Restructuring of Keene Elementary Schools

October 1, 2013

Marinace Architects

Where We Are Now


In the spring, the Keene Board of Education requested that the design team develop detailed engineering drawings of the proposed additions and renovations Engelberth Construction, the selected estimator / construction manager for the project, would use these detailed drawings to provide an accurate cost estimate Today we will review the results of this work

10-1-13

KES restructuring Marinace Architects

Work Completed this Summer


Architects met with school staff & administration to finalize floor plans and space details Site surveys completed of Symonds, Franklin, Fuller Geotechnical engineering studies completed Met with Keene Fire Dept. representatives for input Met with NH Dept. of Education and received approval Structural, Mechanical, Electrical engineers analyzed existing systems in all schools to determine necessary upgrades and to integrate new work Site work grading, drainage, water lines designed Comprehensive design documents completed Detailed cost estimates completed

10-1-13

KES restructuring Marinace Architects

Floor Plans: Symonds

10-1-13

KES restructuring Marinace Architects

Floor Plans: Franklin

10-1-13

KES restructuring Marinace Architects

Floor Plans: Fuller

10-1-13

KES restructuring Marinace Architects

Floor Plans: Wheelock

10-1-13

KES restructuring Marinace Architects

Floor Plans: Daniels

10-1-13

KES restructuring Marinace Architects

Work Included In Project


Renovated areas shown as Blue in the floor plans Additions shown as Green in the floor plans Site work associated with the additions New sprinkler systems at all 5 schools New water lines to three schools to serve sprinklers Heat conversion from steam to hot water in all schools Mechanical upgrades to all schools to replace obsolete fans and equipment, and to provide code-mandated fresh air to all classrooms (no fresh air in many now) New DDC controls to regulate classroom temperatures Fire alarm, emergency lighting upgrades to meet current code
KES restructuring Marinace Architects 9

10-1-13

Project Budget

10-1-13

KES restructuring Marinace Architects

10

Projected Project Savings

10-1-13

KES restructuring Marinace Architects

11

10-1-13

KES restructuring Marinace Architects

12