Process Train-1 (A100) Area A120 Large Bore Piping Erection around TGT Absorber (B19-C201)
Process Train-1 (A100) Area A120 Erected SRU Steam Drum (B19-V103) above Reaction Furnace
Process Train-1 (A100) Area A150 Erected Pre-Fabricated Tank (B19-T601) by CBI
Process Train-1 (A100) Area A150 (South) Piping Erection around Equipments
Process Train-2 (A200) Area A210 Steel Support Erection for AFC above Main PR
Common Process North (B100) Start of Piping Erection above Pipe-rack in Area B140
Common Process South (B200) Area B260 Erected Tanks for Sanitary Treatment Package (B87-Y071)
Common Process South (B200) Installed Instrument Panels inside BSIH-108 Bldg.
Utility (C100) Area Start of Piping Erection above B86-XS-51 Structure in Area C120
Cooling Tower Area (C230) Piping around Fresh Cooling Water Cooler
Cooling Tower Area (C230) Cooling Tower Piping Erection at South Side
Building Area (C320) Warehouse Area of BXK-05 Wall Cladding & Roofing
Building Area (C320) Erection of Overhead Crane inside BXK-05 Warehouse Area by DESCON
Area D210: Piping Erection & Welding above PR-44 for Sulfur Line