BUS ASSEMBLY INSPECTION AND TEST PLAN

PROJECT NAME: APPROVALS NAME SIGNATURE DATE LEGEND: A = Action; H = Hold; W = Witness, V = Verify, N/A = not required ITEM NO. 1 ITEM DESCRIPTION Earth Connection Resistance ACCEPTANCE CRITERIA < 0.5 ohm <100 micro-ohm or manufacturers specification (minimal variation between like connections) >1000 Mohm No disruptive discharge All items completed as per design specification VERIFYING DOCUMENT SP0515C01 Delete or add items as required to comply with scope of works ACTION / INSPECTION REQUIREMENT By who? Comment ERGON ENERGY PROJECT NO: ITP NO: CUSTOMER REV:

Code

Joint Resistance

SP0515C01

Secondary Systems

3 4 5 6

Insulation Resistance HV Withstand Pre-commissioning checklist

SP0515C01 SP0515C01 SP0515C01

A A A

Secondary Systems Secondary Systems Secondary Systems

Plant Description/ Bay Number

1. Earth

Verification by Commissioning Officer of Satisfactory Completion (sign off) 2. Joint 3. Insulation 4. HV Withstand 5. Checklist Resistance Resistance

Comment 6. N/A

Check this is the latest Process Zone version before use.

Page 1 of 1
Ergon Energy Corporation Limited ABN 50 087 646 062 Ergon Energy Queensland Pty Ltd ABN 11 121 177 802

Form SP0515C03 Ver 1 Form Owner: Neil Dwyer, Manager Technical Services