Steel Works: Tie Beams (TB - B)

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

STEEL WORKS

TIE BEAMS (TB B)


SECTION 1 TO 5
MAIN LONGITUDINAL BARS
(4 X 15.85 X 4.4) / 6.00 = 46.493
47 pieces 20 mm x 6.00 meters
EXTRA BARS (TOP)
L1 = 2.60/4 + 0.40 +
meters
L2 = (2.60 + 3.60)/4
5.85 meters
L3 = (3.60 + 3.60)/4
6.60 meters
L4 = (3.60 + 3.60)/4
6.60 meters
L5 = 3.60/4 + 0.40 +
meters
TOTAL: 27.60 meters

L1 = 2.60/4 + 0.40 +
meters
L2 = (2.60 + 3.60)/4
5.85 meters
L3 = (3.60 + 3.60)/4
6.60 meters
L4 = (3.60 + 3.60)/4
6.60 meters
L5 = 3.60/4 + 0.40 +
meters
TOTAL: 27.60 meters

0.25 = 1.30 X 3 = 3.90


+ 0.40 = 1.95 X 3 =
+ 0.40 = 2.20 X 3 =
+ 0.40 = 2.20 X 3 =
0.25 = 1.55 X 3 = 4.65

0.25 = 1.30 X 3 = 3.90

5 pieces 20 mm x 6.00 meters

+ 0.40 = 1.95 X 3 =

EXTRA BARS (BOTTOM)


L6 = 2.60 X 0.60 = 1.56
L7 = 3.60 X 0.60 = 2.16
L8 = 3.60 X 0.60 = 2.16
L9 = 3.60 X 0.60 = 2.16
TOTAL: 8.04 meters

+ 0.40 = 2.20 X 3 =
+ 0.40 = 2.20 X 3 =
0.25 = 1.55 X 3 = 4.65

2 pieces 20 mm x 6.00 meters

5 pieces 20 mm x 6.00 meters


EXTRA BARS (BOTTOM)
L6 = 2.60 X 0.60 = 1.56
L7 = 3.60 X 0.60 = 2.16
L8 = 3.60 X 0.60 = 2.16
L9 = 3.60 X 0.60 = 2.16
TOTAL: 8.04 meters

STIRRUPS
14 pieces + 3 x 19 pieces = 71 pieces
71 pieces x 4 beams = 284
Factor: Beam Size (mm) 250 x 450
Length/Stirrup: 1.25 m
6 METER: 4 pieces
284/4 = 71 pieces
71 pieces 10 mm x 6.00 meters

2 pieces 20 mm x 6.00 meters

GRID A TO D (2B 2)

STIRRUPS
14 pieces + 3 x 19 pieces = 71 pieces
71 pieces x 4 beams = 284
Factor: Beam Size (mm) 250 x 450
Length/Stirrup: 1.25 m
6 METER: 4 pieces
284/4 = 71 pieces

MAIN LONGITUDINAL BARS


(5 X 11.85 X 4.4)/6.00 = 43.45

71 pieces 10 mm x 6.00 meters


GRID A TO D
MAIN LONGITUDINAL BARS
(5 X 11.85 X 4.4)/6.00 = 43.45
44 pieces 20 mm x 6.00 meters
EXTRA BARS (TOP)
L1 = 3.60/4 + 0.40 +
meters
L2 = (2.60 + 3.60)/4
5.85 meters
L3 = (2.60 + 3.60)/4
5.85 meters
L4 = 3.60/4 + 0.40 +
meters
TOTA: 21 meters

44 pieces 20 mm x 6.00 meters


EXTRA BARS (TOP)
L1 = 3.60/4 + 0.40 +
meters
L2 = (2.60 + 3.60)/4
5.85 meters
L3 = (2.60 + 3.60)/4
5.85 meters
L4 = 3.60/4 + 0.40 +
meters
TOTA: 21 meters

