Professional Documents
Culture Documents
Earned Value Management
Earned Value Management
Earned Value Management
Agenda
Earned Value Management
EVM Introduction Base Data Summary Data Forecast Data EVM in Practice.
Agenda
Earned Value Management
EVM Introduction Base Data Summary Data Forecast Data EVM in Practice.
EVM History
1967 1987 1997 1998 DoD Instruction Cost/Schedule control system criteria PMI recommends EVM DoD Regulation 5000.2R on EVM ANSI/EIA 748 adopts EVM.
What is EVM
Best practices focusing on process, people & tools for project tracking and control Integrates
Technical performance (status of work) Schedule performance Cost performance
Advantages of EVM
Easy to understand Low overhead Integrates cost and schedule Based on results Simplifies status reporting Reliable prediction Well proven.
Disadvantages of EVM
Doesnt address critical path Deterministic Can drive wrong behavior Doesnt account quality Cant handle management reserves Doesnt reveal the cause.
Type Of Data
Base Data
Data ONLY for the current period
Summary Data
Derived data based on the base data Rolled-up data till date Indicates the current health of the project
Forecast Data
Project forecast/estimate based on summary data.
Agenda
Earned Value Management
EVM Introduction Base Data Summary Data Forecast Data EVM in Practice.
Base Data
Total Budget (BAC)
Total planned value for the project
Base Data
Actual Cost (AC)
Actual effort/cost incurred on all tasks completed during the period
Base Data
Assume today is 22nd Feb; Task A, B, C, D are complete, E is in-progress, and F not yet started
Task A B C D E F Total Schedule Date 1-Feb-2008 5-Feb-2008 10-Feb-2008 15-Feb-2008 20-Feb-2008 25-feb-2008 PV 5 10 5 10 5 10 EV AC TS 5 14 7 13 3*
Agenda
Earned Value Management
EVM Introduction Base Data Summary Data Forecast Data EVM in Practice.
Summary Data
Cost Variance (CV)
Difference between Earned Value and Actual Cost i.e. EV AC
Summary Data
Schedule Variance (SV)
Difference between Earned Value and Planned Value i.e. EV PV
Summary Data
Assume today is 22nd Feb; Task A, B, C, D are complete; E is in-progress, F not yet started
Task A B C D E F Total PV EV AC TS CV CPI SV SPI
5 10 5 10 5 10
5 14 7 13 3*
Agenda
Earned Value Management
EVM Introduction Base Data Summary Data Forecast Data EVM in Practice.
Forecast Data
Estimate To Complete (ETC)
Estimated effort/cost to complete all pending scheduled tasks Project ETC
Team's estimate of effort/cost required to complete all scheduled tasks (valid when earlier estimations are no longer valid)
Statistical ETC
ETC = (BAC EV) assuming similar variance will not occur in future ETC = (BAC-EV)/CPI assuming similar variance will occur in future.
Forecast Data
Estimate At Completion (EAC)
Estimated effort/cost incurred to complete all scheduled tasks Project EAC
Team's estimate of total effort/cost to complete all scheduled tasks Project EAC = Total Spent + Project ETC
Statistical EAC
EAC = Actual Cost + (BAC-EV) EAC = Actual Cost + (BAC-EV)/CPI.
Forecast Data
Variance At Completion (VAC)
Forecasted variance between Total Budget and Estimate At Completion Project VAC
Team's forecasts of difference between budgeted and actual cost for all tasks Project VAC = Total Budget - Project EAC
Statistical VAC
Statistical VAC = Total Budget - Statistical EAC.
Forecast Data
To Complete Performance Index (TCPI)
Forecasts how efficient the project team needs to be to complete the project on budget TCPI = (Total Budget Earned Value) _________________________ (Total Budget Actual Cost)
Forecast Data
Assume today is 22nd Feb; Task A, B, C, D are complete; E is in-progress, F not yet started
Task A B C D E F Total PV AC CPI SPI ETC EAC VAC TCP I
5 10 5 10 5 10
5 14 7 13 3*
Agenda
Earned Value Management
EVM Introduction Base Data Summary Data Forecast Data EVM in Practice.
Report performance