Progress Report NHA Punjab North
Progress Report NHA Punjab North
Km 1630
Murree
N-75
Rawalpindi (1540)
ISLAMABAD (00)
Sohawa (1473) Jhelum (1432)
Kharian (1412) Gujrat (1380) Wazirabad (1362)
N-80
M-1
Chakri (316)
M-2
N-5 E-3
Gujranwala (1328)
M-3
Ramak (872) Km (868) Sahianwala (32) Millat (48) Faisalabad M-3 (53), E-4 (0)
M-2
LAHORE (1260)
Thokar Niaz Baig Manga (1220) Bahi Pheru (1204) Pattoki (1180) Renala Khurd (1151) Okara (1134) Sahiwal (1102)
N-55
Retra (824)
E-4
N-70
Bewata (181)
E-5
Muzaffargarh (32)
Lar (915) Lodhran N-5 (860), E-5 (100) Bahawalpur (844) Nurpur Nauranga (814)
National Hig hway/Strateg ic Road Expressway Road Proposed for Federalization Motorway (Operational) Motorway (Under construction)
M-5
Jampur (668)
N-55
Rajanpur (604)
N-5
Ahmedpur East (792) T. M. Panah (756) Khan Bela (734) Zahirpir (707) Sardar Garh (693)
M-6
Motorway (Planned) National Capital Provincial Capital City/Town Interchang e Province Boundary River
Kashmor (495)
Km 608
PUNJAB
Road/ Bridge 1. 2. 3. Sutlej Chena b N-5 Project/Section Musa Pak Shaheed Bridge Head Muhammadwala Bridge Jinnah Chowk - Bahawalpur Chowk Km 0.6 1 8 PC-1 Cost 2130 2508 1078 Contract Cost 1616 712 (P1) 405 (P2) 970 (P3) 234 (P1) 532 (P2) 513 PSDP 2012-13 150 50 70
Rs in Million
Progress Expected Completio n
4.
Sutlej
8.6
1108
24
Subst. Completed
5. 6.
N-5 IMDC
1.27 42
873 3414
70 50
7.
N-5
1.1
888
RMA
90%
Jun-2013
8.
Nag Shah Chowk Flyover (4-Lane) Khanewal- Multan Inter District Road (Bosan Road) (2x Packs)
1530
1259
74%
Jul-2013
9.
7.5
4570
750
79%
Jul-2013
(Return)
PUNJAB
Road/ Bridg e
10.
Link to Jinnah Chowk
Rs in Million
Contract Cost PSDP 201213
200 Progress Expected Completion
K m --
PC-1 Cost
1204
1204 1566 (Pack-3) 770 (P1) 570 (P2) 572 (P3) 929
11.
Tri District Link (Jalalpur Pirwala Uch Sharif) (total 3x packs,2 completed)
Sultan Bahoo Bridge (Shorkot - Garh Maharaja) (4x Packs)
42
3171
550
Sep-2013
12. 13
1603 5459
150 70
Dec-2013 Jun-2014
14 15 16 17
50 -500 1000
18
22
809
211
300
13%
Jul-2013
(Return)
PROJECTS IN KP
N-35
Chitral (309) Gilgit (540)
Khunjrab Pass (806) Sust (720) Passu (683) Gulmit (669) Aliabad (630) Rahimabad (570) Sassi (26) Shangash (51 Dambu Das (102) Bagicha (114)
N-95
Pattan (257)
S-1
Skardu (167)
N-45
Tamergara (129) Chakdara N-45 (91), N-95 (0) Batkhela (81) Malakand (74) Sher Ghargh (52)
N-90
Batgram(165)
Mansehra N-15 (0), N-35 (94) Swabi (72) Abbottabad (70) Haripur (33)
Hatian
S-3
Chakothi (55)
Torkham (1756)
N-5
Nowshera
N-5 (1700), N-55 (1264) M-1 (155) Dara Ademkhel (1220) Kohat N-55 (1196), N-80 (146) Lachi (1169) Latambar (1101) Bannu (1073)
PESHAWAR
Kohala (0)
S-2
Srinagar
N-35
ISLAMABAD
N-80
N-55
Pezu (990) Yarik (964)
Road Proposed for Federalization Motorway (Operational) Motorway (Under construction) Motorway (Planned)
Daraban (467)
N-50
Dhanasar (388)
KHYBER PAKHTUNKHWA
Road 1. 2. N-15 N-15 Project Naran - Jhalkhad Jhalkhad - Babusar Top - Chillas (2x Sections) Km 43 66 PC-1 Cost 5345 4017 Contract Cost 1369 1206 (P1) 1313 (P2) 212 (Ghazi) 148 (Chach) 259 (Capt. Col Sher Khan) 1205 (N-5) 5450 2219 981 4341 917 3518
Rs in Million
PSDP Expected Progress 2012-13 Completion 50 175 Subst. Completed 75% Sep-2014
3.
