DCP - Phase 2 Programme of Works: Area 2 (DCO-DCU, DC12-DC16)
DCP - Phase 2 Programme of Works: Area 2 (DCO-DCU, DC12-DC16)
Activity Name Original Start Duration 138 01-May-13 84 01-May-13 36 01-May-13* Finish May 08-Oct-13 06-Aug-13 11-Jun-13 Jun Jul Aug 2013 Sep Oct Nov Dec Jan 08-Oct-13, DCP - Phase 2 Programme of Works 06-Aug-13, Area 2 (DCO-DCU, DC12-DC16) Formwork, Steel, Scaffold, Pouring 2014 Feb
19-May-13 18:01
Mar
Scaffold Removal 1
15 09-Jul-13
25-Jul-13
Scaffold Removal 1
Block Works 1
10 27-Jul-13
06-Aug-13
Block Works 1
7 26-May-13
02-Jun-13
Block Works 2
17 29-May-13
17-Jun-13
Block Works 2
45 07-Aug-13
28-Sep-13
(DCA-DCU) (DC12-DC16)
Backfilling
25 10-Sep-13 18 10-Sep-13
08-Oct-13 30-Sep-13
Dry Mix
7 01-Oct-13
08-Oct-13
Dry Mix
Summary
Oracle Corporation