Redosled Montaže SKELA

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

4.

REDOSLED MONTAE

1. Prvo se formira skela na betonskoj povrini kote +17.710m do ispod eline platforme na koti 24.475m. 2. Radne platforme formiraju se na kotama +19.96 i +22.21m. 3. Skelu ukrutiti za obodne stubove. 4. Drugi deo skele formira se nezavisno sa platforme +24.475. 5. Radne platforme postavljaju se na kote 26.47 i 28.47. 6. Skelu ukrutiti za obodne stubove.