WORK PERMIT SYSTEM

1.0 INTRODUCTION flammable air - hydrocarbon mixture or a


flammable substance.
The Work Permit System is an important
tool for safety in hydrocarbon processing /
handling. The recommended Work Permit
System is described covering various
aspects like when a work permit is required, b) Cold Work : Cold Work is an activity which
types of permits, responsibilities, check does not produce sufficient heat to ignite a
lists, validity etc. The success of a Work flammable air- hydrocarbon mixture or a
Permit System depends upon the training, flammable substance.
motivation and participation of all
individuals concerned with its 4.0 TYPE OF WORK PERMITS
implementation. Since several maintenance/
construction jobs are often carried out with Based on the nature, the work shall be
assistance from contractors, it is essential to undertaken either under Hot Work Permit
provide sufficient exposure to contractor or Cold Work Permit, for which formats are
and his employees as well. exhibited in pages 17-38. Explanatory notes
to check-list items of the formats are
If the work has to be performed in a provided under Section 7.0.
hydrocarbon processing/ handling
installation by any person other than the The two types of permits, one for cold work
operating personnel of that area, a duly and the other for hot work are the minimum
authorised written permit shall be obtained requirements which must be fulfilled before
by the person/agency executing the work commencing work. For jobs like
before commencement of the work. excavation, road/dyke cutting, electrical
However, even for operating personnel, lockout / energising etc., where the work
when work has to be performed outside permit issuing authority may have to take
their normal routine, an exclusive permit to clearances from other sections/ personnel,
that effect by the authorised person shall be organisations may introduce supplementary
obtained. formats for these purposes, if they consider
it necessary. Format for electrical lockout/
2.0 SCOPE energising is given in OISD-STD-137 on
"Inspection of Electrical Equipment".
The Work Permit System shall cover all
hydrocarbon processing / handling Radiography must be carried out when
installations such as onshore /offshore occupancy is least. For precautions to be
processing platforms, gas treating units, taken during radiography, refer OISD-STD-
crude oil terminals, refineries, pipelines, 155 on "Personal Protective Equipment".
marketing installations and LPG bottling
plants. In addition to the regular work permit,
supplementary permits as required by the
3.0 DEFINITIONS local statutory bodies are also to be issued.

a) Hot Work : Hot Work is an activity which


may produce enough heat to ignite a
5.0 PROCEDURE FOR WORK PERMIT Following is the procedure for the
SYSTEM implementation of Work Permit System :

2
(a) The Work Permit System shall always operate
on "Owner - In-charge" concept. (Example: The Safety Officer/Fire Officer / Officer
Process Unit-Shift In-charge; Laboratory- authorised will make periodic check of the
Chief Chemist; Depot-Depot Manager; Hot Work Sites and see that the work is
Pipelines Installation- Shift In-charge). The being carried out as per conditions laid
concerned management shall issue the down in the Hot Work Permit. At any point
appropriate authority limits for various of time, if he considers that the conditions
installations and type of permits based on are not safe enough for the work, he may
this concept. suspend the work and inform the Work
Permit Issuing Authority to restore the safe
(b) The permit shall be in printed form. conditions so that work can be restarted.

(c) Separate forms shall be used for Hot Work (g) For simplification of procedure, Hot Work
and Cold Work. Permit also covers permission for vessel
entry, vessel boxing-up and excavation. All
(d) A system of colour coding is recommended to activities outside the scope of Hot Work
identify two types of permits. The Permit shall be covered by Cold Work
recommended colours are pink for Hot Permit.
Work Permit and yellow for Cold Work
Permit. All permits shall be serially (h) No hot/cold work shall be undertaken without
numbered. a work permit except in the areas pre-
determined and designated by the owner-in-
(e) Hot Work Permit shall be in four copies. The charge. All work permits shall be issued by
original shall be in pink colour and other the person who is designated as responsible
copies shall have the word "COPY" printed person for the operation of the area where
in large pink letters. work is to be carried out. In respect of work
permits for handling highly critical types of
Cold Work Permit shall be in two copies. The work and also for long duration work such
Original shall be in yellow colour and the as in construction jobs in a running
copy shall have the word "COPY" printed installation, the authorising level should be
in large yellow letters. elevated.

(f) It is recommended that both Hot Work Permit (i) The work may be planned to be done either
as well as Cold Work Permit be made in the departmentally or through a contractor. In
form of books with tear-off facility. In the either case, the work permit should be
case of Hot Work Permit, the authorised received and signed by the maintenance /
Original copy shall be given to the receiver, project /construction supervisor of the
the Duplicate to the Fire Section, Triplicate company as he is responsible for the work
to Safety Section and Quadruplicate of the contractor also. Where no such
retained in the book. In case of Cold Work independent
Permit, the authorised Original shall be supervisor exists, for example in small
issued to the receiver, retaining the installations, the owner-in-charge can issue
Duplicate in the book. the permit to the contractor's supervisor
directly and obtain his signature.
It is recommended that plot plans of the
installation and the operating blocks should (j) Permit should be issued only for a single shift
be displayed in the Fire and concerned Unit and its validity should expire at the
Control Rooms respectively and site of hot termination of the shift. However, where
jobs under progress should be indicated on the work has to be continued, the same
these plot plans with red pins. This helps permit may be revalidated in the succeeding
the incoming supervisor /s (both in Fire and shift, by authorised person after satisfying
Operating Departments) to get a quick idea the normal checks.
of the hot jobs being undertaken and help in
identifying the areas which require In instances like plant turn around or an
inspection / attention, depending upon the activity where work is of continuous nature
criticality of the area and the job. involving round the clock activity, blanket

3
Hot Work Permit could be given if the
owner-in-charge is fully satisfied that the (i) Equipment / Area inspected
conditions are totally safe for the multiple
jobs to be performed. But this should not be Equipment or area where work is to be
resorted to, especially in highly integrated conducted, should be inspected to ensure
units. that it is safe to carry out the work and
assess other safety requirements /
Even when construction activity has to be stipulations. In case of vessel box-up
undertaken in non-operating areas in permit, it should be ensured that the work is
integrated units, it is recommended that complete, all personnel are out, no
approval be obtained from designated maintenance gear is left behind and debris
senior management for issuing blanket Hot removed.
Work Permit.

