-8 24-8 10-6 10-8 26-8 10-8 26-8
| PIER 1-10
1 1 -09
283
4318
40.7
SYMMETRICAL ABOUT
d2 BAR LAYOUT d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT. 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. 1 (SEE SECTION A-A ON SHEET H44-66-07.) FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD.
H44-69-07
9/29/2011
2:42:37 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-69-07
11x17_pdf.pltcfg
1 1 -0
1 1 -0
7g2
= 8 -6
5 -1 0 MI N.
8g1
d2 2" CL.
8 SP.@ 1 -0 = 8 -0
1 2 SP.@ 8
9 - 5f2
3 -0
#1 0 BAR
5f1 5f2
f1 f2 g1
6
CL. 1 -1
1 -0
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 25-0 SYMM. ABOUT | PIER
1 -6
3 -0
45 TYP.
TOP OF
g2 PI LE
TYPICAL SECTION
9
3-8
3-8
3-8
1-6
8 -2
7g2
= 8 -6
8 SP.@ 1 -0 = 8 -0
1 2 SP.@ 8
1 3 - 7g 2
3 -0
D=10
8g1
1 -6
1-10
9 - 5f2
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
5f1 5f2
SYMM. ABOUT | PIER 6 24 SP. @ 1-0 = 24-0 25 - 5f1 25-0 SYMM. ABOUT | PIER
1 -6
3 -0
45 TYP.
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR A 75 TON STEEL PI LI NG OPTI ON.
PILING (HP10x57) H IN FT. 22 TO 24 1 9 TO 21 1 6 TO 1 8 | - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 15A 16A 16A 17A 15A 16A 17A 18A 16A 16A 17A 18A 1 DES. BRG. (TONS) 74 72 75 75 75 74 74 72 73 75 75 73 2 LRFD DES. BRG. (KIPS) 215 208 3-6 x 9 x 25 2" CL. 217 217 220 213 3-6 x 9 x 25 213 207 210 218 3-6 x 9 x 25 217 211 4e2 REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 2152 226 232 787 655 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. 4052 29.2 1 g1 g2 34 - #8 @ 0-8 13 - #7 @ 0-8 8-8 24-8 FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD. CONCRETE (CY) WEIGHT (LB.) | PIER 4e1 d1 5 EQUAL SPACES 4 - d1 & d2 BARS d2 BARS FOOTING SIZE 20 SPA. @ 10 = 17-11 21 - d1 & d2 BARS EA. FACE
FOOTING NOTES:
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-66-07.
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER OF ADJACENT PILING SHALL NOT EXCEED 8-0.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
TOTAL
d2 f1 3-6 x 9 x 25 f2
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-66-07.)
H44-70-07
9/29/2011
2:42:40 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-70-07
11x17_pdf.pltcfg
9 -0
9 -0
| PIER
1 -6
8g2
1 1 SP.@ 9 = 8 -3
3 -0
8 SP.@ 1 -0 = 8 -0
8 SP.@ 1 -0 = 8 -0
1 2 - 8g 2
2" CL.
9 -0
1 2 - 8g 2
OMIT ON 18B
3 -0
d2
8g1
1 1 SP.@ 9 = 8 -3
5 -1 0 MI N.
8g2 8g1
1 -6
9 - 5f2
3 -0
9 - 5f2
#1 0 BAR
f1 f2 g1
5f1 5f2
5f1 5f2
CL. 1 -1
1 -0
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
45 TYP.
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
1 -6
3 -0
45 TYP.
TOP OF
g2 PI LE
TYPICAL SECTION
3-10
3-10
3-10
1-6
8g2
1 1 SP.@ 1 0 = 9 -2
8g1
1 2 - 8g 2
9 SP.@ 1 -0 = 9 -0
1 -6
1 0 - 5f2
H IN FT. 37 TO 40 34 TO 36 31 TO 33 28 TO 30 25 TO 27
PILING (HP10x57) | - | ABUT. BRG. 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 201-4 213-10 226-4 243-0 NO. & LAYOUT 16B 17B 17B 18B 16B 17B 18B 18B 17B 17B 18B 19A 17C 17C 18C 19B 17C 18C 18C 19B 1 DES. BRG. (TONS) 74 73 75 74 75 74 72 75 73 75 73 74 73 75 74 74 75 72 75 75 2 LRFD DES. BRG. (KIPS) FOOTING SIZE
212 210 4 x 9 x 26 219 213 216 214 4 x 9 x 26 209 216 210 217 4 x 9 x 26 212 213 212 219 4 x 10 x 26 213 214 216 209 4 x 10 x 26 218 218 d1 2" CL. d2 BARS 20 SPA. @ 10 = 17-11 21 - d1 & d2 BARS EA. FACE
SYMM. ABOUT | PIER 6 25 SP. @ 1-0 = 25-0 26 - 5f1 26-0 SYMM. ABOUT | PIER
1 -6
3 -6
45 TYP.
REVI SED 1 1 -09 - THI S SHEET WAS ADDED FOR A 75 TON STEEL PI LI NG OPTI ON.
4-0 x 10-0 x 26-0 FOR 17C, 18C & 19B FOOTING NOTES:
THESE FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-66-07.
