Professional Documents
Culture Documents
Constantino Suazo
Constantino Suazo
Constantino Suazo Alejandro Hofmann Marcelo Aguilar Yuan Tay Gustavo Bastidas
INTRODUCTION
Collahuasis value optimization is introduced in a simplified manner using the following graphics. The main idea behind the approach is to develop robust grinding and flotation models that allow a proper estimation of the point at which copper production per unit of time reaches a maximum.
6000
Throughput tph
2000
A robust grinding model should include variables such as: Geological Units Blend P80 Grinding Circuit Features Maintenance Plan
0 50 100 150 P80, microns 200 250 300 350
80
Recovery (%)
60
40
20
In general recovery increases as P80 decreases. A robust flotation model should include variables such as: Headgrade Geological Units Blend P80 Flotation Circuit Features
0 P80, microns
100
80 6000
4000 60 2000 0 40
Flotation P80
Flotation P80
Grinding P80
P80, microns
Grinding P80
Recovery (%)
60000
40000
20000
The correct P80 is a balance between high throughput and high recovery; however, it is neither flotation P80 nor grinding P80. It is the Business P80
0 P80, m icrons
Flotation P80
Business P80
Grinding P80
Throughput
Mineralization
Alteration
DEFINITION CRITERIA: Representative geological units. Grouping based on similar geological features (mineralization, lithology, alteration). Intersection of these geological features.
GMU
1 2 3
G M U
% 18 26 19 25 7 5 100
Lithology
4 5 6
Total
Every 40 mt, a 8m length drill core sample was selected as a variability sample
To Assay
HQ Sample preparation
1/2 To Assay
Duplicate
Duplicate
GMU
1 2 3 4 5 6 The following laboratory tests were performed on each variability sample: SMC (DWI, A, b , Axb) Ball mill Wi SPI Specific gravity Abrasion Crush index Full JK DWT (on composite samples)
SAMPLE TYPES
1. COMMINUTION TEST ON EACH GMU: COMPOSITES
Comminution test Mass Required (Kg) (20cm length samples every two meters of drill core) ----Drill hole diameter
PQ
PQ y HQ
HQ
Variability Samples Number of SMC, DWi UGM1 UGM2 UGM3 UGM4 UGM5 UGM6 Samples 87 50 133 138 37 56 Simple average 5.1 6.6 5.6 6.8 4.0 4.6 Standard Deviation 1.5 2.1 1.7 2.0 1.8 1.7
2.- SAG Mill was simulated using JKSimMet. For each iteration, the SAG mill power draw, total load and transfer size were recorded as shown in the table below. 3.- The transfer size and the instantaneous throughput were fed to the Bond equation to predict the P80.
SAG
tph
KW
Ball Mill
tph T80
4.- The iterative process continued until one of the following restrictions were met: 1) Maximum Power Draw = Installed Power 2) Maximum SAG Mill Total Load = 30%
P (KW)
Line 1-2: 1* 32ft *15ft SAG Mill (8000 KW) + 1* 22ft*36ft Ball Mill (9700 KW) Line 3: 1* 40ft *22ft SAG Mill (21000 KW) + 2* 26ft*38ft Ball Mill (15500 KW)
TPH versus P80 curve Bond Equation Ball Mill Power Draw (KW) 14812 14812 14812 P80 estimated from Bond Equation, microns 100 200 241
JKSimMet Simulations Iteration N 1 2 3 tph 2800 4300 4800 Power Draw KW 17605 18600 18900 Transfer Size (T80 um) 3778 4737 4944
GMU 3 GMU 4
C1 C2 C3 C4 C5
80
GMU 5 GMU 6
60
40
SAMPLE C1
20
C2 C3
C4 C5 AVERAGE
4,000
GMU 3
2,000 0 90
GMU 5
110 130 150 170 190 210 230 250 270 290 310 330 350 370 390 P80 (microns)
Ton (P80) : Total processed tonnes per period. H: Total hours in the period Hm l i : Programmed maintenance hours in grinding line i Hf l i : Un-programmed maintenance hours in grinding line i N l i : Number of shut-downs within the period H t : Transient time to achieve stable operation after shut downs PT tchp: Treatment losses due to Crusher Pebbles shut downs Hmchp: Crusher Pebbles Programmed maintenance hours Hfchp: Crusher Pebbles Un-programmed maintenance hours
Observed (tons)
1,600,000
Modelled
1,400,000
1,200,000
tonnes
1,000,000
800,000
600,000
400,000
200,000
%Error = 4.5%
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121 126 131 136 141 146 151 156 161 166
weeks 2007-2011
1,800,000
1,600,000
1,400,000
1,200,000 60% 1,000,000 50% 800,000 40% 600,000 30% 20% 10% 0%
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121 126 131 136 141 146 151 156 161 166
400,000
200,000
Tonnes
-
weeks 2007-2011
%Error = 4.5%
1.400.000
Modelled (tons)
1.200.000
1.000.000
800.000
600.000
400.000
200.000
200.000
400.000
600.000
800.000
1.000.000
1.200.000
1.400.000
1.600.000
Observed(Ton)
1.800.000
CONCLUSIONS
The grinding modelling currently used by Collahuasi Mining Company has been presented showing an updated validation of the predictive capacity of the total treated ore per week from September 2007-May 2011. The aim of developing a robust and accurate forecasting model has been satisfactorily achieved through the use of a combination of simulation and power-based modelling. The model has shown an average relative error of 4.6% as inferred from the statistical analyses using production data from the period September 2007 to June 2011 The Collahuasi grinding modelling allows planning engineers to maximise grinding circuit treatment capacities on the basis of appropriate blending of GMU and also on the basis of the concentrator's maintenance program.
THE END