Professional Documents
Culture Documents
건설 용어 - 부분2
건설 용어 - 부분2
Schedule
23
Deliverable() .
Revamping
24 Work
PSV Sizing, Alarm & Trip scheduling, Operating Mannual, Rerouting Drainage, Pump
Foundation, Pipe Steep
26 BOQ
Bill of Quantity
27 Contract
28 (HEC )
, Arial, 11
JABA
31 Transmittal
Project
Deliverables
5) Engineering Cost
3) BOQ issue
4) Technical Proposal
32
- Critical Activity
- Example : Contract Award -> Basis Design -> MR -> Vendor Data -> etc.
34 Case Study
Case experience
35 Flow
Plot Plan -> ELP -> GAD -> Isometric Drawing (3D )
36 RFQ
37 Bid closing
NCC Project Bid closing Tech, Commercial Proposal
Technical Proposal
1) Engineering Procedure(Plan)
-> Plan Procedure
38
. (CJN, CJN)
2) IT ( )
14,000~15,000
39
80.5%, 10%,
Hard 3% . break down .
, Material Storage Building() .
40 Temporary Facilities
41 Start-up Assistance
Reimbursable
42
Reimbursable
Fixed Lump Sum(LSTK=Lump sum Turn Key)
Index PM , 50% .