(k) As a pre-requisite to issue permit, particularly (ii) Surrounding area checked / cleaned
in the case of hot work/vessel entry permit,
gas test for hydrocarbons / oxygen Unsafe conditions for performance of work
deficiency / toxic gases shall be conducted may arise from surrounding area. It should
as applicable. be cleaned-up to remove flammable
material such as oil, rags, grass etc.
(l) Where gas-free conditions are not fully
ensured for the duration of hot work, a
system of monitoring either by automatic or (iii) Sewers, Manholes, CBD etc. and Hot
by manual periodic verification shall be Surfaces covered
resorted to depending upon the prevalent
conditions of the operating area. Flammable gases may be released from
nearby sewers. Hot un-insulated
(m) After completion or stoppage of the job, the surfaces/pipelines may provide a source of
person to whom the permit was issued, ignition. Therefore, these are to be properly
should thoroughly check the area for covered to prevent fires.
clearing of debris, removal of temporary
electrical installations etc. and then shall (iv) Considered hazard from other routine /
sign the work permit and return it to the non-routine operations and persons
issuer. alerted

(n) The issuer on receiving back the permit would Other activities (routine / non-routine)
satisfy himself regarding completion of the being carried out near-by which can create
job and that the area has been cleaned. conditions unsafe for performance of the
Then he shall also sign the permit and keep permit work, should be taken into
the records for one month. consideration and the concerned persons
should be alerted accordingly.
6.0 SPECIMEN WORK PERMIT FORMS
(v) Equipment electrically isolated and
Specimen Work Permit forms for the two tagged
types of the permits illustrating the
suggested colour code, layout and size are Before issuing permit for mechanical /
exhibited in pages 17-38. electrical work in the operating area, it
should be ensured that electrical switches
7.0 EXPLANATORY NOTES TO WORK are locked-out and cautionary tags duly
PERMIT FORMS signed with date and time are attached.
Wherever local locking arrangement is
The check-listed items in the Work Permit provided in the field, the same should be
Forms are elaborated below to amplify the used. Refer format for electrical lockout /
underlying concepts and highlight their energising given in OISD-STD-137 on
significance: "Inspection of Electrical Equipment".

4
(vi) Running water hose/Portable extinguisher
provided Purging of equipment (vessels, pipelines,
compressors etc.) is done to make them free
Running water hose and portable fire of flammable hydrocarbons and toxic gases.
extinguisher are required respectively to Steam / Inert Gas is used for gas-freeing of
flush / dilute in case of release of any vessels and pipes in refineries and other
hazardous chemical or to quench sparks and locations. Other means of purging is by
to put out small fires immediately. displacement with water and final traces of
gas removed by air eductor. All high point
(vii) Fire water system checked for readiness vents should be unplugged while purging.
Purging may be done continuously or in
In order to meet any contingency, it should batches to conserve purge medium. It
be ensured that the fire water system should be done in a systematic manner to
including fire water pumps, storage, cover the entire equipment/plant and
network etc. is checked and kept ready for continued till the concentration of toxic /
immediate use. flammable gas is lowered to allowable
level.
(viii) Equipment blinded / dis-connected / closed
/ isolated / wedge opened (xi) Equipment water flushed

Equipment / Vessel, on which the work Water flushing is an effective means of


permit is being issued, should be cooling, cleaning and even gas-freeing of
completely isolated from the rest of the equipment. It is also employed to remove
plant with which it is connected during traces of acids / chemicals. Equipment
normal operation, in order to ensure that metallurgy must be considered before using
there is no change in the work environment sea / saline water. Sometimes, flushing with
with respect to presence of toxic / demineralised water would be necessary
flammable gases, liquids, hazardous depending upon the metallurgy of the
chemicals etc. in the course of the work. equipment.

Blinding is one of the most effective ways (xii) Gas / Oxygen deficiency test done and
of isolation. Blinds should be installed as found OK
close to the vessel as possible. If lines
cannot be blinded, they should be Gas test includes measurement of :
disconnected and the open ends should be
made safe by installing pipe caps/plugs, (a) Hydrocarbons by Explosimeter
blind flanges, mud packing etc.
(b) Oxygen Deficiency by Oxygen Meter
(ix) Equipment properly drained /
depressurised (c) Use of Calibrated Meters

Equipment under pressure should be (d) Toxic gases like Hydrogen Sulphide,
depressurised after isolation.This will be Carbon Monoxide, Nickel Carbonyl,
followed by draining / purging / water Chlorine etc. by techniques like Indicator
flushing etc. as the case may be. Tube method, Lead Acetate Paper etc.

Equipment containing liquid hydrocarbons Measurement of lead in air is required for


should be drained completely. There may entering leaded tanks and personal
be a possibility of overlooking liquid protective equipment shall be worn before
collected in pockets or inaccessible areas entering the tank. Octel/Ethyl regulations
such as level gauges, small nozzles / are to be followed while handling leaded
bleeders on vessels, laterals in pipework gasoline tanks.
etc. All low point drains should be in
unplugged condition. Gas tests may be specified for vessel entry
including open excavation where head of a
(x) Equipment properly steamed / purged man will be below ground level and when

5
hot work is being carried out. The person "Caution-Men at Work Inside" on the
carrying out gas test must wear proper manhole of a vessel.
protective gear.

