Faculty of Engineering

Department : Structural Engineering Course : Construction Project Management Course Code : 8414 Class Exercise 8 1. Estimates and schedules when initially prepared assume unlimited resources: a. True b. False b. 2. Float is a useful tool for project management to use in order to level resources: a. True b. False 3. Which would not be considered a scheduling resource: a. People c. Equipment b. Money d. Laydown space : 4th Civil

4. A Precedence network for a project has the logic given in the following table. The resource rates for each activity are also given. It is required to: a- Level resource I and then draw resource histogram before and after leveling on the same diagram. b- Level resource II and then draw resource histogram before and after leveling on the same diagram. c- Level resources I and II simultaneously, and plot the histograms for both resources. Compare the results with those obtained form (a) and (b).

Activity A B C D E F G H K

Predecessors Duration --A A A A B C, D C, D, E F, G, H 2 8 6 4 3 12 4 6 3

Resource Rate Resource I 3 4 8 6 4 2 7 9 2 Resource II 1 6 6 5 1 0 9 5 0

Construction Management

Dr. Emad Elbeltagi

5. Consider the following project. Resources required Plumbers Labors 2 1 1 3 3 1 2 2 3 3 4 1 5 2 4 2 3

Activity A B C D E F G H I J

Predecessor B B C A, D E E F, I

Duration (days) 4 3 6 8 7 2 9 5 4 4

Assume eleven plumbers and nine labors are available for the project. Both resources must work at the same time when assigned to the same activity. Prepare an activity schedule which satisfies the resources constraints.

Construction Management

Dr. Emad Elbeltagi