0.25 = 1.55 X 3 = 4.65


+ 0.40 = 1.95 X 3 =
+ 0.40 = 1.95 X 3 =
0.25 = 1.55 X 3 = 4.65

4 pieces 20 mm x 6.00 meters


0.25 = 1.55 X 3 = 4.65
+ 0.40 = 1.95 X 3 =
+ 0.40 = 1.95 X 3 =
0.25 = 1.55 X 3 = 4.65

4 pieces 20 mm x 6.00 meters


EXTRA BARS (BOTTOM)
L5 = 3.60 X 0.60 = 2.16
L6 = 2.60 X 0.60 = 1.56
L7 = 3.60 X 0.60 = 2.16
TOTAL: 5.88 meters

EXTRA BARS (BOTTOM)


L5 = 3.60 X 0.60 = 2.16
L6 = 2.60 X 0.60 = 1.56
L7 = 3.60 X 0.60 = 2.16
TOTAL: 5.88 meters
1 piece 20 mm x 6.00 meters
STIRRUPS
14 pieces + 2 x 19 pieces = 52 pieces
52 pieces x 5 beams = 260
Factor: Beam Size (mm) 250 x 400
Length/Stirrup: 1.25 m
6 METER: 4 pieces
260/4 = 65 pieces
65 pieces 10 mm x 6.00 meters

1 piece 20 mm x 6.00 meters


STIRRUPS
14 pieces + 2 x 19 pieces = 52 pieces
52 pieces x 5 beams = 260
Factor: Beam Size (mm) 250 x 400
Length/Stirrup: 1.25 m
6 METER: 4 pieces
260/4 = 65 pieces
65 pieces 10 mm x 6.00 meters

BEAM @ GROUND FLOOR CEILING


SECTION 1 TO 5 (2B 1)
MAIN LONGITUDINAL BARS
(4 X 15.85 X 8.8) / 6.00 = 92.99
93 pieces 20 mm x 6.00 meters
EXTRA BARS (TOP)

BEAM @ SECOND FLOOR CEILING


SECTION 1 TO 5 (3B 1)
MAIN LONGITUDINAL BARS
(4 X 15.85 X 6.6) / 6.00 = 69.74
70 pieces 20 mm x 6.00 meters
EXTRA BARS (TOP)
L1 = 2.60/4 + 0.40 +
meters
L2 = (2.60 + 3.60)/4
5.85 meters
L3 = (3.60 + 3.60)/4
6.60 meters
L4 = (3.60 + 3.60)/4
6.60 meters
L5 = 3.60/4 + 0.40 +
meters
TOTAL: 27.60 meters

0.25 = 1.30 X 3 = 3.90


+ 0.40 = 1.95 X 3 =
+ 0.40 = 2.20 X 3 =
+ 0.40 = 2.20 X 3 =
0.25 = 1.55 X 3 = 4.65

5 pieces 20 mm x 6.00 meters


EXTRA BARS (BOTTOM)
L6 = 2.60 X 0.60 = 1.56
L7 = 3.60 X 0.60 = 2.16
L8 = 3.60 X 0.60 = 2.16
L9 = 3.60 X 0.60 = 2.16
TOTAL: 8.04 meters

STIRRUPS
14 pieces + 3 x 19 pieces = 71 pieces
71 pieces x 4 beams = 284
Factor: Beam Size (mm) 200 x 250
Length/Stirrup: 0.828 m
6 METER: 7 pieces
284/7 = 40.57 pieces
41 pieces 10 mm x 6.00 meters

2 pieces 20 mm x 6.00 meters


GRID A TO D (4B 2)
STIRRUPS
14 pieces + 3 x 19 pieces = 71 pieces
71 pieces x 4 beams = 284
Factor: Beam Size (mm) 250 x 450
Length/Stirrup: 1.25 m
6 METER: 4 pieces
284/4 = 71 pieces
71 pieces 10 mm x 6.00 meters
GRID A TO D (3B 2)
MAIN LONGITUDINAL BARS
(5 X 11.85 X 4.4)/6.00 = 43.45
44 pieces 20 mm x 6.00 meters
EXTRA BARS (TOP)
L1 = 3.60/4 + 0.40 +
meters
L2 = (2.60 + 3.60)/4
5.85 meters
L3 = (2.60 + 3.60)/4
5.85 meters
L4 = 3.60/4 + 0.40 +
meters
TOTA: 21 meters

