NTPC Talcher-Kaniha Welcomes

You might also like

Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 16

NTPC TALCHER-KANIHA WELCOMES

BY H N CHAKRABORTY

MAKE TYPE NO. OF STAGES

STEAM PRESSURE/TEMP
NO. OF BEARINGS

: ABB, GEMANY : 3 CYLINDERS, REHEAT,CONDENSING RATED TERMINAL OUTPUT: 500 MW : HP =1 X 16 NOS. ( IMPULSE 1 + REACTION 15) IP =2 X 16 NOS. ( REACTION) LP =2 X 5 NOS. ( REACTION) : 166.7 bar/537 Deg C (HPT INLET) 39.5 bar/ 537 Deg C (IPT INLET) : JOURNAL BRGS: 5 ( 2 FOR TURBINE+ 3 FOR GENERATOR) THRUST BRG : 1

DURING UNIT-2 OVERHAUL LP TURBINE LAST STAGE BLADE INSPECTION WAS CARRIED OUT AS PER THE SCHEDULED OEM RECCOMONDATION AFTER 75000 RUNNING HRS.

DURING INSPECTION 5 NO. BLADES OF GENERATOR SIDE & 6 NO. BLADES OF IP TURBINE SIDE FOUND LOOSE.

EXPERT ADVICED TO REMOVE ALL THE LOOSE BLADES FROM POSITION OEM EXPERT SUGGESTED TO REMOVE THE ROTOR FROM THE POSITION FOR REMOVAL OF LOOSE BLADES.

IN KWU TURBINE LPT LAST STAGE BLADES WERE LOCKED FROM BOTH SIDES BY THE CLAMPING PIECE AND LOCKING PLATES. FOR THIS M/C LP ROTOR SHOULD BE REMOVED FROM POSITION TO REPLACE THE CLAMING PIECES. IN ABB M/C THE LAST STAGE BLADES OF THE LPT WERE LOCKED BY 4 NOS SUB STRUCTURE SPRINGS ( 2 NOS EACH ON BOTH ENDS) WITH ONE SIDE LOCKED BY 2 NOS L-TYPE AXIAL LOCKS ON THE OUTTER SIDE.

AXIAL LOCKS ON THE OUTTER SIDE

HENCE IT WAS DECIDED TO CARRY OUT THE REPLACEMENT OF THE SUBSTRUCTURE SPRINGS FOR THE LOOSE BLADES, IN-SITU.

REMOVING BLADE FROM THE ROOT

L-TYPE AXIAL LOCK SEGMENTS

DP TEST DONE BEFORE BOX UP

REPLACED WITH NEW SUB STRUCTURE SPRINGS

FIXING THE BLADE WITH NEW SPRINGS

NEW L-TYPE LOCKING SEGMENTS IN POSITION

CAULKING OF L-TYPE SEGMENTS

THANK YOU

You might also like