FRONT ELEVATION OVERVIEW

ACTIVE LEVEL (STRUCTURAL)


1 2 3 4 5 6 7 8 9 10

FORMWORKS

WETWORKS

DRYWORKS TOG

WETWORKS
ZOCALLO (T&B) PRECAST WALL DOOR JAMB INSTALLATION BOX ALIGNMENT CHB LAYING (PERIMETER WALL) RUBBED CONCRETE (EXTERIOR)

39TH

38TH

CHB LAYING (PARTITION & T&B WALL)

PLASTERING (PERIMETER)

WATERPROOFING APPLICATION (T&B) SKIMCOAT APPLICATION (PRECAST)

PLASTERING (LDK & T7B)

RUBBED CONCRETE (INTERIOR)

PUNCHLIST

37TH

PRIMER PAINT APPLICATION (EXTERIOR)

ALUMINUM DOORS & WINDOW INSTALLATION (PERIMETER) ALUMINUM DOORS & WINDOW INSTALLATION (HALLWAY)

36TH

SKIMCOAT APPLICATION (INTERIOR)

back to Front Elevation

DRYWORKS
T&B TILES MAIN DOOR HALLWAY WINDOWS PUNCHLIST (T&B) BOXSETTING/ WIRING DRYWALL,CLADDING, CEILING FRAMING SKIM COAT (T&B) LDK TILES DRYWALL CLOSURE

7 8 9 10

INTERMEDIATE PAINT

INSTALLATION OF DEVICES

BASEBOARD INSTALLATION

SPRINKLER HEADS INSTALLATION

TOG INSPECTION

back to Front Elevation

T&B Tiles Installation (DMCI)


Status Manpower: 12 Masons Productivity: 24 T&Bs per wk/ 9 days per floor Actual no. of floors from structural 9 floors Target no. of floors from structural 7 floors Floors delayed: 2 floor Reason for delayed: Manpower

back to Front Elevation

Punchlist T&B (Masonry Subcon)


Status Manpower: 2 Masons and 2 Concrete Planer Productivity: 3 T&Bs per day per subcon Actual no. of floors from structural 9 floors Target no. of floors from structural 7 floors Floors delayed: 2 floor Reason for delayed: Other Trade (T&B Tiles Installation)

back to Front Elevation

Drywall, Cladding, Ceiling Framing (Estolano)


Status Manpower: Drywall/Cladding - 6 installers T&B Ceiling 4 Installers Productivity: Drywall/Cladding 12 units per day T&B Ceiling Frame 10 t&b per day Actual no. of floors from structural 10 floors Target no. of floors from structural 7 floors Floors delayed 3 floors Reason for delayed other trades (Rubbed Concrete, Skim Coat and Ext Window)
back to Front Elevation

Main Door Installation (DMCI)


Status Manpower: 2 Carpenters Productivity: 6 Doors per day/ 7 days per floor Actual no. of floors from structural 9 floors Target no. of floors structural 8 floors Floors delayed 1 floor Reason for delayed - Manpower

back to Front Elevation

Hallway Windows (SPI)


Status Manpower: 2 installers Productivity: 12 units per day/ 2 days per floor Actual no. of floors from structural 10 floors Target no. of floors structural 8 floors Floors delayed 2 floors Reason for delayed Other Trades (Rubbed Concrete)

back to Front Elevation

Box Setting / Electrical Wiring (Anvic)


Status Manpower: 4 persons Productivity: 6 units per day/ 4 days per floor Actual no. of floors from structural 10 floors Target no. of floors structural 8 floors Floors delayed 2 floors Reason for delayed Other Trades (Hallway Windows)

back to Front Elevation

Skim Coat Application T&B Wall (JBLS)


Status Manpower: 7 groups (2 persons each) Productivity: 1 unit per 2 days/ 8 days per floor Actual no. of floors from structural 11 floors Target no. of floors structural 8 floors Floors delayed 3 floors Reason for delayed Other Trades (Masonry Punchlist)

back to Front Elevation

Tiling LDK (DMCI)