MAIN LONGITUDINAL BARS


(5 X 11.80 X 4.4)/6.00 = 43.27
44 pieces 20 mm x 6.00 meters
EXTRA BARS (TOP)
L1 = 3.65/4 + 0.60 =
meters
L2 = (6.30)/4 + 0.35
meters
L3 = (6.30)/4 + 0.35
meters
L4 = 3.65/4 + 0.60 =
meters
TOTA: 13.75 meters

1.5125 X 2 = 3.025
= 1.925 X 2 = 3.85
= 1.925 X 2 = 3.85
1.5125 X 2 = 3.025

3 pieces 20 mm x 6.00 meters


0.25 = 1.55 X 3 = 4.65
+ 0.40 = 1.95 X 3 =
+ 0.40 = 1.95 X 3 =
0.25 = 1.55 X 3 = 4.65

EXTRA BARS (BOTTOM)


L5 = 3.65 X 0.60 = 2.19
L6 = 2.65 X 0.60 = 1.59
L7 = 3.65 X 0.60 = 2.19
TOTAL: 5.97 meters
1 piece 20 mm x 6.00 meters

4 pieces 20 mm x 6.00 meters


EXTRA BARS (BOTTOM)
L5 = 3.60 X 0.60 = 2.16
L6 = 2.60 X 0.60 = 1.56
L7 = 3.60 X 0.60 = 2.16
TOTAL: 5.88 meters

STIRRUPS
14 pieces + 2 x 19 pieces = 52 pieces
52 pieces x 5 beams = 260
Factor: Beam Size (mm) 200 x 250
Length/Stirrup: 0.828 m
6 METER: 7 pieces
260/7 = 37.14 pieces
38 pieces 10 mm x 6.00 meters

1 piece 20 mm x 6.00 meters


STIRRUPS
14 pieces + 2 x 19 pieces = 52 pieces
52 pieces x 5 beams = 260
Factor: Beam Size (mm) 250 x 400
Length/Stirrup: 1.25 m
6 METER: 4 pieces
260/4 = 65 pieces
65 pieces 10 mm x 6.00 meters

BEAM @ WATER TANK CEILING


SECTION 1 TO 5 (5B 1)
MAIN LONGITUDINAL BARS
3.35 + 0.45 = 3.80 x 4 bars = 15.20 meters
15.20 meters x 2 beams = 30.40 meters
6 pieces 20 mm x 6.00 meters

SECTION 1 TO 5 (4B 1)

EXTRA BARS (TOP)


L1 = 2.65/4 + 0.60 = 1.2625
L2 = 2.65/4 + 0.60 = 1.2625
TOTAL: 2.525 meters

MAIN LONGITUDINAL BARS


3.35 + 0.45 = 3.80 x 4 bars = 15.20 meters
15.20 meters x 2 beams = 30.40 meters

EXTRA BARS (BOTTOM)


L3 = 2.65 X 0.60 = 1.19
TOTAL: 1.19 meters

6 pieces 20 mm x 6.00 meters

1 piece 20 mm x 6.00 meters

EXTRA BARS (TOP)


L1 = 2.65/4 + 0.60 =
meters
L2 = (6.30)/4 + 0.35
meters
L3 = (7.30)/4 + 0.35
meters
L4 = (7.30)/4 + 0.35
meters
L5 = 3.65/4 + 0.60 =
meters
TOTAL: 27.15 meters

STIRRUPS
14 pieces
14 pieces x 2 beams = 28
Factor: Beam Size (mm) 200 x 250
Length/Stirrup: 0.828 m
6 METER: 7 pieces
28/7 = 4 pieces

BEAM @ THIRD FLOOR CEILING

1.2625 X 3 = 3.7875
= 1.925 X 3 = 5.775
= 2.175 X 3 = 6.525
= 2.175 X 3 = 6.525

4 pieces 10 mm x 6.00 meters


1.5125 X 3 = 4.5375

5 pieces 20 mm x 6.00 meters


EXTRA BARS (BOTTOM)
L6 = 2.65 X 0.60 = 1.59
L7 = 3.65 X 0.60 = 2.19
L8 = 3.65 X 0.60 = 2.19
L9 = 3.65 X 0.60 = 2.19
TOTAL: 8.16 meters