STEEL PILING USED AS POINT BEARING SHALL HAVE A MINIMUM DISTANCE OF APPROXIMATELY 10 FEET FROM BOTTOM OF FOOTING TO TOP OF BEARING ROCK. THE PILE LAYOUTS ARE SUCH THAT THE DISTANCE CENTER TO CENTER OF ADJACENT PILING SHALL NOT EXCEED 8-0. 5 EQUAL SPACES 4 - d1 & d2 BARS
REINFORCING STEEL (ONE FOOTING) STRUCTURAL BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 8 -8 FOOTING SIZE WEIGHT (LB.) 2259 235 TOTAL CONCRETE (CY)
| PIER 4e1
APPROVED BY BRI DGE ENGI NEER
4e2 D=10
LATEST REVI SI ON DATE
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
d2 f1 4 x 9 x 26 f2 g1 g2 d2 f1 4 x 10 x 26 f2 g1 g2
50 - #10 AS SHOWN 26 - #5 @ 1-0 9 - #5 @ 1-0 28 - #8 @ 0-11 12 - #8 @ 0-9 50 - #10 AS SHOWN 26 - #5 @ 1-0 10 - #5 @ 1-0 35 - #8 @ 0-9 12 - #8 @ 0-10
10-6 8-8 25-8 8-8 25-8 10-6 9-8 25-8 9-8 25-8
| PIER 1-10
1 1 -09
241
4205
34.7
SYMMETRICAL ABOUT
d2 BAR LAYOUT d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT. 2 FOR ESTIMATING PILE LENGTHS USING AASHTO LRFD SPECIFICATIONS. 1 (SEE SECTION A-A ON SHEET H44-66-07.) FOR DETERMINING ACTUAL PILE LENGTHS IN FIELD.
H44-71-07
9/29/2011
2:42:42 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-71-07
11x17_pdf.pltcfg
1 0 -0
9 -0
9 | PIER
4
5 -1 0 MI N.
9 SP.@ 1 1 = 8 -3
4 -6
8 SP.@ 1 -0 =
8 -0;9 - 5f2
8 -0;9 - 5f2
REINFORCING
8 SP.@ 1 -0 =
6g1
1 0 - 7g 2
8 -4;1 1 - 1 0g 2
1 0 SP.@ 1 0 =
7g2
10g2
7g1
REINFORCING
2" CL.
9 -0
4 -6 6 6 5 -0 6 4 -6
d2
BOTT. FOOTING
BOTT. FOOTING
#1 0 BAR
4 -6
5f1
TOP FOOTING
5f1
TOP FOOTING
f1 f2
REINFORCING
5f2
REINFORCING
5f2
1 -0
3" CL.
g1
g2
H IN FT.
| - | ABUT. BRG.
8 -6;1 3 - 8g 2 = 8 SP.@ 1 -0 = 8 -0;9 - 5f2
FOOTING SIZE
9 SP.@ 1 -0 = 9 -0 = 9 -6
8g2
4 -6
BOTT. FOOTING
BOTT. FOOTING
1 3 - 1 0g 2
10g2
138-10 151-4 3-6 x 9 x 27 1 6 TO 1 8 163-10 176-4 188-10 201-4 213-10 3-6 x 10 x 31 243-0 138-10 151-4 1 9 TO 21 163-10 176-4 188-10 201-4 213-10 226-4 243-0 138-10 3-6 x 9 x 27 151-4 22 TO 24 163-10 176-4 188-10 201-4 213-10 226-4 243-0 3-6 x 10 x 31 3-6 x 9 x 31 3-6 x 9 x 29 1-10 3-6 x 10 x 31 9 -0 3-6 x 9 x 31 3-6 x 9 x 29 3-6 x 9 x 27 3-6 x 9 x 29 3-6 x 9 x 31
6g1
REINFORCING
1 2 SP.@ 8
7g1
REINFORCING
1 0 - 5f2
9 -0
5f1
226-4
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
REINFORCING STEEL (ONE FOOTING) STRUCTURAL REVI SED 04-1 2 - EXCAVATI ON LI MI T WAS CHANGED TO 3 -0. FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 2331 244 250 391 545 2331 262 269 443 995 2331 280 288 549 1452 2331 313 320 731 1715 5410 40.2 4900 36.2 SYMMETRICAL ABOUT | PIER 04-1 2 4e2 4300 33.8 | PIER d1 5 EQUAL SPACES 4 - d1 & d2 BARS 3-6 x 9 x 29 f2 g1 g2 d2 f1 3-6 x 9 x 31 f2 g1 g2 d2 f1 3-6 x 10 x 31 f2 g1 g2 9 - #5 @ 1-0 34 - #6 @ 0-10 13 - #8 @ 0-8 50 - #10 AS SHOWN 31 - #5 @ 1-0 9 - #5 @ 1-0 31 - #7 @ 1-0 11 - #10 @ 0-10 50 - #10 AS SHOWN 31 - #5 @ 1-0 10 - #5 @ 1-0 37 - #7 @ 0-10 13 - #10 @ 0-9 28-8 8-8 28-8 10-10 8-8 30-8 8-8 30-8 10-10 9-8 30-8 9-8 30-8 3761 31.5 2" CL. TOTAL WEIGHT (LB.) d2 BARS CONCRETE (CY) 21 - d1 & d2 BARS EA. FACE 20 SPA. @ 10 = 17-11
FOOTING NOTES:
THESE SPREAD FOOTINGS ARE DESIGNED AND DETAILED TO BE USED WITH THE CAP AND COLUMN DETAILS OF THE TEE PIERS AS SHOWN ON SHEET H44-66-07.
d2 f1 3-6 x 9 x 27 f2 g1 g2 d2 f1
THESE SPREAD FOOTINGS SHALL EXTEND AT LEAST 6 INCHES INTO SUITABLE FOUNDATION ROCK AND THE LAST 6 INCHES OF ROCK EXCAVATION SHALL BE TO NEAT LINES OF MASONRY. THE FOUNDATION ROCK SHALL HAVE A MINIMUM LRFD NOMINAL BEARING RESISTANCE OF 30 kips PER SQUARE FOOT (ALLOWABLE BEARING VALUE OF AT LEAST 5 TONS PER SQUARE FOOT).
