Weekly Plan (12월3주)
Weekly Plan (12월3주)
ER-296
Weekly Plan
08/12/2013 ~ 28/12/2013 Last week Location Method of Con Panel No. SIZE Progress
8 Sun Plan 9 Mon 10 Tue 11 Wed 12 Thu 13 Fri 14 Sat 15 Sun 16 Mon 17 Tue
This week
18 Wed 19 Thu 20 Fri 21 Sat 22 Sun 23 Mon 24 Tue
Next week
25 Wed 26 Thu 27 Fri 28 Sat
Remark
Action
Plan
D-Wall
133
800mm
Action
Plan
D-Wall
143
800mm
Action
Plan
D-Wall
134
800mm
Action
Plan
D-Wall Sector 6
56
800mm
Action
Plan
D-Wall
60
800mm
Action
Plan
D-Wall
135
800mm
Action
Plan
D-Wall
62
800mm
Action
Plan
D-Wall
136
800mm
Action
Plan
Capping beam
Action
Plan
NO. 27
93.89M
Action
Plan
NO. 28
93.89M
Action
Plan
NO. 29
93.89M
Action
Plan
Action
Plan
Excavation Shaft
Action
Plan
Action
Sewer line
MA-H 3 to MA-H 4
Plan
97.9M
Action
- Safety brief about Little India accident - Break down BC cutter - Excavation by grab machine(Only 2 or 3 meter excavation per ond day) - Delay of handover micro pile work place as of muddy soil disposal(Capping beam work) - Start capping beam work(10/12/2013)
- D-WALL Sequence(construction period) : 21/12/2013 ~ 22/01/2014 62(3) 138(4) 63(3) 136(4) 145(3) 139(4) 146(3) 64(4) 147(4) - Completed capping beam at sector 6c - Completed Shaft work - Start Pipe Jacking work
Remark