Professional Documents
Culture Documents
Presentation in ASSOCHAM - 290114-Slow Capacity Addition - Challenges and Way Forward
Presentation in ASSOCHAM - 290114-Slow Capacity Addition - Challenges and Way Forward
Contents
Capacity Addition Generation Capacity Addition Transmission Capacity Additoin - Distribution Power Dream gone wrong ?? Way Forward
Generation
Capacity Addition
Generation in GWs
200 132 105
Issues
Capacity addition of 54,962 MW in XI Plan, Jump of 51% in one plan Period, Private sector with a share of 42% Currently at 232 GW 12th plan targets more than 88000 MW, more than 50% to be contributed by private sector. Low interest level of investor, lenders and other stakeholders
Performance of Current Investments Power shortages coexisting with stranded power assets Coal based generation capacities rising, PLFs are falling Growth in peak demand is 27% in last 4 years compared to growth in gen by 55% Fuel Shortage, domestic coal can not support the targets, import- uncertainties Inadequate transmission capacity, not matching the generation capacities and load requirements. long term PPA is a precondition for signing FSA Regulatory risk of cancellations/de-allocations of the some of the blocks allocated to private sector looming large Approvals, clearances and Licenses 44ooo MWs of power plants stuck due to fuel or financial problems (BL 17th Dec 12). More than 15000 MW of plants stuck due to insufficient gas supply Financial health of Discoms, lenders not enthused
9th
10th
11th
Capacity Addition
Transmission
Capacity addition of 53000 Ckt Kms in XI Plan, Jump of 27% in last plan Period, Currently at 243,000 Ckt Kms 12th plan targets more than 109000 Ckt Kms line length and 2,70,000 MVA transformation capacity Layout of about $ 35 Billion, about 45% from private sector
Capacity in '000 Ckt Kms
243 190 146
Issues
9th
10th
11th
Private interest dying down, bidders fallen from 20s to 3 or 4. SBDs not reflecting the changed realities after PoC mechanism - uncertainities Assets not coming up with desired speed Despite more than 230 GW installed power, peak demand of 141 Gw, peak deficit exists of about 9%, impacting 0.4% of GDP In 2012-13, domestic power exchanges failed to execute deals of about worth Rs.1,350 Crores, amounting to 15% of total traded volume of power, due to transmission constraints. (Financial Express) Under long term PPAs, lost 1.93 billion units of generation due to transmission capacity bottlenecks (Financial Express) In resource rich states like Chattisgarh, Jindal and Sterlite plants could not despatch about 3000 MW (ET) Transmission Constraint because of a Pocket of High Demand SR, N2, N3 Transmission Constraint because of a Pocket of High Generation W3, NER
Capacity Addition
Distribution
Per Capita consumption has risen steadly over last many years. Despite problem in sector, rise in per capita is sustained in recent past due to subsidies An addition of 1.73 million circuit km of new lines at 33 kV, 11 kV and low voltage levels targeted in 12th plan.
631
733
778
818
Issues
2006
2007
2008
2009
2010
2011
2012
Inner ring is not sustainable, ISTS capacities unutilized due to lack of downstream evacuation Thumb rule - for every rupee invested in power generation, a rupee should be invested in the Transmission and Distribution (T&D) sector. Paying capacities and financial health vulnerable politics vs economics Funding by lenders not forthcoming 4 states have responded well to FRP, but many not coming forth due to terms of conditions which enforce discipline AT & C losses still in range of 26% More than 20% payments delayed more than 90 days Power cuts and backup gensets galore, 40,000 MW of such backup sets exist across India, eating into diesel subsidy of more than 5000 Crs - Ethiopia Devil is in Distribution?
Way Forward
Address the complete power supply chain, Competition and opening up left to generation only leaving out the other parts of supply chain. Regulatory and Statutory framework
Bring in the Coal Regulator to reign in the monopoly and introduce reforms Effective implementation of open access in transmission
multiple charges non-transparency regarding Available Transmission Capacity (ATC) Mis- use of Sec 11 orders by States Procedural complications
State level operations regulator to be made independent in line with POSOCO to make open access meaningful State Utilities in problem due to poor managerial and operational practices compounded by irrational tariffs fixed by regulators, regulator to be independent. Amendments in Electricity Act address the changing needs
Delay in approvals / clearances as a ground for force majeure & relief Grant of an authorization under section 164 Central Projects Status to all ISTS and ISGS for Forest Clearance Redressal mechanism for unforeseen events Key clearances & authorizations to be in place before financial bid
Level Playing Field between private developers and state owned entities Award of clearances like forest and environmental clearances
Preferential Access to Confidential Information and ability to influence bidding decisions Unfair Commercial Advantages for PSUs All projects through competitive bidding
Way Forward
Competitive bidding framework Amend SBDs to reflect the leanings Transmission an example
Benchmarking costs and tariffs while accepting bids Distribution Franchise model is emerging as a preferred model for PPP Thousands of MWs of generation, More than 100 transmission projects stuck -- Restore confidence Work on congestion management and implementation of OA in letter and spirit Manage the counter-party credit risks pertaining to state-owned distribution utilities continue to remain significantly high Need restructuring of loans for power sector projects Simplified exit norms to allow for asset churning
Transmission
National Power beltway for transmission to enable nation wide plug and play of evacuation system Integrating the states with the National Transmission System
Distribution
Bring maximum states to financial discipline Build regulatory capacity Open Access in Distribution for 1 MW and above to be implemented Separate Carriage and Content Regulator be guided by Cost and less by political considerations on tariff increase and loss reduction targets. Monitoring of FRP conditions to be tightened