4e1
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-66-07.)
H44-72-07
3/28/2012
8:41:57 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-72-07
11x17_pdf.pltcfg
5 -0
5f1
1 2 SP.@ 9
4 -6
1 0 -0
9 -0
H IN FT.
7 -6;1 0 - 9g 2
1 1 SP.@ 9 = 8 -3
9 SP.@ 1 0 =
7 SP.@ 1 -0 =
7 -0;8 - 5f2
8 SP.@ 1 -0 =
25 TO 27
8 -0;9 - 5f2
8 -0
4 x 9 x 30
1 2 - 1 0g 2
163-10
6g1
REINFORCING
9g2
10g2
6g1
REINFORCING
4 -6 6 5 5 -0 6 6 5 -0 6 5 -0 4 -6
151-4
4 -0
BOTT. FOOTING
BOTT. FOOTING
5f1
5f2
4 -0
4 x 9 x 32
4 x 10 x 32
6
5f1
4 x 8 x 30 6 4 x 9 x 30
28 TO 30
4 x 9 x 32
31 TO 33
163-10 176-4 4 -6
1 0 SP.@ 1 0 =
8 -4;1 1 - 9g 2
8 SP.@ 1 -0 =
8 -0;9 - 5f2
| PIER
6g1
REINFORCING
9 SP.@ 1 -0 = 9 -0
9g2
= 9 -6
188-10
4 x 9 x 32
BOTT. FOOTING
4 x 9 x 30
10g2
REINFORCING
1 0 - 5f2
9 -0
2" CL.
5f1
4 -6
d2
1 2 SP.@ 9
34 TO 36
#1 0 BAR
f1 f2
1 -0
37 TO 40
4 x 9 x 32
3" CL.
163-10
g1
g2
4
1 4 SP.@ 8 = 9 -4
10g2
THESE SPREAD FOOTINGS SHALL EXTEND AT LEAST 6 INCHES INTO SUITABLE REINFORCING STEEL (ONE FOOTING) STRUCTURAL FOOTING SIZE BAR NO., SIZE & SPACING LENGTH WEIGHT (LB.) 2438 240 248 345 1009 2438 271 278 417 1110 2438 289 297 456 1635 2438 323 330 692 1771 2438 343 351 731 6036 50.4 5554 47.4 SYMMETRICAL ABOUT | PIER 1-10 4e2 5115 42.7 | PIER d1 5 EQUAL SPACES 4 - d1 & d2 BARS 4 x 9 x 32 f2 g1 g2 d2 f1 4 x 10 x 32 f2 g1 g2 d2 f1 4 x 10 x 34 f2 g1 g2 9 - #5 @ 1-0 35 - #6 @ 0-11 12 - #10 @ 0-9 50 - #10 AS SHOWN 32 - #5 @ 1-0 10 - #5 @ 1-0 35 - #7 @ 0-11 13 - #10 @ 0-9 50 - #10 AS SHOWN 34 - #5 @ 1-0 10 - #5 @ 1-0 37 - #7 @ 0-11 15 - #10 @ 0-8 31-8 8-8 31-8 11-4 9-8 31-8 9-8 31-8 11-4 9-8 33-8 9-8 33-8 4514 40.0 2" CL. d2 BARS 4280 35.6 20 SPA. @ 10 = 17-11 TOTAL WEIGHT (LB.) CONCRETE (CY) FOUNDATION ROCK AND THE LAST 6 INCHES OF ROCK EXCAVATION SHALL BE TO NEAT LINES OF MASONRY. THE FOUNDATION ROCK SHALL HAVE A MINIMUM LRFD NOMINAL BEARING RESISTANCE OF 30 kips PER SQUARE FOOT (ALLOWABLE BEARING VALUE OF AT LEAST 5 TONS PER SQUARE FOOT).
REINFORCING
1 0 - 5f2
50 - #10 AS SHOWN 30 - #5 @ 1-0 8 - #5 @ 1-0 30 - #6 @ 1-0 10 - #9 @ 0-10 50 - #10 AS SHOWN 30 - #5 @ 1-0 9 - #5 @ 1-0 32 - #6 @ 0-11 11 - #9 @ 0-10 50 - #10 AS SHOWN 32 - #5 @ 1-0
11-4 7-8 29-8 7-8 29-8 11-4 8-8 29-8 8-8 29-8 11-4 8-8
4e1 9 -6
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
D=10 04-1 2
d2 BAR LAYOUT
(SEE SECTION A-A ON SHEET H44-66-07.)
d2
NOTE: D = PIN DIAMETER. DIMENSIONS ARE OUT TO OUT.
H44-73-07
2173
3/28/2012
8:41:59 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-73-07
11x17_pdf.pltcfg
5 -0
1 0 -0
1 0 -0
9 -0
6" CORRUGATED METAL PIPE OUTLET, OR 4" CORRUGATED DOUBLE-WALLED PE OR PVC PIPE OUTLET WITH AN APPROPRIATE COUPLER. IF METAL ABUTMENT FACE PIPE IS USED, THE PIPES SHOULD BE COUPLED IN ONE OF THE TWO FOLLOWING WAYS. 1. USE AN INSIDE FIT REDUCER COUPLER ( COUPLER MUST BE INSERTED A MINIMUM OF 1-0 INTO CMP. 2. INSERT 1-0 OF THE 4" SUBDRAIN INTO FORESLOPE THE 6" METAL OUTLET PIPE, THEN FULLY SEAL THE ENTIRE OPENING WITH GROUT.
