Professional Documents
Culture Documents
Epa 5 Schedule: Earthmovement Works 3 Days
Epa 5 Schedule: Earthmovement Works 3 Days
Epa 5 Schedule: Earthmovement Works 3 Days
EPA 5 SCHEDULE
EARTHMOVEMENT WORKS SOIL GRADING & COMPACTION COMPACTION BY GATCHING MECHANICAL EXCAVATION FOR WELL FOUNDATION SLABS PREFABRICATED GUTTER AROUND THE SLAB SLAB CONCRETING SHUTTERING STEEL FIXING CONCRETING POLYETHYLENE SHEET CONCRETE REINFORCED WALLS SHUTTERING STEEL FIXING CONCRETING CONCRETE PREFEBRICATED BLOCKS SHUTTERING STEEL FIXING CONCRETING FACILITIES 35MM BARE COPPER CABLE FOR GROUNDING 16MM BARE COPPER CABLE FOR GROUNDING PLACEMENT OF INSPECTION BOX
31 days 3 days 3 days 3 days 2 days 3 days 2 days 3 days 3 days 2 days 1 day 2 days 3 days 3 days 2 days 1 day 3 days 3 days 2 days 1 day 2 days 2 days 2 days 1 day
07 Jul '13 S M T
14 Jul '13 S M T
21 Jul '13 S M T
28 Jul '13 S M T
04 Aug '13 S M T
11 Aug '13 S M
Deadline Progress