UNIVERSAL TESTING LABORATORY AND INSPECTION, INC.

147 Pasig Boulevard Pasig City, Metro Manila, Philippines Office Telefax.: +63 2 671 0909/ 994 8662/ 671 1301

WORK SCHEDULE (BAR CHART)


Project : Structural Audit of Main Building, North and South Wing Buildings of the House Representatives Location : Common Wealth, Quezon City Item No. A.
1 2 3 4

Work Description Soil Improvement


Mobilization (evening) Preparation of Site Cement Grouting Demobilzation (Evening)

Work Duration ( 15 Days)


23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

5 6 7

Cement Grouting (evening) Checking Demobilzation (Evening)

8 10

Cement Grouting (evening) Demobilzation (Evening)

11 12 13

Cement Grouting (evening) Checking Demobilzation (Evening)

Prepared by:

T. S. Husmalaga Jr. Jr. Materials Engineer