Presentation Masonry & Finishing
Presentation Masonry & Finishing
FORMWORKS
WETWORKS
DRYWORKS TOG
WETWORKS
ZOCALLO (T&B) PRECAST WALL DOOR JAMB INSTALLATION BOX ALIGNMENT CHB LAYING (PERIMETER WALL) RUBBED CONCRETE (EXTERIOR)
39TH
38TH
PLASTERING (PERIMETER)
PUNCHLIST
37TH
ALUMINUM DOORS & WINDOW INSTALLATION (PERIMETER) ALUMINUM DOORS & WINDOW INSTALLATION (HALLWAY)
36TH
DRYWORKS
T&B TILES MAIN DOOR HALLWAY WINDOWS PUNCHLIST (T&B) BOXSETTING/ WIRING DRYWALL,CLADDING, CEILING FRAMING SKIM COAT (T&B) LDK TILES DRYWALL CLOSURE
7 8 9 10
INTERMEDIATE PAINT
INSTALLATION OF DEVICES
BASEBOARD INSTALLATION
TOG INSPECTION
TOG INSPECTION
Status Productivity: 20 units per week Actual no. of floors from structural 11 floors Target no. of floors structural 10 floors Floors delayed 1 floor Total Accepted 338 units Total Balance 659 units Projected end of turnover 20 units per week - July 18, 2014
back to Front Elevation
PRECAST WALL
PRECAST WALL FABRICATION
Status : 24th floor
Manpower: 2 carpenters Productivity: 6 panels per day Gap on Structural: 4 floors
BOX ALIGNMENT
Status: 24TH Floor
Manpower: 2 PAX Productivity: 5 days/floor Gap from Structural: 4 Floors
Punchlist (Exterior)
Status: 19TH Floor
Manpower: 1 Mason (subcon) 2 masons (dmci) Productivity: 3 days/floor Gap from Structural: 9 Floors
PLASTERING WORKS
PLASTERING (LDK)
Status : 22ND floor
Manpower: 21 Mason & 21 Labor Productivity: 7 days/floor Gap on Structural: 6 floors
PLASTERING (T&B)
Status : 19th floor
Manpower: 9 Mason & 9 Labor Productivity: 7 days/floor Gap on Structural: 9 floors Cause of Delay: Waterproofing application
PUNCHLIST
PUNCHLIST (LDK)
Status : 17TH & 18TH floor
Manpower: 2 Mason & 2 Labor Productivity: 7 days/floor Gap on Structural: 9 floors Target Productivity: 4 days/floor Target gap: 6 floors Cause of delay: lack of manpower Additional Manpower: 1 mason & 1 labor
PUNCHLIST (T&B)
Status : 17th floor
Manpower: 3 Mason & 2 Labor Productivity: 7 days/floor Gap on Structural: 10 floors Taret Productivity: 4 days/floor Target gap: 7 floors Cause of Delay: tiling works Additional Manpower: 1 Mason & 1 Labor