Flow Chart For Piping Works
Flow Chart For Piping Works
Flow Chart For Piping Works
THE SPOOLS WILL BE UNLOADED BY NCC. INTERNAL & EXTERNAL COATING WILL BE DONE IN NCC YARD. AFTER FINAL INSPECTION FOR COATING, IT WILL BE LOADED BY NCC
AFTER HYDROTEST, THE SPOOLS WILL BE TRANSPORTED TO NCC COATING WORKSHOP BY IMCO
AFTER NDT IS CLEARED, HYDROTEST WILL BE CARRIED OUT ON ALL SPOOLS (100% HYDROTEST) IN IMCO WORKSHOP
ONCE THE FABRICATION OF SPOOLS ARE COMPLETED, NDT WILL BE CARRIED OUT ON SPOOLS
THERE ARE NO WELDING JOINTS IN FIELD & ONLY BOLTING JOINTS ARE ALLOWED IN FIELD
ONCE THE CIVIL EXCAVATION ARE COMPLETED AND INSPECTIONS DONE, THE PIPE WILL BE LAID IN THE EXCAVATED AREA & BOLTING OF FLANGE JOINTS WILL BE DONE. AFTER, BOLT TORQUE TIGHTENING WILL BE DONE ON BOLTED JOINTS
INSPECTION NOTIFICATION WILL BE SUBMITTED TO PMC BEFORE 24 HOURS PRIOR FOR HYDROTEST
AFTER ALL BOLTING JOINTS ARE DONE IN FIELD, FIELD HYDROTEST WILL BE CARRIED OUT TO CHECK FOR ANY LEAKS
AFTER HYDROTEST ARE DONE , HOLIDAY TEST FOR COATED PIPE WILL BE INSPECTED
AFTER SUCCESSFULLY COMPLETING THE INSPECTION, THE BACKFILLING WILL BE CARRIED OUT