6 0
OUTLET DETAILS
SUBDRAIN OUTLET SEE DETAILS ON SHEET H44-75-07 OR SHEET H44-76-07 SUBDRAIN OUTLET
TOE OF SLOPE REVI SED 1 1 -09 - REMOVED THE GRANULAR BACKFI LL DETAI L.
| BRIDGE
NOTE: SUBDRAIN OUTLET SUBDRAIN OUTLET 4" PERFORATED SUBDRAIN TO BE SLOPED DOWNWARD FROM THE | OF ROADWAY AND UNDERNEATH THE SLOPE PROTECTION AND OUTLET AS SEE ABUTMENT BACKFILL DETAILS SHEET FOR DETAILS NOT SHOWN ON THIS SHEET WHICH ARE PERTINENT TO THIS STRUCTURE.
INDICATED. RATE
APPROVED BY BRI DGE ENGI NEER
SITUATION PLAN
REFER TO SITUATION PLAN FOR NORTH ARROW.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 1 -09
SUBDRAIN DETAILS
H44-74-07
9/29/2011
2:42:48 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-74-07
11x17_pdf.pltcfg
SUBDRAIN NOTES:
FACE OF ABUTMENT FOOTING
NOMI NAL
SEE H44-74-07 AND "GENERAL ELEVATION DATA" SHEETS FOR DETAILS OF PLACING ALL SUBDRAINS AND SUBDRAIN OUTLETS REQUIRED FOR THIS STRUCTURE.
3-0} MAX.
6 MIN.
SUBDRAINS SHALL BE 4" IN DIAMETER AND BE IN ACCORDANCE WITH ARTICLE 4143.01, B, OF THE STANDARD SPECIFICATIONS. THE SUBDRAIN OUTLET SHALL CONSIST OF A 6-0 LENGTH OF PIPE WITH A REMOVABLE RODENT GUARD.
THE DIMENSIONS SHOWN FOR THE PROPOSED SUBDRAINS ARE BASED ON THE PROPOSED GRADING LAYOUT OF BRIDGE BERMS. THE DIMENSIONS SHOWN ARE FOR ESTIMATING ONLY.
REQUIRED LENGTHS AND GENERAL LOCATIONS OF SUBDRAINS ARE SUBJECT TO CHANGE DUE TO FIELD ADJUSTMENTS OF THE GRADING LAYOUT.
OR REBAR. DRIVE PIN OR REBAR VERTICALLY TO " (}) BELOW TOP SURFACE OF TREATED TIMBER.
THE COST OF FURNISHING AND PLACING SUBDRAIN (INCLUDING EXCAVATION), GRANULAR BACKFILL, POROUS BACKFILL, AND SUBDRAIN OUTLET IS TO BE INCLUDED IN THE PRICE BID FOR "STRUCTURAL CONCRETE (BRIDGE)". NO EXTRA PAYMENT WILL BE MADE.
3 -0
3-0
A
4" x 6" TREATED TIMBER EDGING
SUBDRAIN
THE BRIDGE BERM FORESLOPE SHALL BE COMPACTED AND SHAPED AS SHOWN ON 6 ENGINEERING FABRIC THESE PLANS, THE SITUATION PLAN AND AS DIRECTED BY THE ENGINEER. THE BERM FORESLOPE SHALL BE FIRM WHEN THE ENGINEERING FABRIC AND MACADAM STONE ARE PLACED.
WINGWALL MACADAM STONE ( 6" THICKNESS)
THE ENGINEERING FABRIC SHALL BE IN ACCORDANCE WITH ARTICLE 4196.01, B, 3, OF THE PIN OR REBAR STANDARD SPECIFICATIONS. IF THE ENGINEERING FABRIC IS LAPPED THE LAPS SHALL BE A MINIMUM OF ONE FOOT IN LENGTH, SHINGLE FASHION WITH UP SLOPE LAP PIECE
SECTION A-A
THE MACADAM STONE SHALL BE IN ACCORDANCE WITH ARTICLE 4122.02, OF THE STANDARD SPECIFICATIONS FOR COARSE MATERIAL (NO CHOKE STONE IS ALLOWED).
WOOD PRESERVATIVE TREATMENT FOR THE TIMBER EDGING SHALL MEET THE REQUIREMENTS FOR GUARDRAIL POSTS, SAWED FOUR SIDES, AND BE IN ACCORDANCE WITH SECTION 4161, OF THE STANDARD SPECIFICATIONS.
MECHANICAL OR HAND METHODS THAT WILL PROVIDE UNIFORM DEPTH AND DENSITY AND PROVIDE UNIFORM SURFACE APPEARANCE.
PAYMENT FOR THE BRIDGE WING ARMORING SHALL BE INCIDENTAL TO THE BID ITEM "STRUCTURAL CONCRETE (BRIDGE)" AND SHALL INCLUDE COSTS OF ALL MATERIAL AND LABOR TO CONSTRUCT THE WING ARMORING AS SHOWN ON THESE PLANS.
ENGINEERING FABRIC
ABUTMENT FOOTING
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
WINGWALL
SUBDRAIN
LATEST REVI SI ON DATE
1 1 -09
H44-75-07
9/29/2011
2:42:49 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-75-07
11x17_pdf.pltcfg
SUBDRAIN NOTES:
SEE H44-74-07 AND "GENERAL ELEVATION DATA" SHEETS FOR DETAILS OF PLACING ALL SUBDRAINS AND SUBDRAIN OUTLETS REQUIRED FOR THIS STRUCTURE.
