LAPORAN KEMAJUAN FISIK PEMBESIAN

PEKERJAAN
LOKASI

: Pembangunan Ringroad Citywalks


: JL. Ringroad / Gagak Hitam Medan

Tanggal : 25 November 2013


Realisasi

No

Jenis Pekerjaan

(2).

(1).

Satuan

(3).

Volume (kg)

(4).

Progress
(%)

(5).

Sisa

s/d Minggu ini


Progress
(%)

Volume (kg)

Progress
(%)

Volume (kg)

(7).

(8).

(9).

(10).

PEKERJAAN PEMBESIAN

Ulir D-8 x 12 m

kg

210,279.54

26.68

8.37

66,004.50

18.30

144,275.04

Ulir D-10 x 12 m

kg

154,712.60

19.63

12.02

94,712.60

7.61

60,000.00

Ulir D-13 x 12 m

kg

33,047.04

4.19

3.13

24,648.00

1.07

8,399.04

Ulir D-16 x 12 m

kg

101,037.84

12.82

3.01

23,700.00

9.81

77,337.84

Ulir D-19 x 12 m

kg

157,295.28

19.95

8.20

64,625.40

11.76

92,669.88

6
7

Ulir D-22 x 12 m
Ulir D-25 x 12 m

kg

25,032.00

3.18
13.56
100.00

2.27
11.72
48.71

17,880.00
92,400.00
383,970.50

0.91
1.83
51.29

7,152.00
14,460.60
404,294.40

kg
Total

106,860.60
788,264.90

Realisasi
No

(1).

Jenis Pekerjaan

(2).

Satuan

(3).

Volume (kg)

(4).

Progress
(%)

(5).

Sisa

s/d Minggu ini


Progress
(%)

Volume (kg)

Progress
(%)

Volume (kg)

(7).

(8).

(9).

(10).

2300

4.74

450
150

7.4

12.48

360

18.96

270

26.76

150

35.76
46.2