Detail Dumping Sites KN
Detail Dumping Sites KN
Project Component Quantity of Additional Total quantity of Estimated quantity Estimated quantity muck/ debris Quantity of muck muck/ debris of muck/ debris of muck/ debris generated as due to 45% swell including swell proposed to be proposed to be per DPR factor factor utilized dumped Name of the dumping site as shown in the plan Dimension of the dumping site Area in Sqm Average Height of dumping Remarks
1 Diversiom Weir (500) Conveyance (500) Tunnel (1560) Forebay & Penstock (970) Power House (1500) 500 500 1560
9=5/8
10
Dumping Site-I
35 x 20
700
3.2
570
257
827
331
496
Dumping Site-2
20 x 10
200
2.5
400m3 muck to be sent to Dumping site-3 Total=570m3 400m3 muck will be come from Dumping Sute-2 Total=1900m3
1900
855
2755
1102
1653
Dumping Site-3
40 x 60
2400
0.7
mping Site-6