ER420QP- Qualified Person (Supervision) for Contract ER420-New Link in Between Upper Changi Rd and Upper Changi Road East DAILY SITE REPORT
Client Main Contractor Day / Date Working Hours s/N 1 Location Upper Changi Road LAND TRANSPORT AUTHORITY ULT CORPORATION Thursday / 7 March 2013 0830-1800 Chainage MCO2 170 MCO2 100 West Bound Nature of Works Trial Hole to find the alignment of 500mm Dia. Asbestos Pipe Noise Meter- Chainage 100 MCO2 West Bound: Noise Monitoring Meter Installed inside the working Area. Soon Will be relocated Nearer to Residential Houses Site Office Window Grill Works Weather Condition Dry 0800-1800hrs Alfredo Claro Drizzle Rain RTO Time (Hrs) 0800-1800 Remarks
0800-1800
Site Office
0800-1800
New Road
NR 130
0800-1800
Trial Trench-Chainage MCO2 170 : To Locate alignment of 500mm Diameter Asbestos Pipe
Noise Meter- Chainage 100 MCO2 West Bound: Noise Monitoring Meter Installed inside the working Area. Soon Will be relocated Nearer to Residential Houses
ECM (Earth Control Measure) Machine: ECM Machine in Place to contain Silty Water not going into the Public Drain
Site Clearing- New Road- Chainage NR 130: Site Clearing and Disposal works