Weekly Status of Work
Weekly Status of Work
Weekly Status of Work
PROJECT NO. Numar proiect : SITE Santier : Nr. NAME OF WORK crt Denumire lucrari 1 Organizare de santier 2 Fundatii rezervoare 3 Montaj rezervoare 4 Fundatii pavilion comercial 5 Fundatii copertina 6 Fundatii spalatorie "Top wash" 7 Fundatii spalatorie deschisa "Jet wash" 8 Instalare pavilion comercial METALUX 9 Montaj copertina METALUX 10 Montaj spalatorie "Top wash" 11 Montaj spalatorie deschisa "Jetwash" 12 Instalatie tehnologica de descarcare + teste 13 Instalatie tehnologica de tragere + teste 14 Instalatie tehnologica de aerisire + teste 15 Insule pompe 16 Trasee conducte tehnologice 17 Instalatii electrice , paratrasnet , telefon 18 Canalizare 19 Alimentare apa , aer comprimat 20 Pavaje , platforme 21 Trotuare 22 Montaj separator + rigola 23 Racord apa potabila 24 Racord canalizare menajera si pluviala 25 Racord gaz metan 26 Racord telefon 27 Racord energie electrica 28 Montaj pompe si calculatoare 29 Amenajare spatii verzi 30 Imprejmuire 31 Iluminat public 32 Montaj R.V.I. 33 Montaj echipament frigorific HAUSER START DATE
PLANNED REAL
WEEK NO. Nr.saptamina : SUPERVISOR : ing. Liviu Sterian STATUS OF WORKS FINISH DATE REMARKS Observatii
10% 20% 30% 40% 50% 60% 70% 80% 90% 100% PLANNED REAL
34 35 36 37 38 39
Montaj mobilier Montaj echipamente bar Montaj Totem si semnal luminos mare Calibrare rezervoare Descarcare combustibil Deschidere statie