Professional Documents
Culture Documents
Daily Operational Report: Ural Oil & Gas LLP
Daily Operational Report: Ural Oil & Gas LLP
WELL INFO
Supervisor: Chingis Nurliev / Amantay Ibragimov Logistics Supervisor: Sattar Karimov Engineer: Bela Kiss
STATUS
24 hr summary: SLB logging Run 1: Junk Basket. HUD @ 4451m. Set BP at 4390 m. M/U clean up tools. 5 5/8" bit + scraper + brush + magnet. Repair monkey board. Continue RIH 4 1/2" PH6 TBG to 1464 m. Meanwhile filtrate brine surface.
COSTS
Daily cost: 315,444 (USD) Authorized cost: 7,938,092.71 (USD) Cumulative total: 477,135 (USD) Expenditure: 6%
OPERATION SUMMARY
From 0:00 0:30 2:30 To 0:30 2:30 5:30 Dur. (hr) 0.50 2.00 3.00 MD from (m) MD to (m) Operation Continue SLB logging Run 1: Junk Basket. HUD @ 4451m. Start Correlation pass. +3.73m Depth Offset applied. SLB Logging. POOH. L/D Junk Basket. JB Clean. SLB Logging. Prepare Easy Drillable COPPERHEAD Bridge Plug for 7.00" 26-35 ppf casing, Arm the gun Distances: from CCL to MIDDLE of the seal element - 3.5m. From CCL to TOP of the PLUG - 3.15m. From CCL to BOTTOM of the PLUG - 3.8m. SLB Logging. RIH Bridge Plug @4390 m. SLB Logging. Correlation with witnessed UOG geologist and supervisor. Set BP at 4390 m. POOH and R/D WL unit. Start to filtered brine. After 30 minute of work, broken "Petro Unit" electrically pump filter. "Petro Unit" office sent another pump for replacement . M/U clean up tools. 5 5/8" bit + scraper + brush + magnet. ( 2nd clean up tools +/-2200 m ). P/U RIH 4 1/2" PH6 TBG to 1062. Delivery filter pump from "Petro Unit" warehouse and replacement. Meanwhile filtrate brine through filtration unit on surface. NTU @16:00 - 1000; @17:00 - 900; Zero rate applied as per the contract. Repair monkey board. Total downtime in July 8.25 hours. ( Reduced rate first 12hrs per month ). Continue RIH 4 1/2" PH6 TBG from mast 1062 m to 1464 m. Meanwhile filtrate brine through filtration unit on surface. @23:00 - 600; Time Type T2 T2 T2
T2 T2 T1
12:30 14:00
14:00 20:15
1.50 6.25
T1 T1
20:15 22:30
22:30 0:00
2.25 1.50
T2 T1
Continue RIH 4 1/2" PH6 TBG to 3330 m. Meanwhile filtrate brine surface. 50m3 of brine - NTU @ 150; In progress. RIH tandem casing clean-up tool. Circulate. POOH to 2nd clean up tool. RIH to BP.
MUD
Mud Desc: Mud density (sg) 1.220
BRINE
Viscosity (s/qt)
Gel
PV (cp)
YP (lbf/100ft? )
Cl(ppm) 180,000
Ca+ (ppm)
pH
ECD (kg/L)
9.0
HSE Status
DSLTI:
143 (days)
PERSONEL
Total No. of People: 73
Company No. People Company No. People
Baker-BJ SKGW for UOG SKGW Cathering Ural Oil & Gas Grand Activ
4 6 8 4 4
Petro Unit Fluid Engineering SKGW Batys Kuzet ITS Schlumberger Logging
2 27 7 4 7
REMARKS
00:00 - 02:45 Continue RIH 4 1/2" PH6 TBG from mast 1464 m to 2203 m. Meanwhile filtrate brine through filtration unit on surface. NTU @ 02:00 - 300; 02:45 - 03:45 M/U 2nd set of clean up tools. Scraper + brush + magnet.
July 06, 2013 at 8:01 am 1 OpenWells R5000, Kazah v1.1
REMARKS (Continued)
03:45 - 07:30 Continue RIH 4 1/2" PH6 TBG from mast 2209 m to 3330 m. 50m3 of brine - NTU @ 150; In progress. Transported liquid waste: (m3) (sg). Transported cumulative liquid waste: (m3). Transported factory waste: (ton). RIG Diesel Consumption: 3886 liter. Camp Diesel Consumption: 450 liter. RIG & Camp Stock: 72900 liter. Diesel Received: 31136 liter. Equipment to RIG SKGW-38: Equipment from RIG SKG: