WEEK 1/ MONDAY FEB 10: FIRST MEETING Analysis presentations Team defining schedule for semester WEEK 2/ MONDAY FEB 17: NO CLASS/ PRESIDENTS DAY RESCHEDULE WEEK 3/ MONDAY FEB 24: NNHS (COLLABORATIVE WORKSESSION 9-11AM) FRI FEB 28 / 9-12 Gateway Forum [faculty meeting, workshops & pin-up] DEFINING PROJECT PRINCIPLES WEEK 4/ MONDAY MARCH 3: WEEK 5/ MONDAY MARCH 10: WEEK 6/ MONDAY MARCH 17: SPRING BREAK/ NO CLASS
WEEK 7/ MONDAY MARCH 24: NNHS (INTERNAL REVIEW) WEEK 8/ MONDAY MARCH 31: WEEK 9/ MONDAY APRIL 7: FRI APR 11 / 9-12 Gateway Forum [faculty meeting, workshops and pin-up] INITIAL 3 SCHEMES: TEAM PROPOSALS (SCALES/SCOPES) WEEK 10/ MONDAY APRIL 14: NNHS (FULL CLIENT PRESENTATION)
WEEK 11/ MONDAY APRIL 21: NO CLASS/ PATRIOTS DAY RESCHEDULE WEEK 12/ MONDAY APRIL 28: WEEK 13/ MONDAY MAY 5: WEEK 14/ MONDAY MAY 12: FINAL CLIENT PRESENTATION