1.

BUAT JARINGAN PROYEK


2. REKAP TABEL BCWS.BCWP DAN ACWP

ACT.

DURASI
(MING)

A*
B*
C*
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S

10
8
6
4
2
4
4
6
5
5
5
3
3
1
5
2
3
8
6

BIAYA/M
INGGU
PRED
($ K)
-10
A
8
A
16
C
5
C
18
C
20
B
20
B
10
B;C
12
E
16
F
0
G
0
J
0
H,L
14
D,K
16
N
12
O
12
I; P ; Q
13
M; R
11
IMM

BCWS

ACT.YG
SELESAI
(%)
100
100
100
60
50
50
50
20
30
0
0
0
0
0
0
0
0
0
0

100
64
96
20
36
80
40
30
24
40
0
0
0
14
80
24
36
104
66

ACWP

ACWP

($ K)
100
70
95
15
40
100
50
30
30
0
0
0
0
0
0
0
0
0
0

WEEK
10
8,75
15,83333
3,75
20
25
12,5
5
6
0
0
0
0
0
0
0
0
0
0

BCWP

100
64
96
12
18
40
20
6
7,2
0
0
0
0
0
0
0
0
0
0

BCWP
WEEK
10
8
16
3
9
10
5
1
1,44
0
0
0
0
0
0
0
0
0
0

BUAT GANTT CHART


A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
1

S
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

48

BUAT KUMULATIF BCWS,BCWP DAN ACWP PER MINGGU


WEEK

BCWS
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47

BCWS*
0
10
10
10
10
10
10
10
10
10
10
24
24
24
24
24
24
51
51
83
83
58
58
38
10
0
30
28
28
16
16
12
12
12
13
13
13
13
13
13
13
13
11
11
11
11
11
11

ACWP

ACWP*

0
0
0
10
10
10
20
10
20
30
10
30
40
10
40
50
10
50
60
10
60
70
10
70
80
10
80
90
10
90
100
10
100
124 24,58333 124,5833
148
25 149,5833
172
25 174,5833
196
25 199,5833
220
25 224,5833
244
25 249,5833
295
57,5 307,0833
346
58 365,0833
429
52,25 417,3333
512
52 469,3333
570
628
666
676
676
706
734
762
778
794
806
818
830
843
856
869
882
895
908
921
934
945
956
967
978
989
1000

BCWP
0
10
10
10
10
10
10
10
10
10
10
24
24
24
24
24
24
30
30
20,44
20

BCWP*
0
10
20
30
40
50
60
70
80
90
100
124
148
172
196
220
244
274
304
324,44
344,44

AV
0
0
0
0
0
0
0
0
0
0
0
-0,58333
-1,58333
-2,58333
-3,58333
-4,58333
-5,58333
-12,0833
-19,0833
11,66667
42,66667

CV

SPI

CPI

0
0
0
0
1
1
0
1
1
0
1
1
0
1
1
0
1
1
0
1
1
0
1
1
0
1
1
0
1
1
0
1
1
-0,58333
1
1
-1,58333
1
1
-2,58333
1
1
-3,58333
1
1
-4,58333
1
1
-5,58333
1
1
-33,0833 0,928814 0,928814
-61,0833 0,878613 0,878613
-92,8933 0,75627 0,75627
-124,893 0,672734 0,672734

BUAT KURVA S

Kinerja Jadwal Proyek :


Penyimpangan Jadwal

SV = BCWP 20th BCWS 20th = 344,44-512= -167,56 <0

Indeks kinerja jadwal


SPI = BCWP 20th / BCWS 20th = 344,44/ 512 = 0,672 <1
Jadwal aktual lebih lambat dari jadwal rencana

Kinerja biaya proyek


Penyimpangan Biaya
CV = BCWP 20th ACWP 20th = 344,44-469,333= -124,893

Indeks Kinerja Biaya


CPI = BCWP 20th / ACWP 20th = 344,44/469,333= 0,672 <1
Pembiayaan aktual melampaui rencana

Perkiraan jadwal penyelesaian proyek


ECD = (sisa waktu / SPI) + waktu terpakai
= (47-20)/ 0,672 + 20 = 60,178 minggu bisa jadi 60 -61 minggu proyek selesai dari
perkiraan semula 47 minggu

Perkiraan Biaya penyelesaian Proyek

Forecasted cost at completion = (sisa anggaran/CPI)

Forecasted cost to completion = (sisa anggaran/CPI) + ACWP

EAC atau FCTC = (sisa anggaran/CPI) + ACWP 20th


= (Total Biaya (BCAC) BCWP20th)/ CPI + ACWP 20th
= (1000- 344,44)/0,672 + 469,333
= 1444,868
Terjadi penambahan biaya 444,868 dari semula 1000
BUAT KEMBALI KURVA S DENGAN FCAC DAN FCTC, DENGAN PERKIRAAN WAKTU DARI 47 MENJADI
60 MINGGU, BCWS TETAP, ACWP MENJADI 1444,868 PADA MINGGU KE 60 DAN BCWP=BCWS PADA
MINGGU KE 60
SILAKAN KALIAN PLOT DI GRAFIK KURVA S DIATAS

UNTUK CPI DAN SPI INDEX SILAKAN PLOT DARI TABEL DIATAS SPI DAN CPI TIAP MINGGUNYA

MARGINAL

GOOD

SPI
1

MARGINAL

POOR

CPI