Professional Documents
Culture Documents
Marc+Rullo+ +Water+Bath+Heater+Internal+Inspections
Marc+Rullo+ +Water+Bath+Heater+Internal+Inspections
Overview
What is a Water Bath Heater? My Project Heater H-03 Horsley Park Questions
Exhaust Stack
Control System
Source: Devco Process Heaters http://www.devcoheaters.com/indirect.htm
4
Heated Water
Pressure regulation downstream of heaters H-03 needs to be offline during the inspection
Project j Constraints
Customer
Gas delivery temperature was not to be below minimum allowable Ensure no impact on the Sydney distribution network.
Timing
Needed to be completed by 2011 to be compliant with AS2885
Project j Preparation p
Capacity study
Conducted process modelling Actual testing (i.e. isolating the heater on-site) Confirmed heater could be taken offline
Risk Assessment
Cranes on site Lifting above live pipe work Confined space entry P Possible ibl d damage t to process coil il
Development of Procedures
Job Hazard Assessments Safe Work Method Statements Development of a Contingency Plan
10
22mm Clearance
12
13
14
Project j Timing g
Estimated completion time was 4 days
2 additional days contingency for repairs
15
Pre-Work Planning g
Lifti Lifting plan l was agreed d to t with ith Crane operators. Heavy y duty y Scaffolding g set up p over live pipe work New bolts and gaskets procured New N end d plate l t gasket k t pre-drilled d ill d
16
Day 1
Day 2
Day 3
Day 4
17
Day 1
Day 2
Day 3
Day 4
18
Lifting of bundle above pipe work Left to rest on stands away from hazardous area
Day 1
Day 2
Day 3
Day 4
19
Day 1
Day 2
Day 3
Day 4
20
Day 1
Day 2
Day 3
Day 4
21
Day 1
Day 2
Day 3
Day 4
22
Day 1
Day 2
Day 3
Day 4
23
Day 1
Day 2
Day 3
Day 4
24
Day 1
Day 2
Day 3
Day 4
25
Day 1
Day 2
Day 3
Day 4
26
Day 1
Day 2
Day 3
Day 4
27
Replacement of endplate gasket Re Re-bolting bolting of endplate Reattachment of ancillaries and connecting pipe work Leak tested vessel and flanges Vessel was refilled
Day 1
Day 2
Day 3
Day 4
28
Reinstatement of Heater
Day 1
Day 2
Day 3
Day 4
29
Project j Success
No lost time due to injuries No impact on customer deliveries or capacity Delivered within the 4 day timeframe Delivered within the allocated budget Heater remains compliant with Standards
AS 2885 AS 3788
30
Key y Learnings g
Accurate project schedule Important! Crane lifting plan was critical Predrilled endplate gaskets Review drawings! Having a contingency plan in place Key!
31
Thank You
Questions?
ASSETS 100% OWNED & MANAGED BY JEMENA (Customers) 1 2 3 4 5 6 Jemena Electrical Distribution Network (305,000) Jemena Gas Distribution Network (1,020,000) Queensland Gas Pipeline Eastern Gas Pipeline VicHub Colongra Gas Storage and Transportation Facility
ASSETS PARTIALLY OWNED & MANAGED BY JEMENA 7 8 9 ActewAGL Gas, Electricity Network (50%) (151,000) United Energy Distribution (34 (34.1%) 1%) (600 (600,000) 000) TransACT (6.8%)
ASSETS MANAGED BUT NOT OWNED BY JEMENA 10 11 Tasmanian Gas Pipeline p Multinet Gas Holdings
COMPANIES WHO ARE PART OF THE JEMENA GROUP 12 13 14 CLM Infrastructure Outback Power Cape Cable Layers
32