PMP 54formulas V1
PMP 54formulas V1
GroupQUALITY-
Formulas
CoQ = (( Review Efforts + Test Efforts + Training Efforts + Rework Efforts + Efforts of Prevention) / Total Efforts) x 100% PERT = (0+4ML+ P)/6 MEAN -> Average MODE -> The "most found" number RANGE -> Largest - Smallest Measure MEDIUM -> No in the middle or avg. of 2 middle Nos STD, DEV. OF TASK = (P 0)/6 TASKVAR. = (P-0)2/6 = (Std.Dev)2 CP STD. DEV. = 2 + 2 + 2 SIGMA 1 = 68.26%
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Communication
PERT MEAN MODE RANGE MEDIUM STD DEV of TASK TASK VARIANCE CP. STD. DEV. SIGMA
2 = 95.46% 3 = 99.73% 6 = 99.99985% COMMUNICATION CHANNELS = (N2-N)/2 = (Nx(N-1))/ 2 90% PV = FV/(1+r)n FV = PV x(1+r) NPV = S ( PV + PV + PV + PV ) --- --- --- -- -- -------(1+r)n (l+r)n (1+r)n (1+r)n or NPV=FV/(1+R) n
> best
19 20 21 22 23 24 25 26 27 Class of Estimates
Cash Flow = Cash Inflow - Cash Outflow Discounted Cash Flow = CF x Discount Factor ARR = S Cash Flow / No. of Years ROI = (ARR / Investment) * 100 % BCR = Benefits/Cost; > best and > 1 has benefits Exp. Value = Probability % x Consequence $ Definitive Capital Cost Appropriation +5% +10-15% +15-25%
28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
Estimating- Definitive: Bottom Up
Feasibility
+25-35%
Order of Magnitude > +35% Contract Incentives Savings = Target Cost ~ Actual Cost Bonus = Savings x Percentage Contract Cost = Bonus + Fees Total Cost = Actual Cost + Contract Cost EARNED VALUE ANALYSIS PV (Present Value) = BCWS (Budgeted Cost of Work Schedule) EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) CV = EV - AC CPI = EV /AC (efficiency) SV = EV - PV SPI = EV / PV ETC=BAC-EV or (BAC-EV)/CP( EAC = AC + ETC EAC=BAC/CPI VAC = BAG - EAC % COMPLETE = EV / BAC x 100 % SPENT = AC / BAC x 100 CV% = CV/EVx100 SV% = SV/PVx100 Budgetary/Top down/Analogous Rough Order of Magnitude Risk Time Total Float Free Float -5% ~ +10% -10% ~ +25% -25% ~ +75% Expected Monetry Value=Probability x Impact LS-ES or LF-EF Successor (ES) Activity (EF) -