SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SAUDI ARAMCO INSPECTION CHECKLIST


Pump Suction and Discharge Piping Connection
PROJECT TITLE

SAIC NUMBER

DATE APPROVED

QR NUMBER

SAIC-G-2005
WBS / BI / JO NUMBER

25-May-05

MECH-

CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) LAYOUT DRAWING NUMBER SCHEDULED INSPECTION DATE & TIME SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO INSPECTION LEVEL

EQUIPMENT DESCRIPTION REV. NO. PURCHASE ORDER NUMBER

EQPT CODE

SYSTEM ID.

PLANT NO.

EC / PMCC / MCC NO. QUANTITY INSP. MH's SPENT TRAVEL TIME

ACTUAL INSPECTION DATE & TIME SAUDI ARAMCO ACTIVITY NUMBER CONTRACTOR INSPECTION LEVEL

SAUDI ARAMCO USE ONLY


WORK PERMIT REQUIRED?

ITEM No. A.

ACCEPTANCE CRITERIA General Requirements Suction Piping shall have a straight length of pipe at least 5 times the suction nozzle diameter immediately upstream of the nozzle. Note: The above requirement does not apply to horizontal self priming pumps and vertically suspended double casing pumps. In the event of there being insufficient space to accommodate the straight length of piping immediately upstream of the pump, a specially fabricated reducer is provided for direct connection to the pump suction nozzle. This reducer is eccentric with the flat uppermost and has a taper angle not exceeding 12 degrees. Reducers in suction piping shall be of the eccentric type with the flat uppermost and shall be located upstream of the straight pipe length immediately upstream of the suction nozzle of the pump. A check valve is installed on the discharge piping of each pump. Note: Check valve is located upstream of the discharge valve. The suction piping shall be designed to prevent the formation of gas or air pockets. Sufficient venting provisions shall be included. Suction & Discharge nozzles shall be flanged, (API 610 Para. 2.3.2.1). For steel casing, the facing of finished flanges up to and including 24 inches shall be raised face for flanged rating classes 150, 300 and 600 and shall be ring joint for classes 900 and higher. Note: for 26 inches and above, flanges shall be in accordance with Standard Drawings AD-036634, AD-036991 and AD-039973 for classes 150, 300 and 600 respectively.

REFERENCE

PASS

FAIL

N/A

RE-INSP DATE

A1

SAES-G-005, Para. 5.2.3

A3

SAES-G-005, Para. 5.2.4

A4

SAES-G-005, Para. 5.2.4 SAES-G-005, Para. 5.2.6 SAES-G-005, Para. 5.2.2 31-SAMSS-004, Section 1.1.1

A5 A6 A7

A8

31-SAMSS-004, Para. 2.3.2.3

REMARKS:

REFERENCE DOCUMENTS: 1. 31-SAMSS-004 -- Centrifugal Pumps, 30 September, 2003 2. SAES-G-005 -- Centrifugal Pumps, 29 September, 2003 3. API 610 -- Centrifugal Pumps for Petroleum, Heavy Duty Chemicals, and Gas Industry Services, August 1995

Contractor / Third-Party
Construction Representative*
Work is Complete and Ready for Inspection: Name, Initials and Date: Name, Initials and Date:

Saudi Aramco
PMT Representative
T&I Witnessed QC Record Reviewed Work Verified

QC Inspector
Performed Inspection Name, Initials and Date: Work / Rework May Proceed

PID Representative
T&I Witnessed Name, Initials and Date: QC Record Reviewed Work Verified

QC Supervisor
Quality Record Approved: Name, Sign and Date: *Person Responsible for Completion of Quality Work / Test

Proponent and Others


Name, Organization, Initials and Date: T&I Witnessed QC Record Reviewed Work Verified

Y = YES

N = NO F = FAILED

Page 1 of 1