M-1
1067
50
80%
Jul-2013
4. 5. 6. 7. 8. 9.
Lowari Tunnel Peshawar Northern Bypass (Pack-I) Khushalgarh Bridge (Pack-I, Indus)
9 7.6 2.9 73 30 37
Pak Torkham Jalalabad ACW Afghan N-45 KKH Takht Bhai Shergarh-Dargai Shatial Thor Nala Bypass (KKH)
(Return)
Rs in Million
Progress Expected Completion
1.
2. 3. 4. 5. 6. 7. 8. 9. 10. 11.
61
20 14.7 52 28 20.5 29 84 18 34 32
4000
1419 847 1385 3041 829 1043 3300 3683 1214 10443
250
100 100 400 500 70 250 350 500 250 1200 Completed, Inaugurated by President of Pakistan 82% 72% 38% 74% 59% 35% 74% May-2013 June-2013 Sep-2013 May-2013 Jun-2013* Dec-2013 Dec-2013
Completed, Inaugurated by President of Pakistan on 28th Dec, 2012
N-455
BALOCHISTAN
Road/ Bridge 1 2 3 4 5 6 N-65 N-65 N-10 N-65 N-70 M-8 Project/Section Nuttal - Sibbi Dhaddar Jacobabad & Dera Allahyar Lyari- GwadarGabd (MCH) Kolpur Bypass Waigum Rud Khajuri Gwadar -TurbatHoshab (3 Packs) KhuzdarRatodero (3 Packs) Hoshab- Basima - Sorab Km PC-I Cost 3,262 671 17,262 696 3473 18379 Contract Cost P-I 1,575 P-II 452 P-III 180 526 PSDP 201213 5 5 175 116.7 750 3302.5 Date of start Dec-01 Jun-03 Jul-00 Dec-10 Sep-07 Sep-04
13,886
659 1331 P-I 2494 P-II 3687 P-III 3166 P-I 2207 P-II 1908 P-III 2306
7 8
M-8 N-85
143 454
6672 22412
1100 1100
Apr-04 Sep-07
73% 22%
Dec-2013 Jun-2014
17,454
(Return)
ISSUES Delay in completion of the projects is mainly due to: Shortage of Funds. Law & order issues (Balochistan Projects). Land Acquisition problems.
Khanewal
Multan
Shujaabad
Jalalpur Pirwala
Lodhran
Bahawalpur
Ahmedpur East
DISTANCE SAVING 41 KM 10
CONSTRUCTION OF TWO LANE MOOSA PAK SHAHEED BRIDGE AND APPRACH ROADS OVER RIVER SUTLEJ AT AIMANWALA, DISTT. BAHAWALPUR
Length PC-I Cost Contract Cost PSDP Allocations Consultant Contractor Date of Start Date of Completion Overall Progress (Actual) (KM) (Original) (Revised) (Original) (Revised) (2012-13) : : : : : : : : : : : 610 m (approach length 2.8 km and 1.7 km) Rs. 1,148 M Rs. 2,131 M Rs. 1,415 M Rs. 1,616 M Rs. 150 M M/s REC (Pvt.) Ltd M/s Karcon / Mishal Sania (JV) Jul - 2009 May 2011 Subst. Completed
(Original)
Current Status:
Project completed and open to traffic.