Status Manpower: 5 groups (2 tilers each, 1 solo) Productivity: 1 unit per 1.5 days/ 8 days per floor Actual no. of floors from structural 10 floors Target no. of floors structural 8 floors Floors delayed 2 floors Reason for delayed Other Trades (Masonry Punchlist)

back to Front Elevation

Drywall, Cladding and Ceiling Closure (Estolano)


Status Manpower: 20 persons (6 installers, 14 jointers ) Productivity: Drywall/ Cladding Closure 1 unit/2days Jointer 2 units/day Actual no. of floors from structural 11 floors Target no. of floors structural 8 floors Floors delayed 3 floors Reason for delayed Other Trades (Box Setting)
back to Front Elevation

Intermediate Paint (JBLS)


Actual Manpower: 10 groups ( 2 persons each) Productivity: 2.5 days per unit Actual no. of floors from structural 11 floors Target no. of floors structural 9 floors Floors delayed 2 floors Reason for delayed Other Trades

back to Front Elevation

Installation of Devices (Anvic)


Status Manpower: 4 persons Productivity: 20 units per week Actual no. of floors from structural 11 floors Target no. of floors structural 9 floors Floors delayed 2 floors Reason for delayed Other Trades (Intermediate Paint)

back to Front Elevation

Baseboard Installation (DMCI)


Status Manpower: 5 Carpenters Productivity: 20 units per week Actual no. of floors from structural 11 floors Target no. of floors structural 9 floors Floors delayed 2 floors Reason for delayed Other Trades (Intermediate Paint)

back to Front Elevation

Sprinkler Heads (Alpa)


Status Manpower: 1 Installer Productivity: 20 units per week Actual no. of floors from structural 11 floors Target no. of floors structural 9 floors Floors delayed 2 floors Reason for delayed Other Trades (Intermediate Paint)

back to Front Elevation

TOG INSPECTION
Status Productivity: 20 units per week Actual no. of floors from structural 11 floors Target no. of floors structural 10 floors Floors delayed 1 floor Total Accepted 338 units Total Balance 659 units Projected end of turnover 20 units per week - July 18, 2014
back to Front Elevation

PRECAST WALL
PRECAST WALL FABRICATION
Status : 24th floor
Manpower: 2 carpenters Productivity: 6 panels per day Gap on Structural: 4 floors

PRECAST WALL INSTALLATION


Status : 24th floor
Manpower: 2 carpenters Productivity: 5 panels per day Gap on Structural: 4 floors Target productivity: 10 panels per day Additional manpower: 2 Carpenters

back to Front Elevation

RUBBED CONCRETE (EXTERIOR)


Status: 21st Floor
Manpower: 18 mason Productivity: 10 days/floor Gap from Structural: 7 Floors Target Productivity: 8 days/Floor Additional manpower: 6 masons

back to Front Elevation

CHB LAYING (EXTERIOR)


Status: 24TH Floor
Manpower: 3 mason & 3 labor Productivity: 3 days/floor Gap from Structural: 4 Floors

back to Front Elevation

DOOR JAMB INSTALLATION


Status: 24TH Floor
Manpower: 2 Carpenters Productivity: 8 Jambs/day Gap from Structural: 4 Floors

back to Front Elevation

ZOCALLO FORMWORKS INSTALLATION (T&B)


Status: 24TH Floor
Manpower: 1 Carpenter Productivity: 4 units/day Gap from Structural: 4 Floors Target Productivity: 8 units/day Additional manpower: 1 Carpenter

back to Front Elevation

BOX ALIGNMENT
Status: 24TH Floor
Manpower: 2 PAX Productivity: 5 days/floor Gap from Structural: 4 Floors

back to Front Elevation

PLASTERING (PERIMETER WALL)