No hot work shall be permitted unless the (xvii) Portable equipment / Hose nozzles
Explosimeter reading is zero. properly grounded

Vessel entry, where no hot work is to be As a precaution against static electricity


carried out, may be permitted if generation, portable equipment / hose
combustible gases are up-to 5% of lower nozzles e.g. nozzle of a shot / sand blasting
explosive limit (LEL). Entry with an air gun, are to be grounded. Use of
supplied mask may be permitted with hydrocarbon lines for earthing should be
LEL of upto 50%. avoided.

The oxygen level should be at least 19.5 % (xviii) Standby person provided for vessel
vol. and the concentration of toxic gases entry
below the threshold limits.
Whenever a person is entering a vessel or
(xiii) Shield against sparks provided work is being carried out in confined space,
it may be necessary to keep standby persons
In order to protect against welding sparks (minimum two) at the manhole or entry
which can provide ignition in operating point holding the rope connected to the
areas, shields are to be provided. The shield safety belt of the person inside. In case of
material should be non-flammable and any emergency inside or outside the vessel,
should be kept wet with water. the standby will be able to pull the person
out.
(xiv) Proper ventilation and lighting provided
(xix) Standby personnel provided for fire watch
Where natural ventilation is not available, from Process / Maintenance /
fans/air eductors are provided. Some types Contractor / Fire Department
of work like welding may generate fumes.
Facilities may be required for the speedy Depending on the criticality of the job,
dispersal of these fumes. Only approved work permit issuer shall decide the type of
reduced voltage extension lights (not standby to be provided i.e. from which
exceeding 24 volts) are to be allowed for department, of which level, how many and
work inside vessels from consideration of also additional fire fighting support
personal safety. facilities.

(xv) Proper means of exit provided (xx) Iron Sulphide removed / kept wet

Proper means of exit is required in case of Pyrophoric substances may be present in


emergencies developed on account of the operating area / equipment handling
work or otherwise. Availability of an hydrocarbon. Iron sulphide scales is the
alternate route of escape should be most common pyrophoric substances
considered. encountered. These should be either
removed to safe locations or kept wet all the
(xvi) Precautionary tags / boards provided time to prevent their auto-ignition.

To prevent any unwarranted entry in the (xxi) Area cordoned off


work area and also to caution other
personnel taking actions which may In order to prevent the un-authorised entry
endanger people working on the permit job, of people and to avoid accidents during
precautionary tags/boards are to be excavation jobs, work area is to be
provided like "No Entry" sign on roads or cordoned off.

6
(xxii) Precaution against public traffic taken suitable size steel plate for blocking the
opening in case of mishap/tank failure. If no
In case hot work is to be carried out in work is undertaken in evening and night
close proximity of a public road, for shifts, invariably the gap should be closed
example in the case of a trunk pipeline, it with steel plate and mud packing at the end
may be desirable to block-off/divert public of day's work.
traffic for the duration of the job as a
precautionary measure. (xxvi) Checked Flame / Spark arrestor on
mobile equipment
(xxiii) Clearance obtained for excavation from
Technical/ concerned departments No vehicle / engine without flame / spark
arrestor is permitted in operating areas.
For any excavation work which may affect
underground sewers / telephone lines / (xxvii) Checked for oil / gas trapped behind
cables / pipelines etc., Technical Services lining in equipment
Dept. and / or other concerned departments,
should be consulted for obtaining the co- Before undertaking hot jobs, a check should
ordinates and the depth to which excavation be done for oil / gas trapped behind lining
can be resorted to, without damaging the in the equipment. Many a times oil / gas
existing facilities. Markers should be put trapped behind lining depicts itself in the
around the area where excavation can be form of swelling and can be confirmed by
done and the depth can be indicated in the way of drilling holes.
work permit.
(xxviii) Welding machine checked for safe
(xxiv) Clearance obtained for road cutting from location
Technical / Fire / concerned
departments Welding machine should be located in a non-
hazardous and ventilated area. It should
Since road cutting can hamper the have proper supervision while welding job
movement of the fire vehicles, initial is in progress. It should be switched off
clearance should be obtained from Fire immediately on completion of the job.
Department and final approval from the
higher designated authorities. If the road is (xxix) Checked for earthing/return connection to
wide, preferably the road should be cut half the equipment being welded
at a time. Duration of road cut should be
restricted as far as possible. Before commencing the welding job, ensure
that all the cables and earthing connections
(xxv) Clearance obtained for dyke cutting are as per the standard welding codes /
practices.
When the dyke is cut, any mishap in the
tank farm can lead to a free flow of oil to (xxx) Oxygen and Acetylene cylinders kept
outside the bund. A high level authority outside the vessel / tank
should be designated for authorising dyke
cutting. Further, it should be ensured that While performing welding / cutting jobs in
dyke would be reconstructed in the shortest confined spaces like vessel / tank, ensure that
possible time. For example, if pipes have to oxygen and acetylene cylinders are kept
be laid through the dykes, the pipes should outside and hoses for the gases are in good
be laid quickly and plugged / capped so that working condition, without any cracks or
the dyke can be closed. Thereafter, balance wrinkles. Also, hoses should be tightly
of pipe fabrication can continue without any secured at both the ends i.e. the torch and the
risk. Standby personnel should be available cylinder.
at the work site, who should possess a

7
(Yellow in colour)
ORIGINAL

(NAME OF COMPANY)

(LOCATION)

COLD WORK PERMIT

Sl.No.______________

AM / PM DATE AM / PM DATE

VALID FROM__________________________ TO__________________________________________

PERMISSION IS GRANTED TO SECTION/CONTRACTOR_____________________________________________

NAME__________________________________________________________________________________________

NATURE OF WORK______________________________________________________________________________

LOCATION OF WORK____________________________________________________________________________

THE FOLLOWING ITEMS SHALL BE CHECKED BEFORE ISSUING THE PERMIT


(Please put tick [ ] mark in the appropriate box)
--------------------------------------------------------------------------------------------------------------------------------------
S.No. Item Done Not Required
--------------------------------------------------------------------------------------------------------------------------------------