Atharan Hazari
Layyah
Chowk Azam
Chaubara
Garh Maharaja
2.4km 1.5km 11km
Shorkot
Abdul Hakim
Kabirwala
Khanewal
Existing Sher Shah Bridge
N-70
Muzaffargarh
DISTANCE SAVING 40 KM
CONSTRUCTION OF TWO LANE BRIDGE OVER RIVER CHENAB AT HEAD MUHAMMAD WALA DISTT. MULTAN
Length (KM) : 1.010 Km (Bridge) 3.34 Km (Right Approach) 7.37 Km (Left Approach) Rs 2,377 M (Global) Rs 2,508 M (Global) Rs. 50 M (Global) Rs 755.638 M (Pkg-I) Rs 457.117 M (Pkg-II) Rs 940.742 M (Pkg-III) Rs 712.078 M (Pkg-I) Rs 405.568 M (Pkg-II) Rs 907.74 M (Pkg-III) M/s EA Consulting M/s GRC (Pkg-I) M/s Hidayatullah & Co. (Pkg-II) M/s Zarghoon (Pkg-III) Jun - 2009 Dec 2011 Completed (All packages)
: : : :
(Revised)
Consultant Contractor
: :
(Original) (Actual)
: : :
N-5
N-5
14
(Revised)
Consultant Contractor
:
: :
: : : : :
LOCATION OF BABA FARID BRIDGE ACROSS RIVER SUTLEJ LINKING PAKPATTAN WITH MINCHINABAD
OKARA
Dipalpur
PAKPATTAN
Arifwala
Mandi Burewala
VIHARI
MINCHINABAD
Chishtian Mandi
Annex-A
Hasilpur Harunabad
BRIDGE OVER RIVER SUTLEJ CONNECTING PAKPATAN WITH MINCHINABAD (BABA FARID BRIDGE)
Length PC-I Cost PSDP Allocations Contract Cost Consultant Contractor Date of Start Date of Completion (Original) (Revised) (2012-13) (Original) (Revised) : : : : : : : : : : : : : 572 Meter (Main Bridge) 8 Km (Approach Road) Rs. 453.6 M Rs. 1,108 M Rs. 24.128 M Rs. 912.575 M Rs. 913.470 M M/s EA Consulting (Pvt) Ltd M/s Kingcrete Builders Feb-2008 Jan-2010 Sep-2010 Jan-2010 87 % (Subst. Completed)
Peshawar
Hattar Road
: : : : : : : : : : : : :
1.286 Km (Barrel 127 m, Underpass 760 m) Rs 493 M Rs 993 M (Approval under process) Rs 758.966 M Rs 872.500 M Rs 70 M M/s EA Consulting M/s GRC Dec - 2008 Jun - 2010 Feb - 2011 Oct - 2011 Subst. Completed
Jhika Gali
ISLAMABAD MUZAFFARABAD DUAL CARRIAGEWAY SATRA MILE TO LOWER TOPA SECTION (N-75)
Length PC-I Cost Contract Cost (KM) (Original) (Revised) (Original) (Revised) (2012-13) : : : : : : : : : : : : 43Km Rs 8,242 M Rs 12,666 M (approval under process) Rs 2,187 M Rs 3,414 M Rs 200 M M/s NESPAK M/s HAKAS Sep - 1999 July - 2001 Dec - 2010
Subst. Completed
(Original) (Actual)
Project Status: Project Section (Km 0 ~ 33) Project Section (Km 33 ~ 43)
: :
Operational since May, 2008 (Taken over by Operation Wing NHA) Operational since Jan, 2011
: : : : : : : : : : : : : :
330 M 359 M 689 M 850M Rs. 996 Million (under process) Rs. 498 Million Rs. 888.9 Million (VO # 1 yet to be concurred by Finance wing) M/s KNK M/s REC Nov-09 Feb-11 Sep-13 Nil (RMA Funded) 90%
: : : : : : :
: : : : :
Overall Progress
7.5 Km Rs 4570.022 M (Global) Rs 750 M (Global) Rs 460.82 M (Pkg-IA) Rs 530.60 M (Pkg-IB) N/A M/s Loya / Zeeruk M/s Khalid Rauf & Co. (Pkg-IA) M/s FWO (Pkg-IB) Mar - 2011 Oct - 2011 Mar 2013 Jul- 2013 75% (Pkg-1A) 87% (Pkg-1B)
Pending liabilities.
Flyover
Jinnah Chowk Rasheedabad Chowk Chungi 8 Chungi 9 Kalma Chowk Double Phatak Total
Rs in M
1204
Progress
Completed Completed
1210
1597 4011
Completed
Completed
III.
