001
Date
14-Jan-13
6.
Area of Concern and Corrective Action The submitted documents shall be reviewed / commentes / acknowledged by yard and vendor will move on for next step. ( Capacity, Design, etc,. ) SPCO will start procurement of HVAC equipment by week 5 / 2013. To expedite submission of engineering documents. Equipment Arrangement inside Engine Room and it's Technical Data to be Provided. Discussion shall be done as necessary. Action Required Item - 1 Item - 2 Item - 3 Item - 4 Item - 5 Action By SMSC SPCO SPCO SMSC All Remark
1 2 3 4 5
7.
Other Comments
: : : :