NOMI NAL
3-0} MAX.
6 MIN.
SUBDRAINS SHALL BE 4" IN DIAMETER AND BE IN ACCORDANCE WITH ARTICLE 4143.01, B, OF THE STANDARD SPECIFICATIONS. THE SUBDRAIN OUTLET SHALL CONSIST OF A 6-0 LENGTH OF PIPE WITH A REMOVABLE RODENT GUARD.
SUBDRAIN OUTLET
THE DIMENSIONS SHOWN FOR THE PROPOSED SUBDRAINS ARE BASED ON THE PROPOSED GRADING LAYOUT OF BRIDGE BERMS. THE DIMENSIONS SHOWN ARE FOR ESTIMATING ONLY.
| " HOLES FOR " x 1-6 STEEL PIN OR REBAR. DRIVE PIN OR REBAR VERTICALLY TO " (}) BELOW TOP SURFACE OF TREATED TIMBER.
REQUIRED LENGTHS AND GENERAL LOCATIONS OF SUBDRAINS ARE SUBJECT TO CHANGE DUE TO FIELD ADJUSTMENTS OF THE GRADING LAYOUT.
THE COST OF FURNISHING AND PLACING SUBDRAIN (INCLUDING EXCAVATION), GRANULAR BACKFILL, POROUS BACKFILL, AND SUBDRAIN OUTLET IS TO BE INCLUDED IN THE PRICE BID FOR "STRUCTURAL CONCRETE (BRIDGE)". NO EXTRA PAYMENT WILL BE MADE.
3 -0
3-0
TO PREVENT UNDERMINING.
THE BRIDGE BERM FORESLOPE SHALL BE COMPACTED AND SHAPED AS SHOWN ON 6 ENGINEERING
SUBDRAIN
THESE PLANS, THE SITUATION PLAN AND AS DIRECTED BY THE ENGINEER. THE BERM FORESLOPE SHALL BE FIRM WHEN THE ENGINEERING FABRIC AND MACADAM STONE ARE PLACED.
FABRIC
WINGWALL
THE ENGINEERING FABRIC SHALL BE IN ACCORDANCE WITH ARTICLE 4196.01, B, 3, OF THE PIN OR REBAR STANDARD SPECIFICATIONS. IF THE ENGINEERING FABRIC IS LAPPED THE LAPS SHALL BE A MINIMUM OF ONE FOOT IN LENGTH, SHINGLE FASHION WITH UP SLOPE LAP PIECE ON TOP AND STAPLED FOR CONTINUITY.
SECTION A-A
THE MACADAM STONE SHALL BE IN ACCORDANCE WITH ARTICLE 4122.02, OF THE STANDARD SPECIFICATIONS FOR COARSE MATERIAL (NO CHOKE STONE IS ALLOWED).
WOOD PRESERVATIVE TREATMENT FOR THE TIMBER EDGING SHALL MEET THE REQUIREMENTS FOR GUARDRAIL POSTS, SAWED FOUR SIDES, AND BE IN ACCORDANCE WITH SECTION 4161, OF THE STANDARD SPECIFICATIONS.
THE MACADAM STONE SHALL BE DEPOSITED, SPREAD, CONSOLIDATED AND SHAPED BY MECHANICAL OR HAND METHODS THAT WILL PROVIDE UNIFORM DEPTH AND DENSITY AND
BARRIER RAIL
PAYMENT FOR THE BRIDGE WING ARMORING SHALL BE INCIDENTAL TO THE BID ITEM "STRUCTURAL CONCRETE (BRIDGE)" AND SHALL INCLUDE COSTS OF ALL MATERIAL AND LABOR TO CONSTRUCT THE WING ARMORING AS SHOWN ON THESE PLANS.
WINGWALL EXTENSION
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
WINGWALL
SUBDRAIN
1 1 -09
H44-76-07
9/29/2011
2:42:50 PM
tsorens
W:\Highway\Bridge\Standards\Bridges\H44-07.dgn
H44-76-07
11x17_pdf.pltcfg
BRIDGE 2-2
APPROACH PAVEMENT
1 -6
ABUTMENT WING
REVI SED 04-1 2 - EXCAVATI ON LI MI T ON THE FRONT FACE OF THE ABUTMENT WAS CHANGED TO A 3 -0 LI MI T. THE APPROACH FI LL WAS I DENTI FI ED AS THE GRADI NG SURFACE.
WHEN THE FABRIC IS IN PLACE, THE SUBDRAIN SHALL BE INSTALLED DIRECTLY ON THE FABRIC AT THE TOE OF THE REAR EXCAVATION SLOPE. A SLOT WILL NEED TO BE CUT IN THE FABRIC AT THE POINT WHERE THE SUBDRAIN EXITS THE FABRIC NEAR THE END OF THE ABUTMENT WING WALL. FLOODABLE BACKFILL POROUS BACKFILL IS THEN PLACED AND LEVELED, NO COMPACTION IS REQUIRED. BETWEEN WINGS APPROACH FILLS, SUBGRADE ELEV. THE REMAINING WORK INVOLVES BACKFILLING WITH FLOODABLE BACKFILL, SURFACE FLOODING, AND VIBRATORY COMPACTION. THE FLOODABLE BACKFILL MATERIAL SHALL BE FABRI C LI MI TS IN ACCORDANCE WITH THE STANDARD SPECIFICATIONS. THE FLOODABLE BACKFILL SHALL BE PLACED IN INDIVIDUAL LIFTS, SURFACE FLOODED, AND COMPACTED WITH VIBRATORY GEOTEXTI LE COMPACTION TO ENSURE FULL CONSOLIDATION. LIMIT THE LOOSE LIFTS TO NO MORE THAN 2 FEET OF THICKNESS. 1 1 FRONT FACE
~ . . .~ . . ~ .~ . ~ .~ . . . . . ~ ~ ~ . ~ . . ~ . . . . . ~ . ~ . . ~ . ~ . . . . . . . . ~ .~ . . . . . . . ~ ~ . . ~ . . ~ ~ . ~ . ~ . ~ . . . . ~ . .~ .