1. Equipment / Work Area inspected [ ] [ ]

2. Surrounding area checked,cleaned [ ] [ ]


and covered

3. Equipment electrically isolated [ ] [ ]


and tagged

4. Running water hose / Portable [ ] [ ]


extinguisher provided

5. Equipment blinded/disconnected / [ ] [ ]
closed / isolated / wedge opened

6. Equipment properly drained / [ ] [ ]


depressurised

7. Equipment water flushed [ ] [ ]

8. Equipment properly steamed / [ ] [ ]


purged

8
9. Iron Sulphide removed / kept wet [ ] [ ]
(Yellow in colour)

10. Proper ventilation and [ ] [ ]


lighting provided

11. Gas test done , found [ ] [ ]


gas free

12. Area cordoned off [ ] [ ]


(minimum 15m in case of
radiography)

13. Standby personnel provided [ ] [ ]


from Process / Maint. /
Contractor/Fire Deptt.

14. Radio-isotopes kept under [ ] [ ]


safe containers

-------------------------------------------------------------------------------- ---------------------------------------------------------------

SPECIAL INSTRUCTIONS

1. Following personal protective equipment are required (check all items required) :

Safety Helmet / Gloves / Goggles / Safety Shoes / Boiler Suit/ Welding Suit / Dust Respirator / Face Shield /
Fresh Air Mask/Apron / Lifeline / Safety Belt / Airline /Film Badges / Dosimeter.

2. In case of fire alarm, all work must be stopped. All personnel must leave work site and proceed to designated
areas.

3. Remarks on toxic/hazardous chemicals, if any:___________________________________________________


________________________________________________________________________________________
________________________________________________________________________________________

4. Alternate means of escape available/provided/not required.

5. This permit must be available at work site at all times.

6. Additional items, if any:____________________________________________________________________


________________________________________________________________________________________

Name and_____________________ Name and_______________________

Signature of Receiver__________ Signature of Issuer____________

9
(Yellow in colour)

Permit Extended upto Signatures


Additional precautions
--------------------------- required, if any -------------------------------------
Date Time Issuer Receiver
------------------------------------------------------------------------------------------------------------------------------------------------

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

AM / PM DATE
WORK COMPLETED/STOPPED/AREA CLEARED AT ____________________________________

By___________________ By__________________________
Signature Signature

_____________________ __________________________
(Name of Issuer) (Name of Receiver)

(PLEASE RETURN PERMIT TO ISSUER)

10
(White in colour)

DUPLICATE

(NAME OF COMPANY)

(LOCATION)

COLD WORK PERMIT

Sl.No.______________

AM / PM DATE AM / PM DATE

VALID FROM__________________________ TO__________________________________________

PERMISSION IS GRANTED TO SECTION/CONTRACTOR_____________________________________________

NAME__________________________________________________________________________________________

NATURE OF WORK______________________________________________________________________________

LOCATION OF WORK____________________________________________________________________________

THE FOLLOWING ITEMS SHALL BE CHECKED BEFORE ISSUING THE PERMIT


(Please put tick [ ] mark in the appropriate box)
--------------------------------------------------------------------------------------------------------------------------------------
S.No. Item Done Not Required
--------------------------------------------------------------------------------------------------------------------------------------

1. Equipment / Work Area inspected [ ] [ ]

2. Surrounding area checked,cleaned [ ] [ ]


and covered

3. Equipment electrically isolated [ ] [ ]


and tagged

4. Running water hose / Portable [ ] [ ]


extinguisher provided

5. Equipment blinded/disconnected / [ ] [ ]
closed / isolated / wedge opened

6. Equipment properly drained / [ ] [ ]


depressurised

7. Equipment water flushed [ ] [ ]

8. Equipment properly steamed / [ ] [ ]


purged

11
9. Iron Sulphide removed / kept wet [ ] [ ]

(White in colour)

10. Proper ventilation and [ ] [ ]


lighting provided

11. Gas test done , found [ ] [ ]


gas free

12. Area cordoned off [ ] [ ]


(minimum 15m in case of
radiography)

13. Standby personnel provided [ ] [ ]


from Process / Maint. /
Contractor/Fire Deptt.

14. Radio-isotopes kept under [ ] [ ]


safe containers

-------------------------------------------------------------------------------- ---------------------------------------------------------------

SPECIAL INSTRUCTIONS

1. Following personal protective equipment are required (check all items required) :

Safety Helmet / Gloves / Goggles / Safety Shoes / Boiler Suit/ Welding Suit / Dust Respirator / Face Shield /
Fresh Air Mask/Apron / Lifeline / Safety Belt / Airline /Film Badges / Dosimeter.

2. In case of fire alarm, all work must be stopped. All personnel must leave work site and proceed to designated
areas.

3. Remarks on toxic/hazardous chemicals, if any:___________________________________________________


________________________________________________________________________________________
________________________________________________________________________________________

4. Alternate means of escape available/provided/not required.

5. This permit must be available at work site at all times.

6. Additional items, if any:_____________________________________________________________________


________________________________________________________________________________________

Name and_____________________ Name and_______________________

Signature of Receiver__________ Signature of Issuer____________

12
(White in colour)

Permit Extended upto Signatures


Additional precautions
--------------------------- required, if any -------------------------------------
Date Time Issuer Receiver
------------------------------------------------------------------------------------------------------------------------------------------------

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

AM / PM DATE
WORK COMPLETED/STOPPED/AREA CLEARED AT ____________________________________

By___________________ By__________________________
Signature Signature

_____________________ __________________________
(Name of Issuer) (Name of Receiver)

(PLEASE RETURN PERMIT TO ISSUER)

13
(Pink in colour)

ORIGINAL

(NAME OF COMPANY)

(LOCATION)

