Construction Programme For Ancillary Building / Main Building On - / - / 201 - Starting Time Location (Grid No:) Description Officer-In-Charge
Construction Programme For Ancillary Building / Main Building On - / - / 201 - Starting Time Location (Grid No:) Description Officer-In-Charge
7.00 AM
8.00 AM
9.00 AM
10.00 AM
11.00 AM
12.00 PM
01.00 PM
02.00 PM
03.00 PM
04.00 PM
Note: STEMS Representative & DoB-PE is not available after 04.00 PM & You may not be able to ask for their inspections after that. Therefore please be kind enough to show the relevant inspection to ICC-QA/QC Team who would bring it to the notice of STEMS Representative & DoB-PE on the following day AEAP. After 04.00 PM for ICCQA/QC Team (i.e: Following day to the STEMS & DoB)