| APPROACH ROADWAY
LI MI TS OF BOTTOM
2 -0
PAY LIMIT
START SURFACE FLOODING FOR EACH FLOODABLE BACKFILL LIFT AT THE HIGH POINT OF THE SUBDRAIN AND PROGRESS TO THE LOW POINT WHERE THE SUBDRAIN EXITS THE FABRIC. TO ENSURE UNIFORM SURFACE FLOODING, WATER RUNNING FULL IN A 2-INCH DIAMETER HOSE SHOULD BE SPRAYED IN SUCCESSIVE 6-FOOT TO 8-FOOT INCREMENTS FOR 3 MINUTES WITHIN EACH INCREMENT.
FLOODABLE BACKFILL LIFT PLACEMENT, FLOODING, AND COMPACTION SHALL PROGRESS 2-2 (TYP.) UNTIL THE REQUIRED FULL THICKNESS OF THE ABUTMENT BACKFILL HAS BEEN COMPLETED.
4"SUBDRAIN GEOTEXTILE
WATER REQUIRED FOR FLOODING, SUBDRAINS, POROUS BACKFILL, FLOODABLE BACKFILL, AND GEOTEXTILE FABRIC FURNISHED AT THE BRIDGE ABUTMENTS WILL NOT BE MEASURED SEPARATELY FOR PAYMENT. 4" SUBDRAIN
THE COST OF WATER REQUIRED FOR FLOODING, SUBDRAINS, POROUS BACKFILL, FLOODABLE BACKFILL, AND GEOTEXTILE FABRIC FURNISHED AT THE BRIDGE ABUTMENTS SHALL BE INCLUDED IN THE CONTRACT UNIT PRICE BID FOR STRUCTURAL CONCRETE.
SECTION A-A
BACKFILL DETAILS
NOTE: GEOTEXTILE FABRIC WILL BE ATTACHED TO FACE OF ABUTMENT FOOTING AND WINGS. TOP SLOPE OF GEOTEXTILE FABRIC *DIMENSION VARIES DUE TO 2% SUBDRAIN SLOPE.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 -6
04-1 2
ABUTMENT WING
2-2
NOTE: SEE SUBDRAIN DETAILS SHEET FOR DETAILS NOT SHOWN ON THIS SHEET WHICH ARE PERTINENT TO THIS STRUCTURE.
H44-77-07
3/28/2012
8:42:00 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-77-07
11x17_pdf.pltcfg
2 -0
OF ABUTMENT
2 -0
BACK FACE
3 -0
POROUS BACKFILL
2 1
BRIDGE "W"
APPROACH PAVEMENT
"W" DIMENSION
SKEW 15 DIMENSION 2-2 2-6 3-0
1 -6
ABUTMENT WING
30 45
REVI SED 04-1 2 - EXCAVATI ON LI MI T ON THE FRONT FACE OF THE ABUTMENT WAS CHANGED TO A 3 -0 LI MI T. THE APPROACH FI LL WAS I DENTI FI ED AS THE GRADI NG SURFACE.
WHEN THE FABRIC IS IN PLACE, THE SUBDRAIN SHALL BE INSTALLED DIRECTLY ON THE FABRIC AT THE TOE OF THE REAR EXCAVATION SLOPE. A SLOT WILL NEED TO BE CUT IN THE FABRIC AT THE POINT WHERE THE SUBDRAIN EXITS THE FABRIC NEAR THE END OF THE ABUTMENT WING WALL. FLOODABLE BACKFILL POROUS BACKFILL IS THEN PLACED AND LEVELED, NO COMPACTION IS REQUIRED. BETWEEN WINGS APPROACH FILLS, SUBGRADE ELEV. THE REMAINING WORK INVOLVES BACKFILLING WITH FLOODABLE BACKFILL, SURFACE FLOODING, AND VIBRATORY COMPACTION. THE FLOODABLE BACKFILL MATERIAL SHALL BE FABRI C LI MI TS IN ACCORDANCE WITH THE STANDARD SPECIFICATIONS. THE FLOODABLE BACKFILL SHALL BE PLACED IN INDIVIDUAL LIFTS, SURFACE FLOODED, AND COMPACTED WITH VIBRATORY GEOTEXTI LE COMPACTION TO ENSURE FULL CONSOLIDATION. LIMIT THE LOOSE LIFTS TO NO MORE THAN 2 FEET OF THICKNESS. 1 1 FRONT FACE
~ . . .~ . . ~ .~ . ~ .~ . . . . . ~ ~ ~ . ~ . . ~ . . . . . ~ . ~ . . ~ . ~ . . . . . . . . ~ .~ . . . . . . . ~ ~ . . ~ . . ~ ~ . ~ . ~ . ~ . . . . ~ . .~ .
| APPROACH ROADWAY
LI MI TS OF BOTTOM
2 -0
PAY LIMIT
START SURFACE FLOODING FOR EACH FLOODABLE BACKFILL LIFT AT THE HIGH POINT OF THE SUBDRAIN AND PROGRESS TO THE LOW POINT WHERE THE SUBDRAIN EXITS THE FABRIC. TO ENSURE UNIFORM SURFACE FLOODING, WATER RUNNING FULL IN A 2-INCH DIAMETER HOSE SHOULD BE SPRAYED IN SUCCESSIVE 6-FOOT TO 8-FOOT INCREMENTS FOR 3 MINUTES WITHIN EACH INCREMENT.