HOT WORK/ VESSEL ENTRY/ VESSEL BOX-UP/ EXCAVATION


PERMIT

AM / PM DATE AM / PM DATE

VALID FROM_____________________________ TO__________________________________

PERMISSION IS GRANTED TO SECTION/CONTRACTOR____________________________________________

NAME_________________________________________________________________________________________

NATURE OF WORK_____________________________________________________________________________

LOCATION OF WORK___________________________________________________________________________

THE FOLLOWING ITEMS SHALL BE CHECKED BEFORE ISSUING THE PERMIT


(Please put tick [ ] mark in the appropriate box)
-----------------------------------------------------------------------------------------------------------------------------------------------
S.No. Item Done Not required
-----------------------------------------------------------------------------------------------------------------------------------------------

1. Equipment / Work Area inspected [ ] [ ]

2. Surrounding area checked/cleaned [ ] [ ]


up: oil/ rags/grass etc. removed

3. Sewers , manholes , CBD etc. and [ ] [ ]


hot surfaces nearby covered

4. Considered hazard from other [ ] [ ]


routine / non-routine operations
and concerned persons alerted

5. Equipment electrically isolated [ ] [ ]


and tagged

6. Fire water hose / Portable [ ] [ ]


extinguisher provided

7. Fire water system checked for [ ] [ ]


readiness

14
8. Equipment blinded/disconnected/ [ ] [ ]
closed / isolated / wedge opened

(Pink in colour)

9. Equipment properly drained / [ ] [ ]


depressurised

10. Equipment properly steamed/purged [ ] [ ]

11. Equipment water flushed [ ] [ ]

12. Gas / Oxygen deficiency test [ ] [ ]


done and found OK

13. Shield against sparks provided [ ] [ ]

14. Proper ventilation and lighting [ ] [ ]


provided

15. Proper means of exit provided [ ] [ ]

16. Precautionary tags / boards [ ] [ ]


provided

17. Portable equipment / nozzles [ ] [ ]


properly grounded

18. Standby personnel provided for [ ] [ ]


vessel entry

19. Standby personnel provided for [ ] [ ]


fire watch from Process/Maint./
Contractor / Fire Deptt.

20. Iron Sulphide removed/ kept wet [ ] [ ]

21. Area cordoned off [ ] [ ]

22. Precautions against public [ ] [ ]


traffic taken

23. Clearance obtained for excavation [ ] [ ]


from Technical/concerned deptts.

24.* Clearance obtained for road [ ] [ ]


cutting from Technical / Fire /
concerned deptts.

25.* Clearance obtained for dyke [ ] [ ]


cutting

26. Checked Flame / Spark arrestor [ ] [ ]


on mobile equipment

15
27. Checked for oil / gas trapped [ ] [ ]
behind lining in equipment

(Pink in colour)

28. Welding machine checked for [ ] [ ]


safe location

29. Check for earthing / return [ ] [ ]


connection to the equipment
being welded

30. Oxygen and Acetylene cylinders [ ] [ ]


kept outside the vessel/tank
------------------------------------------------------------------------------------------------------------------------------------------------

Note: For Items marked (*), clearance to be obtained from higher designated authority.

SPECIAL INSTRUCTIONS

1. Following personal protective equipment are required


(Check all items required) :

Safety Helmet / Gloves / Goggles / Safety Shoes / Boiler Suit /Welding Suit, Dust Respirator/Face
Shield/Face Shield/ Fresh Air Mask/Apron/Life line/Safety Belt.

2. In case of fire alarm, all work must be stopped and running fire water must be closed. All personnel must
leave work site and proceed to designated areas.

3. In case of liquid / gas release, stop work and immediately advise concerned Operation Personnel.

4. Only certified vehicles/engines and permitted type of electrical equipment and tools are allowed in operating
areas.

5. Ensure proper grounding/earthing/insulation of cables.

6. For hot tapping, ensure continuous/sufficient flow in the line.

7. This permit must be available at the work site at all times.

8. No hot work shall be permitted unless the Explosimeter reading is zero.

9. Vessel entry, where no hot work is to be carried out, may be permitted if combustible gases are up-to 5% of
lower explosive limit (LEL). Entry with an air supplied mask may be permitted with LEL of upto 50%. The
oxygen level should be at least 19.5 % vol. and the concentration of toxic gases below the threshold limits.

10. Additional remarks, if any:___________________________________________________________________

________________________________________________________________________________________

Name and__________________________ Name and __________________________

16
Signature of Receiver________________ Signature of Issuer____________________

Pink in colour

________________________________________________________________________________________________
GAS TEST(HYDROCARBON/ PERMIT ADDITIONAL
TOXIC GAS/OXYGEN EXTENDED PRECAUTIONS SIGNATURES
DEFICIENCY)DONE UPTO REQD.,IF ANY
-----------------------------------------------------------------------------------------------------------------------------------------------
DATE/ TAKEN TEST DATE/ ISSUER RECEIVER
TIME BY VALUE TIME
-----------------------------------------------------------------------------------------------------------------------------------------------
INITIAL GAS
TEST
------------------------------------------------------------------------------------------------------------------------------------------------

------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
________________________________________________________________________________________________

NOTE: HOT WORK INCLUDES WELDING, BURNING, GRINDING, SOLDERING, SAND BLASTING,
CHIPPING, RIVETING, DRILLING, CAMERA FLASHING, POWER TOOLS, IC ENGINE
OPERATIONS/ENTRY, OPEN FLAME, VEHICLE ENTRY.

