INSPECTION TEST PLAN EQUIPMENT NO: PMT NO: PROJECT : DATE: 4 JANUARI 2010

H P = = HOLD (100% WITNESS) APPROVAL REQUIRED PREPARED W1 = W2 = 100% WITNESS SPOT WITNESS M =

PAGES:

1 OF 10

JOB NO: REV NO: ISSUE NO:


R/A =

EWR-A1-0166 0 0
REVIEW REPORT/ DOCUMENT/ APPROVED NOT APPLICABLE

MONITOR PROCESS/RANDOM CHECK

AR =

N/A =

NO

INSPECTION

ACCEPTANCE CRITERIA

CHARACTERISTIC TO BE VARIFIED

REPORT FORMAT

INSPECTION FREQUENCY

STATUS STS AIM

PRIOR TO WELDING 1 Documentary Review (if required) a) Welding Procedure Specification (WPS) b) Procedure Qualification Record (PQR) c) Welder Qualification Test Certificate d) Drawing 2 Material Verification a) Material Receiving Inspection (MRI) b) Visual Inspection As Per Material Specified 10% Dimensional, Appearance & Heat No. Mechanical & Chemical properties Tube size (I.D,O.D & length) Mill Certificates 10% M M R/A R/A As Per Standard ASME IX Mechanical Test Visual, Radiography Examination & Mechanical Test As Per Requirement Approved WPS Approved PQR WQT Drawing 100% 100% 100% 10% P P P R/A R/A R/A P

DURING AND AFTER WELDING 3 Welding Preparation

Approve WPS/PQR Approve Drawing ASME B31.3

Tube Details

As Per WPS As Per Drawing

100% 100% 100%

M M M

M/R/A M/R/A M/R/A

Monitoring Welding a) Welding Rod @ Electrode Approve WPS/PQR Approve WPS F No. Classification Weld Defects As Per WPS Visual Report 100% 100% R/W2 W2/M R/A R/A

Visual Inspection

NON DESTRUCTIVE TEST 6 Dye Penetrant Test (DPT) ASME Sec. V Weld Defects DPT Report 100% P R/A

HYDROTEST 7 Hydrotest Preparation a) Check Preparation b) After Hydrotest ASME B31.3 Calibration Certificate No Leak Holding Time Calibration of Pressure Gauge Leakage Pressure Test Cert. Valid Calibration Cert. Pressure Test Cert. 100% 100% 100% M M M M/R/A M/R/A M/R/A

Comment by Client (if any)

Comment by Client (if any) 0 Rev. Date Revision Description Prepared By Reviewed By Approve By

EWR-A1-0166 0 0
REVIEW REPORT/ DOCUMENT/ APPROVED NOT APPLICABLE

REMARKS

i) Approve WPS, PQR & WQT ii) Inspect & evaluate all RT report

Mill Cert. Receiving Inspection

Visual Report

DPT Report

Client (if any)

Client (if any)