GRID A TO D (5B 2)
MAIN LONGITUDINAL BARS
4.35 + 0.45 = 4.80 x 6 bars = 28.80 meters
28.80 meters x 2 beams = 57.60 meters
10 pieces 20 mm x 6.00 meters
EXTRA BARS (TOP)
L1 = 3.65/4 + 0.60 = 1.5125
L2 = 3.65/4 + 0.60 = 1.5125
TOTAL: 3.025 meters

2 pieces 20 mm x 6.00 meters


EXTRA BARS (BOTTOM)

L3 = 3.65 X 0.60 = 2.19


TOTAL: 1.19 meters
1 piece 20 mm x 6.00 meters
STIRRUPS
19 pieces
19 pieces x 2 beams = 38
Factor: Beam Size (mm) 200 x 250
Length/Stirrup: 0.828 m
6 METER: 7 pieces
38/7 = 4 pieces
6 pieces 10 mm x 6.00 meters

COLUMNS @ FTG. - 2ND FLR.C.LNE


MAIN VERTICAL BARS
Total No. of Columns: 20 pieces
No. and Size: 8 pieces 20 mm
Overall Length: 10.90 m + 0.45 m = 11.35 m
Total Length: 11.35 x 8 = 90.80 m
Overall Total Length: 90.80 x 20 = 1816 m
Commercial Bar Size: 6.00 m
Allowance for Splices & Wastage: 10%
1816/6.00 x 1.10 = 332.93; say
333 pieces 20 mm x 6.00 meters
STIRRUPS
Total No. of Columns: 20 0.40 m x 0.40 m
Overall Height: 10.50 m
Size of Tie Bars: 10 mm @ 0.25 m 0.C.
No. of Ties per Column: 10.50/0.25 = 42 Ties
Overall Total No. of Ties: 42 x 20 = 840
Length/Stirrup: 1.528 m
6 METER: 3 pieces
840/3 = 280
280 pieces 10 mm x 6.00 meters

COLUMNS @ 2ND FLR.C.LNE WATER


TANK C.LNE
MAIN VERTICAL BARS
Total No. of Columns: 4 pieces
No. and Size: 4 pieces 20 mm
Overall Length: 7.75 m + 0.45 m = 8.20 m
Total Length: 8.20 x 4 = 32.80 m
Overall Total Length: 32.80 x 4 = 132 m
Commercial Bar Size: 6.00 m
Allowance for Splices & Wastage: 10%
132/6.00 x 1.10 = 24.20; say
25 pieces 20 mm x 6.00 meters
STIRRUPS
Total No. of Columns: 4 0.35 m x 0.35 m
Overall Height: 7.75 m
Size of Tie Bars: 10 mm @ 0.25 m 0.C.
No. of Ties per Column: 7.75/0.25 = 31 Ties
Overall Total No. of Ties: 31 x 4 = 124
Length/Stirrup: 1.328 m
6 METER: 4 pieces
124/4 = 31
31 pieces 10 mm x 6.00 meters

COLUMNS @ 2ND FLR.C.LNE WATER


TANK C.LNE
MAIN VERTICAL BARS
Total No. of Columns: 16 pieces
No. and Size: 4 pieces 20 mm
Overall Length: 5.65 m + 0.45 m = 6.10 m
Total Length: 6.10 x 4 = 24.40 m
Overall Total Length: 24.40 x 16 = 391 m
Commercial Bar Size: 6.00 m
Allowance for Splices & Wastage: 10%
391/6.00 x 1.10 = 71.68; say
72 pieces 20 mm x 6.00 meters

STIRRUPS
Total No. of Columns: 16 0.35 m x 0.35 m
Overall Height: 5.65 m
Size of Tie Bars: 10 mm @ 0.25 m 0.C.
No. of Ties per Column: 5.65/0.25 = 23 Ties
Overall Total No. of Ties: 23 x 16 = 368
Length/Stirrup: 1.328 m
6 METER: 4 pieces
368/4 = 92
92 pieces 10 mm x 6.00 meters

SLABS

You might also like