AM / PM DATE
WORK COMPLETED / STOPPED / AREA CLEARED AT ________________________________________

By____________________________ By____________________________

Signature Signature

____________________________ ____________________________
(Name of Issuer) (Name of Receiver)

(PLEASE RETURN PERMIT TO ISSUER)

17
(White in colour)

DUPLICATE

(NAME OF COMPANY)

(LOCATION)

HOT WORK/ VESSEL ENTRY/ VESSEL BOX-UP/ EXCAVATION


PERMIT

AM / PM DATE AM / PM DATE

VALID FROM_____________________________ TO__________________________________

PERMISSION IS GRANTED TO SECTION/CONTRACTOR____________________________________________

NAME_________________________________________________________________________________________

NATURE OF WORK_____________________________________________________________________________

LOCATION OF WORK___________________________________________________________________________

THE FOLLOWING ITEMS SHALL BE CHECKED BEFORE ISSUING THE PERMIT


(Please put tick [ ] mark in the appropriate box)
-----------------------------------------------------------------------------------------------------------------------------------------------
S.No. Item Done Not required
-----------------------------------------------------------------------------------------------------------------------------------------------

1. Equipment / Work Area inspected [ ] [ ]

2. Surrounding area checked/cleaned [ ] [ ]


up: oil/ rags/grass etc. removed

3. Sewers , manholes , CBD etc. and [ ] [ ]


hot surfaces nearby covered

4. Considered hazard from other [ ] [ ]


routine / non-routine operations
and concerned persons alerted

5. Equipment electrically isolated [ ] [ ]


and tagged

6. Fire water hose / Portable [ ] [ ]


extinguisher provided

7. Fire water system checked for [ ] [ ]


readiness

18
8. Equipment blinded/disconnected/ [ ] [ ]
closed / isolated / wedge opened

(White in colour)

9. Equipment properly drained / [ ] [ ]


depressurised

10. Equipment properly steamed/purged [ ] [ ]

11. Equipment water flushed [ ] [ ]

12. Gas / Oxygen deficiency test [ ] [ ]


done and found OK

13. Shield against sparks provided [ ] [ ]

14. Proper ventilation and lighting [ ] [ ]


provided

15. Proper means of exit provided [ ] [ ]

16. Precautionary tags / boards [ ] [ ]


provided

17. Portable equipment / nozzles [ ] [ ]


properly grounded

18. Standby personnel provided for [ ] [ ]


vessel entry

19. Standby personnel provided for [ ] [ ]


fire watch from Process/Maint./
Contractor / Fire Deptt.

20. Iron Sulphide removed/ kept wet [ ] [ ]

21. Area cordoned off [ ] [ ]

22. Precautions against public [ ] [ ]


traffic taken

23. Clearance obtained for excavation [ ] [ ]


from Technical/concerned deptts.

24.* Clearance obtained for road [ ] [ ]


cutting from Technical / Fire /
concerned deptts.

25.* Clearance obtained for dyke [ ] [ ]


cutting

26. Checked Flame / Spark arrestor [ ] [ ]


on mobile equipment

19
27. Checked for oil / gas trapped [ ] [ ]
behind lining in equipment

(White in colour)

28. Welding machine checked for [ ] [ ]


safe location

29. Check for earthing / return [ ] [ ]


connection to the equipment
being welded

30. Oxygen and Acetylene cylinders [ ] [ ]


kept outside the vessel/tank
------------------------------------------------------------------------------------------------------------------------------------------------

Note: For Items marked (*), clearance to be obtained from higher designated authority.

SPECIAL INSTRUCTIONS

1. Following personal protective equipment are required


(Check all items required) :

Safety Helmet / Gloves / Goggles / Safety Shoes / Boiler Suit /Welding Suit, Dust Respirator/Face
Shield/Face Shield/ Fresh Air Mask/Apron/Life line/Safety Belt.

2. In case of fire alarm, all work must be stopped and running fire water must be closed. All personnel must
leave work site and proceed to designated areas.

3. In case of liquid / gas release, stop work and immediately advise concerned Operation Personnel.

4. Only certified vehicles/engines and permitted type of electrical equipment and tools are allowed in operating
areas.

5. Ensure proper grounding/earthing/insulation of cables.

6. For hot tapping, ensure continuous/sufficient flow in the line.

7. This permit must be available at the work site at all times.

8. No hot work shall be permitted unless the Explosimeter reading is zero.

9. Vessel entry, where no hot work is to be carried out, may be permitted if combustible gases are up-to 5% of
lower explosive limit (LEL). Entry with an air supplied mask may be permitted with LEL of upto 50%. The
oxygen level should be at least 19.5 % vol. and the concentration of toxic gases below the threshold limits.

10. Additional remarks, if any:___________________________________________________________________

________________________________________________________________________________________

Name and__________________________ Name and __________________________

20
Signature of Receiver________________ Signature of Issuer____________________

( White in colour)

________________________________________________________________________________________________
GAS TEST(HYDROCARBON/ PERMIT ADDITIONAL
TOXIC GAS/OXYGEN EXTENDED PRECAUTIONS SIGNATURES
DEFICIENCY)DONE UPTO REQD.,IF ANY
-----------------------------------------------------------------------------------------------------------------------------------------------
DATE/ TAKEN TEST DATE/ ISSUER RECEIVER
TIME BY VALUE TIME
-----------------------------------------------------------------------------------------------------------------------------------------------
INITIAL GAS
TEST
------------------------------------------------------------------------------------------------------------------------------------------------

------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
________________________________________________________________________________________________

NOTE: HOT WORK INCLUDES WELDING, BURNING, GRINDING, SOLDERING, SAND BLASTING,
CHIPPING, RIVETING, DRILLING, CAMERA FLASHING, POWER TOOLS, IC ENGINE
OPERATIONS/ENTRY, OPEN FLAME, VEHICLE ENTRY.

