ANALYSIS of the proposed $70 million to $85 million Police Addition plus Seismic retrofit.
THE CITY'S ROUGH SKETCH OUTLINE OF THEIR PROPOSAL SUPERIMPOSED ON AN AERIAL PHOTO
There was no involvement of the people of Salem in these overly expensive plans
YOU WILL SEE THE FOLLOWING EXPENSIVE & DISRUPTIVE IMPACTS ON OUR CIVIC CENTER 1. PEACE PLAZA IS TO BE REDUCED IN SIZE !
and City plans to REMOVE sculpture, peace plaques, grand staircase, all mature trees on either side, so our Peace Plaza apparently becomes a hole in the ground while a basement parking garage is constructed below.
4. COUNCIL CHAMBERS IS REBUILT ! as an East Wing of City Hall with Public Works offices, and Courts.
This removes ALL the mature trees at east end of Peace Plaza, and the grand staircase. We love our Plaza the way it is !
5. POLICE PARKING GARAGE ! is constructed underground all the way from Mirror Pond to the Library.
Designed to accommodate 210 cars. The rule of thumb is $20,000 per parking space. So $40 million ? TOO EXPENSIVE !
WE SAY YES TO POLICE FACILITY AND YES TO A $20M SEISMIC RETROFIT BUT WE SAY NO TO MESSING WITH OUR PLAZA, CHAMBERS, LAKE FOR $40 MILLION MORE
The bond issue maybe will be $85 million if they add seismic reinforcement of the Public Library.
Eugene just built their 60,000 sq.ft Police Facility with 200+ spaces for under $17 million! So Let's find a site or a building ! Save $40M ! It's too expensive to force it at our City Hall !