Lab No. UTD/NSK/B-1206122 Dt. 29/06/2012: F:/A.E (M) /Reports/Load Test Report - Doc-529
Lab No. UTD/NSK/B-1206122 Dt. 29/06/2012: F:/A.E (M) /Reports/Load Test Report - Doc-529
Date-
Sub: Load test in respect of M/s.President Manmad Municipal Corporation. In this connection it is to inform you that testing engineers were deputed to above H.T. consumer on Dt. 02/01/14. Meter is found to be working within permissible limit of error. Load test was taken and it was found satisfactory. Details of TOD Meter: Make: - HPL CTR: - -/5A Sr. No: -308878 P.T.R. 11 KV 110V 3 3 CD: - 500KVA CL: - 750 KW Readings as are follows: Kwh 233421 KVAh 240584 KVAMD 27.70
Lab No. UTD/NSK/B-1206122 Dt. 29/06/2012
RKVAH 40802
Reset 17
PTR = 11 KV 110V 3 3
Remarks: 1) Data retrieval & analysis to be carried out at your end. 2) Instantaneous IIIrd current Harmonics found Beyond Permissible limit.
Executive Engineer Rural Testing Div MSEDCL, Nashik. Copy s.w.rs.to.: 1) The S.E (O&M) Rural Circle, MSEDCL Nashik. Copy to: 1) The Dy. Manager (F&A) O&M Rural Circle, MSEDCL Nashik. 2) The A.E.Yeola-R S/Dn. MSEDCL, Manmad.