A
BACK FACE OF ABUTMENT
3 -0
2 2 -0 1
FLOODABLE BACKFILL LIFT PLACEMENT, FLOODING, AND COMPACTION SHALL PROGRESS UNTIL THE REQUIRED FULL THICKNESS OF THE ABUTMENT BACKFILL HAS BEEN COMPLETED.
AND GEOTEXTILE FABRIC FURNISHED AT THE BRIDGE ABUTMENTS WILL NOT BE MEASURED SEPARATELY FOR PAYMENT.
THE COST OF WATER REQUIRED FOR FLOODING, SUBDRAINS, POROUS BACKFILL, FLOODABLE 4" SUBDRAIN BACKFILL, AND GEOTEXTILE FABRIC FURNISHED AT THE BRIDGE ABUTMENTS SHALL BE INCLUDED IN THE CONTRACT UNIT PRICE BID FOR STRUCTURAL CONCRETE.
SECTION A-A
BACKFILL DETAILS
NOTE: GEOTEXTILE FABRIC WILL BE ATTACHED TO FACE OF ABUTMENT FOOTING AND WINGS. *DIMENSION VARIES DUE TO 2% SUBDRAIN SLOPE.
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 -6
04-1 2
ABUTMENT WING
"W"
H44-78-07
3/28/2012
8:42:02 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-78-07
11x17_pdf.pltcfg
BRIDGE
1 -6
ABUTMENT WING
REVI SED 04-1 2 - EXCAVATI ON LI MI T ON THE FRONT FACE OF THE ABUTMENT WAS CHANGED TO A 3 -0 LI MI T. THE APPROACH FI LL WAS I DENTI FI ED AS THE GRADI NG SURFACE.
( TYP. )
FLOW RATE
ASTM D4491
(GAL/MIN/FT) % STRENGTH
2 -2
ASTM D4355
RETAINED
70
WHEN THE FABRIC IS IN PLACE, THE SUBDRAIN SHALL BE INSTALLED DIRECTLY ON THE FABRIC AT THE TOE OF THE REAR EXCAVATION SLOPE. A SLOT WILL NEED TO BE CUT IN THE FABRIC AT THE POINT WHERE THE SUBDRAIN EXITS THE FABRIC NEAR THE END OF THE ABUTMENT WING WALL. FLOODABLE BACKFILL POROUS BACKFILL IS THEN PLACED AND LEVELED, NO COMPACTION IS REQUIRED. BETWEEN WINGS APPROACH FILLS, SUBGRADE ELEV. THE REMAINING WORK INVOLVES BACKFILLING WITH FLOODABLE BACKFILL, SURFACE FLOODING, AND VIBRATORY COMPACTION. THE FLOODABLE BACKFILL MATERIAL SHALL BE FABRI C LI MI TS IN ACCORDANCE WITH THE STANDARD SPECIFICATIONS. THE FLOODABLE BACKFILL SHALL BE PLACED IN INDIVIDUAL LIFTS, SURFACE FLOODED, AND COMPACTED WITH VIBRATORY GEOTEXTI LE COMPACTION TO ENSURE FULL CONSOLIDATION. LIMIT THE LOOSE LIFTS TO NO MORE THAN 2 FEET OF THICKNESS. 1 1 FRONT FACE
~ . . .~ . . ~ .~ . ~ .~ . . . . . ~ ~ ~ . ~ . . ~ . . . . . ~ . ~ . . ~ . ~ . . . . . . . . ~ .~ . . . . . . . ~ ~ . . ~ . . ~ ~ . ~ . ~ . ~ . . . . ~ . .~ .
| APPROACH ROADWAY
2 -0
LI MI TS OF BOTTOM
PAY LIMIT
START SURFACE FLOODING FOR EACH FLOODABLE BACKFILL LIFT AT THE HIGH POINT OF THE SUBDRAIN AND PROGRESS TO THE LOW POINT WHERE THE SUBDRAIN EXITS THE FABRIC. TO ENSURE UNIFORM SURFACE FLOODING, WATER RUNNING FULL IN A 2-INCH DIAMETER HOSE SHOULD BE SPRAYED IN SUCCESSIVE 6-FOOT TO 8-FOOT INCREMENTS FOR 3 MINUTES WITHIN EACH INCREMENT.
FLOODABLE BACKFILL LIFT PLACEMENT, FLOODING, AND COMPACTION SHALL PROGRESS UNTIL THE REQUIRED FULL THICKNESS OF THE ABUTMENT BACKFILL HAS BEEN COMPLETED.
4"SUBDRAIN GEOTEXTILE
WATER REQUIRED FOR FLOODING, SUBDRAINS, POROUS BACKFILL, FLOODABLE BACKFILL, AND GEOTEXTILE FABRIC FURNISHED AT THE BRIDGE ABUTMENTS WILL NOT BE MEASURED SEPARATELY FOR PAYMENT.
THE COST OF WATER REQUIRED FOR FLOODING, SUBDRAINS, POROUS BACKFILL, FLOODABLE BACKFILL, AND GEOTEXTILE FABRIC FURNISHED AT THE BRIDGE ABUTMENTS SHALL BE INCLUDED IN THE CONTRACT UNIT PRICE BID FOR STRUCTURAL CONCRETE.
