Revision 1

ANNEX A-1 LABELLING OF METERS FOR IMPORT AND EXPORT 1. Active Energy Active Energy is considered to be imported when it flows to the power station from APTRANSCO System. The meter(s) registering this Active Energy should be labelled Import. Active Energy is considered to be exported when it flows from the Power station to APTRANSCO. The meter(s) registering this Active Energy should be labelled Export 2. Reactive Energy Reactive Energy is considered to be imported or exported as follows: Flow of Active Energy Power Factor Flow of Reactive Energy Import Lagging Import* Import Leading Export* Import Unity Zero Export Lagging Export Export Leading Import Export Unity Zero For the purposes of labelling of meters the conditions asterisked above will determine labelling where import for active Energy is defined as in 1 above.

Section 5

5A-1

June 2001

You might also like