AM / PM DATE
WORK COMPLETED / STOPPED / AREA CLEARED AT ________________________________________

By____________________________ By____________________________

Signature Signature

____________________________ ____________________________
(Name of Issuer) (Name of Receiver)

(PLEASE RETURN PERMIT TO ISSUER)

21
(White in colour)

TRIPLICATE

(NAME OF COMPANY)

(LOCATION)

HOT WORK/ VESSEL ENTRY/ VESSEL BOX-UP/ EXCAVATION


PERMIT

AM / PM DATE AM / PM DATE

VALID FROM_____________________________ TO__________________________________

PERMISSION IS GRANTED TO SECTION/CONTRACTOR____________________________________________

NAME_________________________________________________________________________________________

NATURE OF WORK_____________________________________________________________________________

LOCATION OF WORK___________________________________________________________________________

THE FOLLOWING ITEMS SHALL BE CHECKED BEFORE ISSUING THE PERMIT


(Please put tick [ ] mark in the appropriate box)
-----------------------------------------------------------------------------------------------------------------------------------------------
S.No. Item Done Not required
-----------------------------------------------------------------------------------------------------------------------------------------------

1. Equipment / Work Area inspected [ ] [ ]

2. Surrounding area checked/cleaned [ ] [ ]


up: oil/ rags/grass etc. removed

3. Sewers , manholes , CBD etc. and [ ] [ ]


hot surfaces nearby covered

4. Considered hazard from other [ ] [ ]


routine / non-routine operations
and concerned persons alerted

5. Equipment electrically isolated [ ] [ ]


and tagged

6. Fire water hose / Portable [ ] [ ]


extinguisher provided

7. Fire water system checked for [ ] [ ]


readiness

8. Equipment blinded/disconnected/ [ ] [ ]
closed / isolated / wedge opened

22
(White in colour)

9. Equipment properly drained / [ ] [ ]


depressurised

10. Equipment properly steamed/purged [ ] [ ]

11. Equipment water flushed [ ] [ ]

12. Gas / Oxygen deficiency test [ ] [ ]


done and found OK

13. Shield against sparks provided [ ] [ ]

14. Proper ventilation and lighting [ ] [ ]


provided

15. Proper means of exit provided [ ] [ ]

16. Precautionary tags / boards [ ] [ ]


provided

17. Portable equipment / nozzles [ ] [ ]


properly grounded

18. Standby personnel provided for [ ] [ ]


vessel entry

19. Standby personnel provided for [ ] [ ]


fire watch from Process/Maint./
Contractor / Fire Deptt.

20. Iron Sulphide removed/ kept wet [ ] [ ]

21. Area cordoned off [ ] [ ]

22. Precautions against public [ ] [ ]


traffic taken

23. Clearance obtained for excavation [ ] [ ]


from Technical/concerned deptts.

24.* Clearance obtained for road [ ] [ ]


cutting from Technical / Fire /
concerned deptts.

25.* Clearance obtained for dyke [ ] [ ]


cutting

26. Checked Flame / Spark arrestor [ ] [ ]


on mobile equipment

27. Checked for oil / gas trapped [ ] [ ]


behind lining in equipment

23
(White in colour)

28. Welding machine checked for [ ] [ ]


safe location

29. Check for earthing / return [ ] [ ]


connection to the equipment
being welded

30. Oxygen and Acetylene cylinders [ ] [ ]


kept outside the vessel/tank
------------------------------------------------------------------------------------------------------------------------------------------------

Note: For Items marked (*), clearance to be obtained from higher designated authority.

SPECIAL INSTRUCTIONS

1. Following personal protective equipment are required


(Check all items required) :

Safety Helmet / Gloves / Goggles / Safety Shoes / Boiler Suit /Welding Suit, Dust Respirator/Face
Shield/Face Shield/ Fresh Air Mask/Apron/Life line/Safety Belt.

2. In case of fire alarm, all work must be stopped and running fire water must be closed. All personnel must
leave work site and proceed to designated areas.

3. In case of liquid / gas release, stop work and immediately advise concerned Operation Personnel.

4. Only certified vehicles/engines and permitted type of electrical equipment and tools are allowed in operating
areas.

5. Ensure proper grounding/earthing/insulation of cables.

6. For hot tapping, ensure continuous/sufficient flow in the line.

7. This permit must be available at the work site at all times.

8. No hot work shall be permitted unless the Explosimeter reading is zero.

9. Vessel entry, where no hot work is to be carried out, may be permitted if combustible gases are up-to 5% of
lower explosive limit (LEL). Entry with an air supplied mask may be permitted with LEL of upto 50%. The
oxygen level should be at least 19.5 % vol. and the concentration of toxic gases below the threshold limits.

10. Additional remarks, if any:___________________________________________________________________

________________________________________________________________________________________

Name and__________________________ Name and __________________________

Signature of Receiver________________ Signature of Issuer____________________

24
(White in colour)

________________________________________________________________________________________________
GAS TEST(HYDROCARBON/ PERMIT ADDITIONAL
TOXIC GAS/OXYGEN EXTENDED PRECAUTIONS SIGNATURES
DEFICIENCY)DONE UPTO REQD.,IF ANY
-----------------------------------------------------------------------------------------------------------------------------------------------
DATE/ TAKEN TEST DATE/ ISSUER RECEIVER
TIME BY VALUE TIME
-----------------------------------------------------------------------------------------------------------------------------------------------
INITIAL GAS
TEST
------------------------------------------------------------------------------------------------------------------------------------------------

------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
________________________________________________________________________________________________

NOTE: HOT WORK INCLUDES WELDING, BURNING, GRINDING, SOLDERING, SAND BLASTING,
CHIPPING, RIVETING, DRILLING, CAMERA FLASHING, POWER TOOLS, IC ENGINE
OPERATIONS/ENTRY, OPEN FLAME, VEHICLE ENTRY.