SECTION A-A
BACKFILL DETAILS
NOTE: GEOTEXTILE FABRIC WILL BE ATTACHED TO FACE OF ABUTMENT FOOTING AND WINGS. *DIMENSION VARIES DUE TO 2% SUBDRAIN SLOPE. ( TYP. ) 2 -2
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 -6
04-1 2
ABUTMENT WING
2-2
NOTE: SEE SUBDRAIN DETAILS SHEET FOR DETAILS NOT SHOWN ON THIS SHEET WHICH ARE PERTINENT TO THIS STRUCTURE.
H44-79-07
3/28/2012
8:42:03 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-79-07
11x17_pdf.pltcfg
2 -0
OF ABUTMENT
2 -0
BACK FACE
3 -0
POROUS BACKFILL
2 1
BRIDGE
1 -6
ABUTMENT WING
REVI SED 04-1 2 - EXCAVATI ON LI MI T ON THE FRONT FACE OF THE ABUTMENT WAS CHANGED TO A 3 -0 LI MI T. THE APPROACH FI LL WAS I DENTI FI ED AS THE GRADI NG SURFACE.
( TYP. )
FLOW RATE
ASTM D4491
(GAL/MIN/FT) % STRENGTH
2 -2
ASTM D4355
RETAINED
70
WHEN THE FABRIC IS IN PLACE, THE SUBDRAIN SHALL BE INSTALLED DIRECTLY ON THE FABRIC AT THE TOE OF THE REAR EXCAVATION SLOPE. A SLOT WILL NEED TO BE CUT IN THE FABRIC AT THE POINT WHERE THE SUBDRAIN EXITS THE FABRIC NEAR THE END OF THE ABUTMENT WING WALL. FLOODABLE BACKFILL POROUS BACKFILL IS THEN PLACED AND LEVELED, NO COMPACTION IS REQUIRED. BETWEEN WINGS APPROACH FILLS, SUBGRADE ELEV. THE REMAINING WORK INVOLVES BACKFILLING WITH FLOODABLE BACKFILL, SURFACE FLOODING, AND VIBRATORY COMPACTION. THE FLOODABLE BACKFILL MATERIAL SHALL BE FABRI C LI MI TS IN ACCORDANCE WITH THE STANDARD SPECIFICATIONS. THE FLOODABLE BACKFILL SHALL BE PLACED IN INDIVIDUAL LIFTS, SURFACE FLOODED, AND COMPACTED WITH VIBRATORY GEOTEXTI LE COMPACTION TO ENSURE FULL CONSOLIDATION. LIMIT THE LOOSE LIFTS TO NO MORE THAN 2 FEET OF THICKNESS. 1 1 FRONT FACE
~ . . .~ . . ~ .~ . ~ .~ . . . . . ~ ~ ~ . ~ . . ~ . . . . . ~ . ~ . . ~ . ~ . . . . . . . . ~ .~ . . . . . . . ~ ~ . . ~ . . ~ ~ . ~ . ~ . ~ . . . . ~ . .~ .
A
| APPROACH ROADWAY
2 -0
LI MI TS OF BOTTOM
PAY LIMIT
START SURFACE FLOODING FOR EACH FLOODABLE BACKFILL LIFT AT THE HIGH POINT OF THE SUBDRAIN AND PROGRESS TO THE LOW POINT WHERE THE SUBDRAIN EXITS THE FABRIC. TO ENSURE UNIFORM SURFACE FLOODING, WATER RUNNING FULL IN A 2-INCH DIAMETER HOSE SHOULD BE SPRAYED IN SUCCESSIVE 6-FOOT TO 8-FOOT INCREMENTS FOR 3 MINUTES WITHIN EACH INCREMENT.
FLOODABLE BACKFILL LIFT PLACEMENT, FLOODING, AND COMPACTION SHALL PROGRESS UNTIL THE REQUIRED FULL THICKNESS OF THE ABUTMENT BACKFILL HAS BEEN COMPLETED.
4"SUBDRAIN GEOTEXTILE
2 2 ( T Y P . )
WATER REQUIRED FOR FLOODING, SUBDRAINS, POROUS BACKFILL, FLOODABLE BACKFILL, AND GEOTEXTILE FABRIC FURNISHED AT THE BRIDGE ABUTMENTS WILL NOT BE MEASURED SEPARATELY FOR PAYMENT.
4" SUBDRAIN
THE COST OF WATER REQUIRED FOR FLOODING, SUBDRAINS, POROUS BACKFILL, FLOODABLE BACKFILL, AND GEOTEXTILE FABRIC FURNISHED AT THE BRIDGE ABUTMENTS SHALL BE INCLUDED IN THE CONTRACT UNIT PRICE BID FOR STRUCTURAL CONCRETE.
SECTION A-A
BACKFILL DETAILS
NOTE: GEOTEXTILE FABRIC WILL BE ATTACHED TO FACE OF ABUTMENT FOOTING AND WINGS. *DIMENSION VARIES DUE TO 2% SUBDRAIN SLOPE. ( TYP. ) 2 -2
Highway Division
STANDARD DESIGN - 44 ROADWAY, THREE SPAN BRIDGE
1 -6
04-1 2
ABUTMENT WING
2-2
H44-80-07
3/28/2012
8:42:04 AM
tsorens
W:\Highway\Bridge\NewStandards\April_2012_Release\H44-07.dgn
H44-80-07
11x17_pdf.pltcfg
2 -0
OF ABUTMENT
2 -0
BACK FACE
3 -0
POROUS BACKFILL
2 1