(Revised)
Consultant Contractor
: :
Rs. 1209.45 M (Pkg-II: Flyover at chungi # 8&9) Rs. 1262.19 M (Pkg-III: Flyover at Kalma chowk & Double phatak chowk) Rs 1203.72 M (Pkg-I) N/a (Pkg-II) Rs. 1596.07 M (Pkg-III) M/s EA (Pvt.) Ltd. M/s RMC (Pvt.) Ltd (Pkg-I)
M/s Maqbool Associate (Pkg-II) M/s Sarco-MSL (JV) Pkg-III)
(Original) (Actual)
Overall Progress
: : : :
Feb - 2010 Aug - 2011 Jan - 2013 Subst. Complete (Pkg-I) Subst. Complete (Pkg-II) Subst. Complete (Pkg-III
Khanewal
Shujaabad
Jalalpur Pirwala
Aminwala Bridge
Lodhran
Bahawalpur
JALALPUR PIRWALA UCH ROAD (N-115) (REHABLITATION/UP GRADATION OF TRI DISTRICT LINK, SOUTHERN PUNJAB)
Length PC-I Cost PSDP Allocations Contract Cost (KM) (Original) (Revised) (2012-13) (Original) : : : : : 42 Km Rs 2,289.29 M (Global) Rs 3,171 M (Global) Rs 550 M (Global) Rs 641.849 M (Pkg-I) Rs 774.633 M (Pkg-II) Rs 1,565.570 M (Pkg-III) Rs 827.526 M (Pkg-I) Rs 796.692 M (Pkg-II) N/A (Pkg-III) M/s ACC M/s Friends Enterprises (Pkg-I) M/s RMC (Pkg-II) M/s SKB (Pkg-III) Dec - 2009 Nov - 2010 Jun - 2012 Sep - 2013 Subst. Complete (Pkg-I) Subst. Complete (Pkg-II) 44% (Pkg-III)
(Revised)
Consultant Contractor
: :
Overall Progress
: : : : :
JHANG
LAHORE FAISALABAD
GARH MAHARAJA
SHORKOT
PROPOSED BRIDGE
CONSTRUCTION OF BRIDGE ACROSS RIVER CHENAB LINKING SHORKOT AND GARH MAHARAJA
Length (Package-I) (Package-II) (Package-III) : : : : : : : : : : : : : : : : : : : 855 M 3.2 Km 4.097 Km Rs. 1603 M Rs. 150 M Rs. 770 M (Main Bridge) Rs. 678 M (Revised) Rs. 570 M (Garh Maharaja Side Approach Rd) Rs. 572 M (Shorkot side Approach Road & Drainage & Erosion Work) M/s REC (Pvt) Ltd M/s SARCO-Mishal Sania (JV) M/s Hidayat-Ullah Khan & Co. M/s Friends Enterprise &HNAC (JV) June, 2010 September, 2010 September, 2011 Dec, 2013 (Expected) 76 % 42% 40 %
(Original) (2012-13) (Package-I) (Package-II) (Package-III) Supervisory Consultant Contractor (Package-I) (Package-II) (Package-III) Date of Start (Package-I) (Package-II) (Package-III) Date of Completion Overall Progress (Package-I) (Package-II) (Package-III) Issues & Impediments:
Project suffered due to paucity of funds and resultant delay in payment to contractors.
SHAHEED BENAZIR BHUTTO BRIDGE OVER RIVER INDUS LINKING N-5 WITH N-55 AT NISHTAR GHAT
PC-I Cost PSDP Allocations Contract Cost (Original) (2012-13) (Package-II) (Package-III) : : : : : : : : : : : : Rs. 5459 M Rs. 70 M Rs. 929 M (Main Bridge) Rs. 594 M (Approach Rd Zahir Pir To Chachran Sharif) M/s EA Consulting (Pvt) Ltd M/s REC (Pvt) Ltd M/s FWO (Main Bridge) M/s RMC (Approach Rd ZP to CS) Jan 2012 Jun 2014 35% (Main Bridge) 30% (Approach Rd ZP to CS)
Design Consultant Supervisory Consultant Contractor (Package-II) (Package-III) Date of Start Expected Date of Completion Overall Progress (Package-II) (Package-III)
Current Status: Procurement of approach road from Rajanpur & River bed approx. 18 Km and Guide Banks / Training Works yet to be completed.
CONSTRUCTION OF 2 LANE LINK ROAD FROM HEAD MUHAMMAD WALA BRIDGE TO BAND BOSAN ROAD
PC-I Cost (Original) PSDP Allocations (2012-13) Contract Cost Supervisory Consultant Contractor Date of Start Date of Completion (Original) (Expected) Overall Progress Project Status: Substantially completed. : : : : : : : : : Rs. 189 M N/A Rs. 189 M M/s EA Consulting (Pvt) Ltd M/s Hidayat Ullah Khan & Co. Dec 2011 Jun 2012 Dec-2012 Subst. completed
PSDP Allocations PSDP Allocations Consultant Contractor Date of Commencement Date of Completion (Original) (Revised) (Expected) Overall Progress (Actual) Present Status:
Project is completed in Dec-2012.
