Professional Documents
Culture Documents
Billing No. 1 Up Clark
Billing No. 1 Up Clark
PERIOD
P.O. NO.
SUBCON
:
:
:
:
ITEM NO.
A
WORK DESCRIPTION
GROUND FLOOR
CHB Laying 6" & 4"
Interior Plastering (CHB Wall)
Exterior Plastering (CHB Wall)
Concrete Plastering
Concrete Topping (Finish)
Edging (Interior & Exterior)
Stiffener Columns & Lintel Beam
Concreting (Ready Mix)
Door Installation with Stiffiner Columns
Window Installation welded on Sides
Billing No. :
QTY
294.80
676.75
156.14
100.61
405.35
555.85
201.70
40.54
6
14
UNIT
sq.m
sq.m
sq.m
sq.m
sq.m
lm
lm
cu.m
pc
set
UNIT LABOR
COST
80.00
90.00
90.00
110.00
100.00
50.00
140.00
170.00
300.00
350.00
SUB-TOTAL
B
SECOND FLOOR
CHB Laying 6" & 4"
Interior Plastering (CHB Wall)
Exterior Plastering (CHB Wall)
Concrete Plastering
Concrete Topping (Finish)
Edging (Interior & Exterior)
Stiffener Columns & Lintel Beam
Door Installation with Stiffiner Columns
Window Installation welded on Sides
340.21
649.70
166.80
75.01
422.00
623.85
208.05
9
14
sq.m
sq.m
sq.m
sq.m
sq.m
lm
lm
pc
set
80.00
90.00
110.00
110.00
100.00
50.00
140.00
300.00
350.00
SUB-TOTAL
C
THIRD FLOOR
CHB Laying 6" & 4"
Interior Plastering (CHB Wall)
Exterior Plastering (CHB Wall)
Concrete Plastering
Concrete Topping (Finish)
Edging (Interior & Exterior)
Stiffener Columns & Lintel Beam
Door Installation with Stiffiner Columns
Window Installation welded on Sides
SUB-TOTAL
371.84
531.71
123.10
74.42
404.00
194.60
180.55
9
14
sq.m
sq.m
sq.m
sq.m
sq.m
lm
lm
pc
set
80.00
90.00
110.00
110.00
100.00
50.00
140.00
300.00
350.00
CONTRACT
AMOUNT
PREVIOUS
%
AMOUNT
23,584.00
60,907.50
14,052.60
11,067.10
40,535.00
27,792.50
28,238.00
6,891.80
1,800.00
4,900.00
219,768.50
27,216.80
58,473.00
18,348.00
8,251.10
42,200.00
31,192.50
29,127.00
2,700.00
4,900.00
222,408.40
29,747.20
47,853.90
13,541.00
8,186.20
40,400.00
9,730.00
25,277.00
2,700.00
4,900.00
182,335.30
ACCOMPLISHMENT
THIS PERIOD
%
AMOUNT
25.15
2.70
95.09
100.00
36.34
23.23
100.00
77.78
100.00
58.78
80.73
76.87
24.98
29.19
87.62
33.33
100.00
51.35
5,932.00
5,932.00
25,881.60
58,473.00
2,998.60
7,247.50
29,127.00
2,100.00
4,900.00
130,727.70
24,014.40
36,787.50
2,044.90
2,840.00
22,148.00
900.00
4,900.00
93,634.80
%
25.15
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2.70
95.09
100.00
0.00
36.34
0.00
23.23
100.00
77.78
100.00
58.78
80.73
76.87
0.00
24.98
0.00
29.19
87.62
33.33
100.00
51.35
TO DATE
AMOUNT
5,932.00
5,932.00
25,881.60
58,473.00
2,998.60
7,247.50
29,127.00
2,100.00
4,900.00
130,727.70
24,014.40
36,787.50
2,044.90
2,840.00
22,148.00
900.00
4,900.00
93,634.80
PROJECT
PERIOD
P.O. NO.
SUBCON
:
:
:
:
ITEM NO.
D
WORK DESCRIPTION
PARAPET WALL
CHB Laying
Plastering (Exterior)
Stiffener Columns & Lintel Beam
Edging
Billing No. :
QTY
91.80
107.10
75.00
102.00
UNIT
sq.m
sq.m
lm
lm
UNIT LABOR
COST
100.00
110.00
140.00
50.00
SUB-TOTAL
E
EXTERIOR
Concrete Plastering
114.70
SUB-TOTAL
TOTAL AMOUNT
sq.m
110.00
CONTRACT
AMOUNT
ACCOMPLISHMENT
THIS PERIOD
%
AMOUNT
PREVIOUS
%
AMOUNT
-
0.00
0.00
0.00
0.00
36,561.00
12,617.00
0.00
12,617.00
0.00
673,690.20
34.18
Sub-Contractor
Cost Engineer
Recommending Approval:
Project In-Charge
Project Manager
Approved by:
Project Foreman
230,294.50
230,294.50
23,029.45
100,000.00
107,265.05
Evaluated by:
Checked by:
TO DATE
AMOUNT
9,180.00
11,781.00
10,500.00
5,100.00
GROSS BILLING
Less: RETENTION (10%)
Less: CASH ADVANCE
NET AMOUNT DUE
Prepared by:
General Manager
34.18
230,294.50
230,294.50
23,029.45
107,265.05