AM / PM DATE
WORK COMPLETED / STOPPED / AREA CLEARED AT ________________________________________

By____________________________ By____________________________

Signature Signature

____________________________ ____________________________
(Name of Issuer) (Name of Receiver)

(PLEASE RETURN PERMIT TO ISSUER)

25
(White in colour)

QUADRUPLICATE

(NAME OF COMPANY)

(LOCATION)

HOT WORK/ VESSEL ENTRY/ VESSEL BOX-UP/ EXCAVATION


PERMIT

AM / PM DATE AM / PM DATE

VALID FROM_____________________________ TO__________________________________

PERMISSION IS GRANTED TO SECTION/CONTRACTOR____________________________________________

NAME_________________________________________________________________________________________

NATURE OF WORK_____________________________________________________________________________

LOCATION OF WORK___________________________________________________________________________

THE FOLLOWING ITEMS SHALL BE CHECKED BEFORE ISSUING THE PERMIT


(Please put tick [ ] mark in the appropriate box)
-----------------------------------------------------------------------------------------------------------------------------------------------
S.No. Item Done Not required
-----------------------------------------------------------------------------------------------------------------------------------------------

1. Equipment / Work Area inspected [ ] [ ]

2. Surrounding area checked/cleaned [ ] [ ]


up: oil/ rags/grass etc. removed

3. Sewers , manholes , CBD etc. and [ ] [ ]


hot surfaces nearby covered

4. Considered hazard from other [ ] [ ]


routine / non-routine operations
and concerned persons alerted

5. Equipment electrically isolated [ ] [ ]


and tagged

6. Fire water hose / Portable [ ] [ ]


extinguisher provided

7. Fire water system checked for [ ] [ ]


readiness

8. Equipment blinded/disconnected/ [ ] [ ]
closed / isolated / wedge opened

26
(White in colour)

9. Equipment properly drained / [ ] [ ]


depressurised

10. Equipment properly steamed/purged [ ] [ ]

11. Equipment water flushed [ ] [ ]

12. Gas / Oxygen deficiency test [ ] [ ]


done and found OK

13. Shield against sparks provided [ ] [ ]

14. Proper ventilation and lighting [ ] [ ]


provided

15. Proper means of exit provided [ ] [ ]

16. Precautionary tags / boards [ ] [ ]


provided

17. Portable equipment / nozzles [ ] [ ]


properly grounded

18. Standby personnel provided for [ ] [ ]


vessel entry

19. Standby personnel provided for [ ] [ ]


fire watch from Process/Maint./
Contractor / Fire Deptt.

20. Iron Sulphide removed/ kept wet [ ] [ ]

21. Area cordoned off [ ] [ ]

22. Precautions against public [ ] [ ]


traffic taken

23. Clearance obtained for excavation [ ] [ ]


from Technical/concerned deptts.

24.* Clearance obtained for road [ ] [ ]


cutting from Technical / Fire /
concerned deptts.

25.* Clearance obtained for dyke [ ] [ ]


cutting

26. Checked Flame / Spark arrestor [ ] [ ]


on mobile equipment

27. Checked for oil / gas trapped [ ] [ ]


behind lining in equipment

27
(White in colour)

28. Welding machine checked for [ ] [ ]


safe location

29. Check for earthing / return [ ] [ ]


connection to the equipment
being welded

30. Oxygen and Acetylene cylinders [ ] [ ]


kept outside the vessel/tank
------------------------------------------------------------------------------------------------------------------------------------------------

Note: For Items marked (*), clearance to be obtained from higher designated authority.

SPECIAL INSTRUCTIONS

1. Following personal protective equipment are required


(Check all items required) :

Safety Helmet / Gloves / Goggles / Safety Shoes / Boiler Suit /Welding Suit, Dust Respirator/Face
Shield/Face Shield/ Fresh Air Mask/Apron/Life line/Safety Belt.

2. In case of fire alarm, all work must be stopped and running fire water must be closed. All personnel must
leave work site and proceed to designated areas.

3. In case of liquid / gas release, stop work and immediately advise concerned Operation Personnel.

4. Only certified vehicles/engines and permitted type of electrical equipment and tools are allowed in operating
areas.

5. Ensure proper grounding/earthing/insulation of cables.

6. For hot tapping, ensure continuous/sufficient flow in the line.

7. This permit must be available at the work site at all times.

8. No hot work shall be permitted unless the Explosimeter reading is zero.

9. Vessel entry, where no hot work is to be carried out, may be permitted if combustible gases are up-to 5% of
lower explosive limit (LEL). Entry with an air supplied mask may be permitted with LEL of upto 50%. The
oxygen level should be at least 19.5 % vol. and the concentration of toxic gases below the threshold limits.

10. Additional remarks, if any:___________________________________________________________________

________________________________________________________________________________________

Name and__________________________ Name and __________________________

Signature of Receiver________________ Signature of Issuer____________________

28
(White in colour)

________________________________________________________________________________________________
GAS TEST(HYDROCARBON/ PERMIT ADDITIONAL
TOXIC GAS/OXYGEN EXTENDED PRECAUTIONS SIGNATURES
DEFICIENCY)DONE UPTO REQD.,IF ANY
-----------------------------------------------------------------------------------------------------------------------------------------------
DATE/ TAKEN TEST DATE/ ISSUER RECEIVER
TIME BY VALUE TIME
-----------------------------------------------------------------------------------------------------------------------------------------------
INITIAL GAS
TEST
------------------------------------------------------------------------------------------------------------------------------------------------

------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------------------------------------------
________________________________________________________________________________________________

NOTE: HOT WORK INCLUDES WELDING, BURNING, GRINDING, SOLDERING, SAND BLASTING,
CHIPPING, RIVETING, DRILLING, CAMERA FLASHING, POWER TOOLS, IC ENGINE
OPERATIONS/ENTRY, OPEN FLAME, VEHICLE ENTRY.

AM / PM DATE
WORK COMPLETED / STOPPED / AREA CLEARED AT ________________________________________

By____________________________ By____________________________

Signature Signature

____________________________ ____________________________
(Name of Issuer) (Name of Receiver)