Status: 23TH Floor
Manpower: 5 Mason & 5 Labor Productivity: 2 days/floor Gap from Structural: 5 Floors

back to Front Elevation

Punchlist (Exterior)
Status: 19TH Floor
Manpower: 1 Mason (subcon) 2 masons (dmci) Productivity: 3 days/floor Gap from Structural: 9 Floors

back to Front Elevation

RUBBED CONCRETE (INTERIOR)


Status: 18TH Floor
Manpower: 24 Mason Productivity: 10 days/floor Gap from Structural: 10 Floors Target gap: 4 floors Target productivity: 7 days/floor Cause of delay: lack of manpower Additional manpower needed: 24 masons until 3rd week of January

back to Front Elevation

CHB LAYING (PARTITION & T&B)


Status: 23RD Floor
Manpower: 15 Mason & 15 Labor Productivity: 7 days/floor Gap from Structural: 5 Floors

back to Front Elevation

WATERPROOFING APPLICATION (T&B))


Status: 20TH Floor
Manpower: 3 pax Productivity: 6 days/floor Gap from Structural: 7 Floors Target Productivity: 3 days/floor Target gap: 5 floors Cause of delay: lack of manpower Additional manpower needed: 4 pax

back to Front Elevation

PLASTERING WORKS
PLASTERING (LDK)
Status : 22ND floor
Manpower: 21 Mason & 21 Labor Productivity: 7 days/floor Gap on Structural: 6 floors

PLASTERING (T&B)
Status : 19th floor
Manpower: 9 Mason & 9 Labor Productivity: 7 days/floor Gap on Structural: 9 floors Cause of Delay: Waterproofing application

back to Front Elevation

PUNCHLIST
PUNCHLIST (LDK)
Status : 17TH & 18TH floor
Manpower: 2 Mason & 2 Labor Productivity: 7 days/floor Gap on Structural: 9 floors Target Productivity: 4 days/floor Target gap: 6 floors Cause of delay: lack of manpower Additional Manpower: 1 mason & 1 labor

PUNCHLIST (T&B)
Status : 17th floor
Manpower: 3 Mason & 2 Labor Productivity: 7 days/floor Gap on Structural: 10 floors Taret Productivity: 4 days/floor Target gap: 7 floors Cause of Delay: tiling works Additional Manpower: 1 Mason & 1 Labor

back to Front Elevation

PRIMER PAINT APPLICATION (perimeter)


Status: 20TH Floor
Manpower: 1 Pax Productivity: 3 days/floor Gap from Structural: 7 Floors Target Productivity: 2 days/floor Target gap: 5 floors Cause of delay: Exterior Rubbed Concrete, punchlist

back to Front Elevation

SKIMCOAT APPLICATION (perimeter)


Status: 18TH Floor
Manpower: 1 Pax Productivity: 5 days/floor Gap from Structural: 9 Floors Target Productivity: 2 days/floor Target gap: 5 floors Cause of delay: Punchlist

back to Front Elevation

ALUMINUM DOORS & WINDOWS (perimeter)


Status: 18TH Floor
Manpower: 7 Pax Productivity: 7 days/floor Gap from Structural: 9 Floors Target Productivity: 3 days/floor Target gap: 5 floors Cause of delay: Skimcoat Application

back to Front Elevation

SKIMCOAT APPLICATION (interior)


Status: 17TH Floor
Manpower: 14 Pax Productivity: 7 days/floor Gap from Structural: 10 Floors Target Productivity: 5 days/floor Target gap: 6 floors Cause of delay: Interior rubbed Concrete, Punchlist

back to Front Elevation

ALUMINUM DOORS & WINDOWS (hallway)


Status: 17TH Floor
Manpower: 7 Pax Productivity: 7 days/floor Gap from Structural: 10 Floors Target gap: 5 floors Cause of delay: Interior Rubbed concrete, Punchlist

back to Front Elevation