KHUNJERAB (806)
Ht 14000 ft
Jhalkhad Babusar
Babusar Top-Chillas Total
29
38 230
1206
1643 6959
68%
82%
HASSANABAD (624)
DANYORE(545)
KKH
BARSEEN (307)
Chillas
(417)
JAGLOT (500)
TATTAPANI (468)
DASSU (290)
PATTAN (257)
RAIKOT
BESHAM (218)
Kaghan (99)
THAKOT (190)
BATGRAM (160) DHODIAL
HAZARA UNIVERSITY
Ganool (57) 8 Kms Balakot (40) Attarshisha (14.5) GARHI HABIBULLAH (28) 12 Kms MUZAFFARABAD (62) LEGEND
PROPOSED ALIGNMENT
Mansehra
HASSAN ABDAL (0)
: : : : : : : : : : : :
28.5 Rs. 4,017 M Rs. 977M Rs. 1206 M Rs. 175 M M/s REC M/s FWO Oct-2004 Dec-2006 Dec-2010 Dec-2014 68.4%
: : : : : : : : : : : :
38 Rs. 4,017 M Rs. 1313M N/A Rs. 175 M M/s REC M/s FWO Jan-2005 Dec-2006 Dec-2010 Dec-2014 82.5%
North & South access roads (18 km) completed in 2007 & 2009
Rail Tunnel converted into Road Tunnel PC-I cost is Rs 18 B Physical progress is 45%
SNOW
NORTH PLATFORM
SOUTH PLATFORM
Lowari Top
Baradam Bridge
South Platform
Highway Tunnel (1900 M) Highway Tunnel Bridge North Link Access Road (4 Km) North Link North Platform Access Road
LEGEND:
Tunnel Works Deleted from M/s SAMBU Contract
DIR
: : : : : : : : : : : : : :
8.5 Km + 1.9 Km Rs. 7,984M Rs. 18,132M Rs. 5,429M Rs. 6,047M Rs. 1200M Geo-Consult Geo-Consult/Typsa JV Sep-2005 Sep-2008 May-2012 Jul-2017 44.5% 36.7%
N
START
(N-5)
JAMRUD
SURKAMAR
RAILWAY TRACK
END
(N-55) 2
: : : : : : : : : : : : :
7.6 Rs. 9,003 M N/A Rs. 1,962 M Rs. 2,219 M Rs. 1,318 M M/s EA M/s Matracon Feb-2010 May-2011 Jul-2012 Jul-2013 47%
49
NEW KHUSHALGARH BRIDGE ACROSS RIVER INDUS Existing rail-cum-road Bridge constructed in 1905 Work on New Bridge commenced in Nov-2011 Project cost is Rs 1.5 B Physical progress is 50%
Khushal Garh Bridge over River Indus (N-80), (Bridge 0.358 Km, approach 2.46 Km)
Length PC-I Cost Contract Cost PSDP Allocations Consultant Contractor Date of Start Date of Completion Expenditure todate Overall Physical Progress Current Status:
Progress of work is satisfactory.
: : : : : : : : : : :
0.35 + 2.4 Rs. 1,538 Million Rs. 981 Million Rs. 1008 Million Rs. 100 Million M/s Loya Associates M/s Usmani Associates Oct -2011 Oct-2013 694 Million 70%
(Original)
(Actual)
ECW ACW
Progress: 58% Cost: Rs 4.9 B Start: Jan-2007 Work suspended since Aug-2008 Non payment issue PSDP 2012-13: Nil
Landi Kotal
FATA
Overall Progress
Issues & Impediments:
Work was stopped by the contractor since Aug 2008 due to non payment of their bills. Meeting has been arrange in P&D Division for re-mobilization of Contractor M/s FWO and Minutes of Meeting has also been issued. Re-mobilization plan is submitted by M/s FWO on 13th of December, 2012.
Chitral
Contract Cost
PSDP Allocations Consultant Contractor Date of Start Date of Completion Overall Progress
: : : : : : : : : : : : :
25 Rs. 1,620M Rs. 2,399M Rs. 622M Nil Rs. 50 M M/s ACE M/s NLC Dec-2005 May-2006 Mar-2009 Mar-2009 Substantially Complete
: : : : : : : : : : : : :
25 Rs. 1,620M Rs. 2,399M Rs. 501M Rs. 570 M Rs. 50 M M/s KCEI M/s NLC Jun-2006 Nov-2007 Dec-2009 Sep-2010 Subst. Complete